Field Office Compliance - Assistance


Assistance ID - 138621
Ames Water Pollution Control Facility - 312530802
56797 280TH ST Ames, IA 50010
Story County

FO 5

Report
File Name File Type File Date Note
Comments
8/10/2026 Spoke to Tyler on 8/4/26, and they ran power cords directly into the facilty to forgo use of the emergency generator. BRYAN BUNTON
8/10/2026 The Ames WPCF is in the process of refurbishing their entire facility and requested to operate an emergency engine (permit# 11-A-007 ) for up to 120 hours while electrical components are being upgraded. Per AQB, Their options are: 1) Apply for a permit modification to add a catalyst/control equipment to the engine (I'm assuming this would take too much time since they want to start this project soon). 2) Operate the other 3 engines permitted for non-emergency use. 3) Bring in a temporary/portable engine. Ames WPC could use an engine that falls under the small unit exemption. Calculations would need to show that the engine falls under the emission threshold. John Curtin said that since they are planning on running it for less than 200 hours, a Tier 4 would almost certainly meet the SUE requirement, and a Tier 2 potentially could as well. If the temporary/portable engine could not meet the SUE, then a variance would be needed. BRYAN BUNTON