Field Office Compliance - Assistance


Assistance ID - 137450
Mitchellville City Of Stp - 310640107
110 2ND STREET NE Mitchellville, IA 50169
Polk County

FO 5

Report
File Name File Type File Date Note
Comments
3/20/2026 Tom Atkinson 4:13?PM (4 hours ago) to me, Bryan, Matt, Jason, Jan, Luke, Jacobe, Cody As of 2:45 p.m. today the UV system at the Mitchellville wastewater treatment plant was returned to service. We are working with Enaqua to rehab the system more after the disinfection season. If you have any questions or concerns please don't hesitate to ask. Tom JANET GASTINEAU
3/20/2026 March 18 I talked to Tom Atkinson about progress being made on repairs. Enaqua is helping and they're thinking by the end of the week it will be operational. They're going to wait until the end of the disinfection period and do a more comprehensive overhaul. Turns out there is some kind of cooling radiator system in the UV system that requires maintenance that's never been done. He said the ISAM and digester bids are just about all in and a decision will be made. Bids for the WTP improvements are also flying in; they have plans for the pretreatment buidling, which Matt has also mentioned he'd like to do. Since Luke Anderson won't be at Prairie City anymore, he'll work into the OIC at Mitchellville. Tom will let us know when. City council meeting was postponed Monday because the mayor vetoed or denied Jacoby as city clerk. It was rescheduled for tonight. Tom's not sure what progress is being made on the VA. Jacoby was also interim city administrator. JANET GASTINEAU
3/20/2026 Jan let me know the UV flooded and is not operational. They're working with the mfg, who happened to be in Iowa, to get it back into service. Turns out there's no way to remove the bulbs. I told him that was brought up several years ago. Some type of crane/gantry was part of the project originally. They're not going to have it operational by 3/15/2026 start to disinfection system. JANET GASTINEAU