Field Office Compliance - Assistance


Assistance ID - 88728
IPL - Ottumwa Generating Station- Switchgrass Processing Facility - 318511125
20775 Power Plant Road Chillicothe, IA 52501
Wapello County

FO 6

Report
File Name File Type File Date Note
Comments
9/7/2016 8/29/2016 1549: Phone correspondence with Rob Saunders of Alliant - Ottumwa Generating Station regarding the stack discrepancy deficiencies noted on the AQ CE from late 2015. The discrepancies were associated with EP 72 and EP 73. He mentioned that he was in correspondence with Michael Lee with Alliant who does permitting from the Cedar Rapids office. He mentioned that he was currently out of the office but that he would be back in a few days and that they would modify the respective construction permits in order to match the observed stack characteristics. JON RYK