IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Wapsipinicon State Park | Date: 8/17/2023 | Project No. |
Culvert and Bridge Repair | County: | JONES | Time: 11:00 a.m. | 18-06-53-04 |
![]() | 1 | 2 | 3 | ![]() | |||||||||
Estimated Cost: $74,000.00 | Contractor: | ![]() | Connolly Excavating Inc | Connolly Construction Inc | Boomerang Corp of Iowa | ![]() | |||||||
Funding Source: 100% Park & Institutional Road Fund, | ![]() | PO Box 942 | ![]() | 18409 N Cascade Rd | ![]() | 13225 Circle Drive Suite A PO Box 227 | ![]() | ||||||
![]() | Cascade IA 52033 | ![]() | Peosta IA 52067 | ![]() | Anamosa IA 52205 | ![]() | |||||||
Plan Sets Requested: 0 | Quantities | ![]() | 563-513-9772 | ![]() | 563-876-3225 | ![]() | 319-462-4435 | ![]() | |||||
No. | Description: | No. | Unit | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() | Unit Price | Amount | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
1 | Mobilization | 1 | L.S. | ![]() | $9,500.00 | $9,500.00 | ![]() | $7,200.00 | $7,200.00 | ![]() | $40,000.00 | $40,000.00 | ![]() |
2 | 2012-Excavation, CL12, Boulder/Rock Fragment | 50 | C.Y. | ![]() | $285.00 | $14,250.00 | ![]() | $176.00 | $8,800.00 | ![]() | $50.00 | $2,500.00 | ![]() |
3 | 2104-Excavation, CL13, Channel | 50 | C.Y. | ![]() | $275.00 | $13,750.00 | ![]() | $85.00 | $4,250.00 | ![]() | $50.00 | $2,500.00 | ![]() |
4 | 2507-Concrete Grout-Revetment | 10 | C.Y. | ![]() | $505.00 | $5,050.00 | ![]() | $400.00 | $4,000.00 | ![]() | $285.00 | $2,850.00 | ![]() |
5 | 2507-Revetment, Class E | 176 | Tons | ![]() | $55.00 | $9,680.00 | ![]() | $60.00 | $10,560.00 | ![]() | $80.00 | $14,080.00 | ![]() |
6 | 2507-Erosion Stone | 50 | Tons | ![]() | $55.00 | $2,750.00 | ![]() | $51.00 | $2,550.00 | ![]() | $50.00 | $2,500.00 | ![]() |
7 | 2518-Safety Closure | 2 | Each | ![]() | $1,500.00 | $3,000.00 | ![]() | $325.00 | $650.00 | ![]() | $100.00 | $200.00 | ![]() |
8 | 2528-Traffic Control | 1 | L.S. | ![]() | $2,500.00 | $2,500.00 | ![]() | $1,600.00 | $1,600.00 | ![]() | $100.00 | $100.00 | ![]() |
9 | Culvert Clean-out | 90 | L.F. | ![]() | $175.00 | $15,750.00 | ![]() | $265.00 | $23,850.00 | ![]() | $100.00 | $9,000.00 | ![]() |
10 | Turret Grouting | 1 | L.S. | ![]() | $9,650.00 | $9,650.00 | ![]() | $27,500.00 | $27,500.00 | ![]() | $40,000.00 | $40,000.00 | ![]() |
11 | Bridge Cleaning and Vegetation Removal | 1 | L.S. | ![]() | $10,000.00 | $10,000.00 | ![]() | $6,000.00 | $6,000.00 | ![]() | $28,000.00 | $28,000.00 | ![]() |
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
$95,880.00 | ![]() | $96,960.00 | ![]() | $141,730.00 | ![]() | ||||||||
![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() | ![]() |
7/27/2024