Field Office Compliance - Field Activity - 82516


Eagle Iron Works - 310618472
129 E. HOLCOMB AVE. Des Moines, IA 50304
Polk County

FO 5

Activity Report
Document Name Type File Date Note
Eagle Iron Works DM no exposure certification.pdf
Inspection Report (public)
10/27/2021 120921 No exposure certification
File Name File Type File Date Note
Comments
12/14/2021 Re: NPDES GP #1 Inbox Lasnek, Mark 4:09 PM (16 minutes ago) to me The no-exposure has been entered and the authorization has been discontinued. Thanks! JANET GASTINEAU
12/9/2021 see attached JANET GASTINEAU
12/9/2021 RE: NPDES GP #1 External Inbox Matt Kinter Attachments 3:21 PM (17 minutes ago) to me, Jasen Good Afternoon, The stormwater no exposure certificate has been mailed to the stormwater coordinator at the DNR address. I’ve also attached a copy to this email. Thanks, Matt Kinter From: Gastineau, Janet <[email protected]> Sent: Tuesday, December 7, 2021 10:03 AM To: Matt Kinter <[email protected]> Cc: Jasen Hammer <[email protected]> Subject: Re: NPDES GP #1 Do you know what the status of your efforts is to achieve compliance? The last I heard was from Evora about submitting a no exposure certificate, but I have not received it. On Tue, Nov 2, 2021 at 4:42 PM Gastineau, Janet <[email protected]> wrote: No problem. I understand it may take some time as the Des Moines facility navigates some transition. On Tue, Nov 2, 2021 at 12:35 PM Matt Kinter <[email protected]> wrote: Hi Janet, I haven’t ignored this request, I’m just familiarizing myself with the facility out there in Des Moines and getting access to the files that the facility manager had before he left the company. Thanks, Matt Kinter Safety Manager [email protected] JANET GASTINEAU
12/7/2021 Gastineau, Janet <[email protected]> Mon, Dec 6, 8:53 AM (1 day ago) to Kevin Did this get done? I have not seen a copy. On Fri, Nov 5, 2021 at 12:31 PM Gastineau, Janet <[email protected]> wrote: Completion of the no exposure certification and notice of discontinuance should resolve the issue. On Fri, Nov 5, 2021 at 11:05 AM Kevin Jensen <[email protected]> wrote: Hi Janet, A representative from Eagle Iron Works reached out to me based on your contact with them about their expired stormwater permit coverage and other items you wanted to review. After talking with him, it sounds like they have rearranged and covered their operations so as not to have materials or activities exposed to stormwater. Since I am not aware of much of the history here, I am checking to see if they would be able to certify their eligibility under the no-exposure certification and submit an NOD assuming the items in Section C are all “No’s” and then have their permit rescinded? If there are other circumstances requiring them to be permitted, please let me know. JANET GASTINEAU
12/7/2021 Re: NPDES GP #1 Gastineau, Janet <[email protected]> 9:03 AM (0 minutes ago) to Matt, jasenhammer Do you know what the status of your efforts is to achieve compliance? The last I heard was from Evora about submitting a no exposure certificate, but I have not received it. On Tue, Nov 2, 2021 at 4:42 PM Gastineau, Janet <[email protected]> wrote: No problem. I understand it may take some time as the Des Moines facility navigates some transition. On Tue, Nov 2, 2021 at 12:35 PM Matt Kinter <[email protected]> wrote: Hi Janet, I haven’t ignored this request, I’m just familiarizing myself with the facility out there in Des Moines and getting access to the files that the facility manager had before he left the company. JANET GASTINEAU
10/27/2021 I called to schedule an inspection but learned the individual responsible for this put in his notice last week and is no longer working for EIW. As they are in transition I told Jasen that he could pull it together and/or work with corporate on their GP1 status, so I sent the following email. Generally speaking he didn't have a clue what this was or who will be taking care of these duties. He'll get back to me. JANET GASTINEAU
10/27/2021 RE: NPDES GP #1 External Inbox Jasen Hammer 2:11 PM (2 minutes ago) to me Received, thank you! From: Gastineau, Janet <[email protected]> Sent: Wednesday, October 27, 2021 12:58 PM To: Jasen Hammer <[email protected]> Subject: NPDES GP #1 Please refer to this link to see what permit I am interested in inspecting your facility to determine its compliance status https://programs.iowadnr.gov/stormwater/pages/activityLog.aspx?permitID=2420. Currently, the authorization for discharge of stormwater has expired. The renewal reminder is attached; one was also transmitted to Gary in August 2020. Information I need to review to determine your facility's compliance status includes, but is not limited to, the following: A copy of the Pollution Prevention Plan, including signature according to Part VI.G of the permit. Description of potential pollutant sources Description of stormwater management controls (including employee training) Records of visual inspection (no less than 1/year) Records retention: Storm water permit, monitoring records, copies of all reports required by the permit, and records of all data used to prepare the NOI must be retained on site for at least 3 years.Storm water permit, monitoring records, copies of all reports required by the permit, and records of all data used to prepare the NOI must be retained on site for at least 3 years. The permit itself is attached and this link to an EPA fact sheet might help https://www.epa.gov/sites/default/files/2015-10/documents/sector_f_primarymetals.pdf. JANET GASTINEAU
Compliance Tracking
Action Type Date Completed Date Comment Delete