The following are the results of bids received February, 2024 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| DICKINSON -- PROJECT # 22-01-30-06 2/22/2024 Large Project Letting
| SPIRIT LAKE HATCHERY
| ROAD MAINTENANCE | | BIDS RECEIVED: |
Beck Excavating Inc
|
$89,265.90 |
|
| JONES -- PROJECT # 23-06-53-01 2/22/2024 Large Project Letting
| WAPSIPINICON STATE PARK
| FEMA FLOOD REPAIRS | | BIDS RECEIVED: |
Top Grade Excavating Inc
|
$357,296.25 |
Shift Companies
|
$389,515.00 |
Aaron Crane Construction LLC
|
$401,714.00 |
Connolly Construction Inc
|
$511,239.80 |
Miller Trucking & Excavating Co
|
$545,374.50 |
B & J Hauling & Excavating Inc
|
$592,685.00 |
RW Excavating Solutions LC
|
$614,808.00 |
Boomerang Corp of Iowa
|
$617,936.00 |
Newt Marine Services
|
$687,860.00 |
Legacy Corporation of IL
|
$770,359.50 |
|
| BUTLER -- PROJECT # 23-03-12-01 2/22/2024 Small Project Letting
| BIG MARSH WILDLIFE MANAGEMENT AREA
| LUNDIE WETLAND-SHALLOW WATER EXCAVATION | | BIDS RECEIVED: |
Cook Construction of Iowa LLC
|
$14,820.00 |
Aaron Crane Construction LLC
|
$17,720.00 |
Blumer Excavating Co LLC
|
$18,540.00 |
Chad Heim Excavating & Trucking LLC
|
$19,338.00 |
Matt Construction Inc
|
$19,714.80 |
M & S Dirtwork
|
$19,960.80 |
Ludovissy Enterprises
|
$21,370.00 |
Cole Excavating LLC
|
$23,090.00 |
Empire Excavation
|
$24,534.00 |
Connolly Excavating Inc
|
$24,644.00 |
Lahr Custom Excavating LLC
|
$24,980.00 |
Dig It Land Improvements
|
$26,420.00 |
K & M Enterprise LLC
|
$44,600.00 |
Eckard Construction LLC
|
$54,060.00 |
|
| CERRO GORDO -- PROJECT # 23-03-17-07 2/22/2024 Small Project Letting
| MCINTOSH WOODS STATE PARK
| SHELTER ROOF REPLACEMENTS (REBID) | | BIDS RECEIVED: |
PG Customs
|
$38,800.00 |
Larson Contracting Central
|
$41,227.80 |
|
| JACKSON -- PROJECT # 24-06-49-02 2/22/2024 Small Project Letting
| MAQUOKETA CAVES
| SEWER IMPROVEMENTS | | BIDS RECEIVED: |
Offset Construction LLC
|
$45,667.50 |
Connolly Construction Inc
|
$51,352.50 |
Connolly Excavating Inc
|
$57,790.00 |
Tschiggfrie Excavating Co
|
$66,074.00 |
F. L. Krapfl, Inc
|
$68,610.00 |
Boomerang Corp of Iowa
|
$73,127.50 |
Top Grade Excavating Inc
|
$73,591.50 |
Miller Trucking & Excavating Co
|
$115,260.00 |
|
| JONES -- PROJECT # 23-06-53-02 2/29/2024 Small Project Letting
| WAPSIPINICON & PALISADE-KEPLER STATE PARK
| FUEL TANK REPLACEMENT | | BIDS RECEIVED: |
Connolly Construction Inc
|
$44,888.00 |
Haworth Land Construction
|
$47,700.00 |
Kupka Excavating & Trucking
|
$47,916.00 |
F. L. Krapfl, Inc
|
$48,960.00 |
Connolly Excavating Inc
|
$59,180.00 |
Acterra Group LLC
|
$94,165.00 |
|
|