IPL - Ottumwa Generating Station- Switchgrass Processing Facility - 318511125
20775 Power Plant Road Chillicothe, IA 52501
Wapello County

FO 6

Report
File Name File Type File Date Note
Comments
6/1/2023 The following is a summary of an email provided by Rob Saunders with OGS on 6/1/2023. Saunders reported the OGS bottom ash pond closure project has progressed to the point where the ash is fully covered by clay and any water that flows out of Outfall 001 cannot contact ash. This means that any water effluent from Outfall 001 is not ash contact water, but is now storm water. We agreed that they will continue to sample any storm water effluent from Outfall 001 according to the requirements in the existing permit for Outfall 001 with the following understandings: The existing Parshall flume will no longer be functional because a new hole will be cut in the concrete outfall structure. Therefore, they will estimate future flows. Automated flow measuring equipment will be non-functional but will estimate flows weekly and on days samples are collected so they can calculate mass. Depending on precipitation, there may be periods of time with no discharge. Rob will use "NO DISCHARGE” codes on the eDMR to indicate periods where there was no flow and add a note in the comments section of the eDMR. Due to the likeliness of intermittent flows, they will collect grab samples instead of composite samples to ensure samples are collected. This is in line with the email I sent Rob on March 3, 2023. OGS will attempt to collect quarterly E. coli samples as required by the permit, but may be limited to the number of samples they can collect because of the likeliness of intermittent flow, but will run a geomean on the samples they get if they can not get the five required samples. Rob will add comments to the eDMR as needed. They will continue following these protocols until the new permit is issued later this year. The new permit will designate Outfall 001 as a storm water outfall and no sampling from Outfall 001 will be required. I wrote back to Rob with the following: Rob- The rationale, conditions, and protocols detailed in your email seem reasonable. Although we can not change the terms and conditions of the current NPDES permit, we recognize the ash pond closure limits flow through outfall 001 to storm water only and will result in frequent low or no flow conditions. Therefore, we are agreeable to your proposed approach until the new NPDES permit is issued and better clarifies monitoring and reporting requirements at outfall 001 now that the ash pond discharges have been discontinued. TERRY JONES