Comments
6/11/2010 On June 7, 2010 at 2:00 PM I received a call from Doug Chabino with Magellan Midstream Partners regarding the letter (dated June 2, 2010) I sent as a follow up to the meeting on April 29, 2010. Doug wanted to talk about the recommendations I put in the letter. He said they were developing a program of identifying and addressing high risk areas of underground piping at the site. This would include areas with known dead legs, low velocity or low volume lines, or lines that had evidence of internal corrosion (based on corrosion studies done on the lines at the site). Doug wasn't sure they could or needed to make all underground lines at the site where they could be pigged. He said their program of corrosion protection (cathodic protection of lines), assessment, and anti corrosion additives should be sufficient. Doug did mention that they were looking at replacing all of the underground lines that supply the truck loading rack and he thought there would be sufficient flow through these lines to prevent areas of sediment deposition. Doug said he would send a letter outlining their plans for a corrosion prevention program. I said I thought that a letter was a good idea and I would respond back in writing after reviewing his letter. BILL GIBBONS
6/2/2010 On April 29, 2010 at 1:30 PM there was a meeting at the Magellan Des Moines Terminal to discuss the corrosion protection program. Steve Steward (Area Supervisor for Magellan) called for the meeting because of my question about how much underground piping there was at the Des Moines Terminal and what was done in terms of corrosion protection for underground piping. These questions came up because of recent releases at the terminal on February 11, 2008, March 2, 2010 and April 16, 2010. In all three cases the release was a result of internal corrosion in underground piping that was conveying product. Steve Stewerd called in Doug Chabino – Manager Asset Integrity Engineering, and Rick Werner – Sr. Corrosion Technologist, to discuss the corrosion protection program at this terminal and other Magellan facilities. Also in attendance were Rodger Teasdale (Magellan), Tristan Grover (Magellan), and Dave Hruby with Apex Environmental (see attached letter dated June 2, 2010 for full description of meeting and recommendations). BILL GIBBONS
Compliance Tracking
Action Type Date Completed Date Comment Delete