Comments
9/15/2010 Todd reported the City completed the 5th St relief sewer in 2009 and construction of the west relief sewer is in progress with completion expected Nov. 2011. Funding reportedly delayed the construction as I-jobs reprioritized some work. The City is planning to add an EQ basin (ground has been purchased) – design just began. I reminded Todd that post-relief flow monitoring must be initiated by 10/01/10 according to schedule. He indicated inline meters could be installed in the system, he expected to meet this date. KATE BASON