Field Office Compliance - Desktop Activity


Desk Action ID - 167378
Osage City Of Stp - 310651768
1990 357TH ST Osage, IA 50461-0029
Mitchell County

FO 2

Activity Report
Document Name Type File Date Note
City of Osage (2023-05-25) LNC Failure to Meet Compliance Schedule Milestone.pdf
Letter (public)
05/25/2023 City of Osage (2023-05-25) LNC Failure to Meet Compliance Schedule Milestone
City of Osage LNC response from SEH Tom Madden 2023-06-22.pdf
Letter (public)
05/25/2023 City of Osage LNC response from SEH Tom Madden 2023-06-22
State of Iowa Mail - Osage Notice of Non-compliance 2023-06-22.pdf
Letter (public)
05/25/2023 State of Iowa Mail - Osage Notice of Non-compliance 2023-06-22
File Name File Type File Date Note
Comments
6/22/2023 Received a response letter to the LNC for compliance Schedule Milestone. Mr. Madden also provided DNR with an update in regards to the copper compliance schedule, stating that as of this date (date of the letter June 20, 2023), the City has obtained DNR construction permits for addition of polyphosphate to the drinking water system, and the City has ordered and received the chemical feed equipment and is in the process of scheduling the installation. Once installed, the effect of adding the polyphosphate should be noticeable at the WW treatment facility within 30 days at which time he would provide another project update to the Department. ISAIAH LARY
5/25/2023 Issued LNC for Failure to Meet Compliance Schedule Milestone ISAIAH LARY
Compliance Tracking
Action Type Date Completed Date Comment Delete