File Name File Type File Date Note
Comments
12/12/2023 Email received 12/11/23 to address bypasses: Currently our solutions to bypasses are two-fold. We check problematic and main sewer lines twice a week. We have a check list we work from and have documentation dating back to 2018. We also keep records of any lines that we jet and have documentation dating back to 2016. This would be for clogged lines as well as preventative maintenance jetting which we perform as time allows. There are a number of lines we jet a few times a year in order to deal with their tendency to get blocked. Smoke testing was performed early in 2023 and we are slowly but surely dealing with issues revealed during that process. Most of what we found is uncovered clean-outs but a couple more serious issues were found including a storm sewer that was getting smoke into it and one place where smoke was just coming up through a citizens yard. That turned out to be a clean out that was broken and buried. The issue has been resolved as have the majority of uncovered clean-outs. The storm drain has not but we are looking to televise in 2024 and that will be one of the first places we will have looked at. It is my understanding that the city of Red Oak is trying to secure funding for a plant upgrade to deal with some ongoing issues here. In talking with the mayor, city manager, and a couple council members they seem to understand that the collections system must be improved. It is my understanding that the city is also looking at relining parts of the collection system as well funding improvements to the plant itself. In the meantime we are tasked with improving the performance of the collection system as it now exists. We have started a more organized approach to preventative maintenance jetting. We will attempt to find at least four hours a week to jet lines systematically covering the entirety of the city sewer lines. Tentatively the goal would be to jet every sewer line in the city at least once every calendar year. This past Friday, December 8 2023, we had a meeting with the engineers , mayor, two council members and city manager about upgrades to the plant. During the meeting I brought up the requirement that we secure this sight by installing new or repairing the existing fencing. I was asked to inquire about a timeframe the DNR would like us to follow for completing those repairs/installation. The thinking was that as part of the upgrades we are looking at it's likely that the fence would have to be taken down to move equipment and building supplies onto the sight. The city was hoping the DNR would allow the fencing issues to be addressed as part of the coming upgrade, KRISTI BURG