Field Office Compliance - Assistance


Assistance ID - 127707
IPL - Ottumwa Generating Station- Switchgrass Processing Facility - 318511125
20775 Power Plant Road Chillicothe, IA 52501
Wapello County

FO 6

Report
File Name File Type File Date Note
Comments
4/17/2023 Saunders called and noted on April 17, they have water in Outfall 001 to pump for the first time this month but noted that if the follow the E.coli sampling requirements in their NPDES Permit, and start sampling for E. coli on April 17, they would not be able to collect the fifth sample until May 1. They didn't want to wait until May just incase there was no flow that month so we agreed to taking four E. coli samples in April (April 17, 19, 24, and 26) instead of five samples in April just to make sure they had data for the monitoring quarter. Provided permission to do collect the 4 samples instead of five and do a geomean on the four. They will add comments to the DMR for the month to document. TERRY JONES