Field Office Compliance - Field Activity - 76187


SAPP BROS TRAVEL CENTERS - 310335492
2496 210TH AVE Percival, IA 51648
Fremont County

FO 4

Activity Report
Document Name Type File Date Note
percival042820.ww.sappbrostravelcenterwastewaterinspectionreport.wittrock.pdf
Inspection Report (public)
05/04/2020 nov
File Name File Type File Date Note
Comments
11/4/2024 Text message from Eric Cherko on 11/2/24: I go ahold of the contractor. They have the flow meter in their possession. I'm giving them a deadline to install or purchase and have another company install. KRISTI BURG
10/29/2024 Text message from Eric Cherko 10/29/24. Contractor ordered the meter but then stopped answering my calls and I didn't pursue it. I'll have to get the ball rolling again. Let me make some calls. KRISTI BURG
8/2/2022 Suspense date changed to September 30, 2022. Eric Cherko contacted FO4 and stated that the flow meter had been received by the contractor and the contractor was working on scheduling the work to be completed in the next month. WENDY WITTROCK
2/7/2022 Received an email from E Cherko regarding the delay in the installation of the flow meter. The suspense date has been delayed until June 1, 2022. eric cherko <[email protected]> Fri, Feb 4, 2022 at 2:19 PM To: "Wittrock, Wendy" <[email protected]> Wendy, I wanted to update you on my progress for the wastewater effluent meter. The contractor I had been working with has become unresponsive. I have no idea why they would go through the trouble of a joint call and site visit if not they did not intend to do the project, but I have had to move on. I have another contractor lined up who has done work for I29 Hwy 2 SID before. I am also working with a Sensus rep to get the appropriate meter for this application. They are saying the type of meter we had been looking at that sits outside the pipe and induces flow is not suitable for the material our effluent piping is constructed of. When I get more details on the final plan I will forward it to you before we start the project. WENDY WITTROCK
8/23/2021 Request by Eric Cherko to extend the suspense date another 45 days for the installation on the flow meter. Extension approved. Mr. Cherko is working with DNR and consultants to plan for the installation of the new flowmeter. WENDY WITTROCK
6/15/2021 eric cherko 1:10 PM (12 minutes ago) to me Wendy, We have enlisted the help of an engineer, TD2, as I was not getting anywhere on the effluent flow measurement project. With the July 1st deadline approaching, I was hoping to get another extension to September 1st. Request approved. Suspense date changed to September 1, 2021. WENDY WITTROCK
5/8/2020 flow meter must be installed to accurately determine flow being processed through Sapp Bros Travel Center ww system RHONDA PAHL
5/8/2020 submit plan of action to address the exceedances and how you plan to meet your permit limits RHONDA PAHL
5/4/2020 Notice of Violation issued for permit conditions not being met as the facility was not measuring effluent flow. WENDY WITTROCK
Compliance Tracking
Action Type Date Completed Date Comment Delete