PROJECTS LETTING -  February , 2024

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

BUTLER 23-03-12-01 Big Marsh Wildlife Management Area - Lundie Wetland-Shallow Water Excavation-2024-02-22   Bid Completion detail
CERRO GORDO 23-03-17-07 McIntosh Woods State Park - Shelter Roof Replacements (REBID)-2024-02-22   Bid Completion detail
DICKINSON 22-01-30-06 Spirit Lake Hatchery - Road Maintenance-2024-02-22   Bid Completion detail
JACKSON 24-06-49-02 Maquoketa Caves - Sewer improvements-2024-02-22   Bid Completion detail
JONES 23-06-53-01 Wapsipinicon State Park - FEMA Flood Repairs-2024-02-22   Bid Completion detail
MONONA 21-01-67-05 Lewis and Clark State Park - Visitor Center Water Mitigation-2024-02-22   Bid Completion detail
JONES 23-06-53-02 Wapsipinicon & Palisade-Kepler State Park - Fuel Tank Replacement -2024-02-29   Bid Completion detail




DICKINSON -- PROJECT # 22-01-30-06                2/22/2024                Large Project Letting
SPIRIT LAKE HATCHERY
ROAD MAINTENANCE
Proposal Guarantee: $6,250
Completion Date: 9/15/2024

   This project consists of grading and placing rock on approximately 0.35 miles rock roads, parking lots, and shoulders. Patching, cleaning and filling cracks and fog sealing approximately 0.3 mile of HMA pavement and parking lots of varying widths.

ESTIMATED QUANTITIES:
    Asphalt Emulsion-Fog Seal (Pavement)     275 GAL.
    Patch, Full-Depth Finish, 6-inch, By Area, HMA     105.6 S.Y.
    Patch, Full-Depth Finish, 6-inch, By Count, HMA     4 Each
    Subbase (Patch)     17.7 C.Y.
    Transverse Joint Repair     24 Tons
    Longitudinal Joint Repair (HMA)     150 L.F.
    Cleaning and Filling Cracks (HMA Surfaces)     0.5 MI.
    Sealer Material (HMA Surfaces)     250 LB.
    Slurry Level     0.5 MI.
    Safety Closure     4 Each
    Painted Pavement Marking, High-Build Waterborne     15 STA.
    Painted Symbol+Legend, High-Build Waterborne     2 Each
    Signing     1 Each
    Reconstruction of Roadbed - Blading/Shaping     19.8 STA.
    Granular Shoulder, Type B     2.2 Tons
    Granular Surface, Class A Crushed Stone     428 Tons
    Traffic Control     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JONES -- PROJECT # 23-06-53-01                2/22/2024                Large Project Letting
WAPSIPINICON STATE PARK
FEMA FLOOD REPAIRS
Proposal Guarantee: $25,000
Completion Date: 9/27/2024

   Project includes constructing 18 weirs in the Wapsipinicon River with 450 large boulders and other revetment stone, also includes a bank repair at Dutch Creek.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Construction Survey     1 L.S.
    Clearing and Grubbing     0.75 Acres
    Large Boulders     900 Each
    Revetment, Class B     540 Tons
    Rock, 6" Minus     270 Tons
    Engineering Fabric     68 S.Y.
    Revetment, Class E     80 Tons
    Site Restoration     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




MONONA -- PROJECT # 21-01-67-05                2/22/2024                Large Project Letting
LEWIS AND CLARK STATE PARK
VISITOR CENTER WATER MITIGATION
Proposal Guarantee: $4,000
Completion Date: 6/30/2024

   Lewis and Clark State Park has a Visitor Center built in 2009, the north side of the building leaks water through a side-wall pipe entrance. The side door area and sidewalk is heaved and in need of replacement. This project will waterproof the incoming pipe, install new subgrade drain pipes and backfill, and concrete sidewalks and stoop footings.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Demolition and Excavation     1 L.S.
    Pipe Caulking     1 L.S.
    4" Perforated Drain Tile     140 L.F.
    6" Dual Wall Pipe     190 L.F.
    8" Dual Wall Pipe     40 L.F.
    HDPE Pipe Fitting     1 L.S.
    Pea Gravel Backfill     100 C.Y.
    EPDM Membrane and Filter Fabric     1 L.S.
    5" PCC Sidewalk and Subbase     55 S.Y.
    Site Restoration     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BUTLER -- PROJECT # 23-03-12-01                2/22/2024                Small Project Letting
BIG MARSH WILDLIFE MANAGEMENT AREA
LUNDIE WETLAND-SHALLOW WATER EXCAVATION
Proposal Guarantee:
Completion Date: 6/15/2024

   Project consists of shallow water excavation of a wetland

Contact:
Kenneth Howe
319-240-3553
Kenneth.howe@dnr.iowa.gov




CERRO GORDO -- PROJECT # 23-03-17-07                2/22/2024                Small Project Letting
MCINTOSH WOODS STATE PARK
SHELTER ROOF REPLACEMENTS (REBID)
Proposal Guarantee: $0
Completion Date: 6/30/2024

   McIntosh Woods State Park has a Shelter and Fish Cleaning Shelter, and Ventura Access also has a shelter. All of these structures are in need of a new roof. This project will include removing all existing roofing, new fascia boards, and new steel roofing and underlayment on the structures. The Fish Cleaning Shelter will have its skylights removed and filled-in. Ventura Access and Fish Cleaning Shelter shall be part of the base bid and McIntosh Woods Shelter as an alternate.

Contact:
Kenneth Howe
319-240-3553
Kenneth.howe@dnr.iowa.gov




JACKSON -- PROJECT # 24-06-49-02                2/22/2024                Small Project Letting
MAQUOKETA CAVES
SEWER IMPROVEMENTS
Proposal Guarantee:
Completion Date: 5/1/2024

   Project includes replacing two air release valves in a sanitary sewer for main, installing two 1,500 gallon septic tanks, jetting 2070 LF of sewer pipe, and widening access road.

Contact:
Mark Moeller
515-214-9532
mark.moeller@dnr.iowa.gov




JONES -- PROJECT # 23-06-53-02                2/29/2024                Small Project Letting
WAPSIPINICON & PALISADE-KEPLER STATE PARK
FUEL TANK REPLACEMENT
Proposal Guarantee:
Completion Date: 10/31/2024

   Project includes replacing existing fuel tanks at Palisades-Kepler State Park and Wapsipinicon State Park.

Contact:
Mark Moeller
515-214-9532
mark.moeller@dnr.iowa.gov