Field Office Compliance - Assistance


Assistance ID - 130581
Cedar Rapids Water Pollution Control - 310631377
7525 BERTRAM ROAD SE Cedar Rapids, IA 52403-7111
Linn County

FO 1

Report
File Name File Type File Date Note
Comments
3/26/2024 Roughing filters back online 3/22/2024. MICHELE SMITH
2/23/2024 Meeting notes: ~ 4 weeks ago a sinkhole/pipe collapsed at CR WPCF discovered by steam rising out of the ground. Blocked off area. Able to stop flow shortly after to televise line: 2 x 10’ sections of 84’’ pipe had tops collapse, carried down to next junction box. Had a contractor excavate to explore extent of issue. This is downstream of roughing filters on the path to the activated sludge process. Currently, plant is operating fairly normally. Plan is to go from primary clarifiers -> bypass roughing filters -> go right to activated sludge process Trying to minimize hauled waste and heavy industry load during bypass Requires us to take entire roughing filter process out of commission to complete Impacts ability to remove organic waste Schedule: Bypass starting Fri Mar 01 Believe we can be complete by Mar 08 We will be proactively correcting another portion of pipe we’ve identified as an issue Roughing filters Typically account for ~50% of BOD removal Not running means generating more solids thru activated sludge A clarifiers Modified slightly to make bypass pumping work – scum arm partially removed Monitoring to see if Rotorooter needs to remove scum layer periodically IDNR question: Do you anticipate an effluent violation? Orcutt: BOD should be in pretty good shape. Typically have 98% removal across the plant and have some cushion. We are unsure how many secondary solids will be produced. Focusing on maximizing dewatering equipment on site. We have not been through this situation before so we are heading into some unknown territory. O’Neil: Also working on an emergency action plan in the event an issue occurs with bypass pumping. Bypass pumping will happen w/ 3 dedicated lines w/ 6 pumps for redundancy. We have the ability to also stop one clarifier if needed. Also coming up w/ monitoring options – TOC, solids, DO. IDNR question: With more activated sludge use, do you have concerns w/ ammonia? Orcutt: Where the river is now, it’s not as big of a concern as it was in the late fall / early winter. Assuming replacement goes as planned, we will have everything back functional before Mar 15 when we start chlorination process. O’Neil: Also we’ve worked to have capacity in our storage tank in the event we have a major issue w/ ammonia, we do have capacity w/ storage. IDNR question: Can you have someone visually inspect the diffuser daily? We want to know what the public may see. Schroeder: Yes, we will be able to do this. We will grab a photo daily. Attendees: Cedar Rapids: Drew Campbell Paul Bestick Terry Tiedemann Aaron Orcutt Justin Schroeder Lauren O’Neil Jereme Gravert IDNR: Michele Smith Justin Schroeder (he/him) Environmental Manager Utilities MICHELE SMITH