Field Office Compliance - Field Activity - 97617


Hog Haven - 310695015
2075 G Avenue Red Oak, IA 51566
Montgomery County

FO 4

Activity Report
Document Name Type File Date Note
RedOak022525.afo.HogHaven.basinletter.baker.pdf
Inspection Report (public)
02/25/2025 Basin Inspection
59895_FO4_051425_01.pdf
Facility Response (public)
02/25/2025 Basin Repair Plans
59895_FO4_121525_02.pdf
Inspection Report (public)
02/25/2025 Basin Closure
File Name File Type File Date Note
Comments
5/14/2025 On May 13, 2025, Jeremy Clark contacted FO4 to let us know that closure had been completed. I followed up later that day to document that proper closure had been completed. At this time, the basin is considered closed, and no further action is needed. JOHN BAKER
5/14/2025 On April 29, 2025, Jeremy Calrk with ESB Clark Heavy Construction, called to say that the facility had planned to close the basin instead of repair it and that closure was going to begin later that day. JOHN BAKER
5/14/2025 On April 27, 2025, FO4 received plans for basin repairs at this facility. JOHN BAKER
4/25/2025 On April 25, 2025, Jeremy Clark with ESB Clark Heavy Construction, called me to discuss the requirements for the basin at the Hog Haven Site. At this time, I still have not received any plan of closure or repairs. JOHN BAKER
4/25/2025 On April 15, I contacted the owner to get an update on the site. At that time, I was unable to reach them. JOHN BAKER
3/7/2025 Submit a plan of action KRISTI BURG
3/4/2025 A plan of action for this facility must be sent to Field Office 4 by April 1, 2025. The plan of action must state the plans for this facility to include a date of completion for either removal of the basin if ceasing operations or repairs to the basin if staying in operation. JOHN BAKER
Compliance Tracking
Action Type Date Completed Date Comment Delete
"
"