Document Name Type File Date Note
121574_112921_01.pdf
Facility Response (public)
11/17/2025 response
File Name File Type File Date Note
Comments
11/30/2021 After the initial inspection, Dan placed a sump pump in the groundwater lowering tile around the perimeter of the outdoor concrete storage structure. The water from the tile was pumped into concrete storage structure. I spoke to Dan on 11/29/21. He stated that his intentions are to leave the sump pump in the tile located next to the groundwater lowering structure. He stated that after the initial pumping, the sump hasn't ran much if any. Dan submitted photos of what the tile riser and hose from the sump pump look like. He would like to use a PVC pipe to make it a little more permanent and to ensure proper fall from the sump pump to the concrete storage structure. The concrete storage structure has mostly rain water in it. Dan doesn't plan to pump it this fall. Suspense date completed. KRISTI BURG
"
"