Field Office Compliance - Field Activity - 104454


Ginger West Data Center - 11100 Booneville Rd - 401154636
11100 Booneville Road West Des Moines, IA 50266
Dallas County

FO 5

Activity Report
Document Name Type File Date Note
25-17-008_FO5_062326_01.pdf
Inspection Report (public)
06/15/2026
File Name File Type File Date Note
Comments
6/23/2026 Reminders: • Notify the Iowa DNR of the actual start of construction, installation, or alteration and the actual start of operation following the issuance of an air permit. The notices must be submitted via Iowa EASY Air within 30 days of the start of construction or 15 days of the start of operation. [567 IAC 22.3(3)b] • Condition 10A of the construction permits specifies that the permit or amendment shall become void if the construction or implementation of the proposed project is not initiated within 18 months or not completed within 36 months after the permit issuance date. BRYAN BUNTON
Compliance Tracking
Action Type Date Completed Date Comment Delete