PROJECTS LETTING -  December , 2017

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

BLACK HAWK 17-03-07-04 George Wyth State Park - Revetment Repair-2017-12-28   Bid Completion detail
EMMET 18-01-32-03 4 Mile Lake - Wetland Channel Excavation-2017-12-28   Bid Completion detail
APPANOOSE 18-05-04-06 Rathbun Fisheries Management Unit - Boiler Room Roof Replacement-2018-01-18   Bid Completion detail
BREMER 18-03-09-02 Sweet Marsh WMA - Railroad Dike Repair-2018-01-18   Bid Completion detail
BREMER 18-03-09-03 Sweet Marsh WMA - Meyer Pond Dike Repair-2018-01-18   Bid Completion detail
DICKINSON 18-01-30-03 Gull Point Law Enforcement - Storage Building Renovation-2018-01-18   Bid Completion detail
BREMER 18-03-09-04 Sweet Marsh WMA - Albright Wetland Development-2018-01-25   Bid Completion detail
SAC 18-01-81-02 Black Hawk Lake - Ice House Point Shoreline Armor-2018-01-25   Bid Completion detail




APPANOOSE -- PROJECT # 18-05-04-06                1/18/2018                Large Project Letting
RATHBUN FISHERIES MANAGEMENT UNIT
BOILER ROOM ROOF REPLACEMENT
Proposal Guarantee: $2,500
Completion Date: 6/29/2018

   Rathbun Fish Hatchery's boiler room has a ballasted EPDM roof which needs to be replaced. The membrane is stretched and has many different leaks. The contractor shall remove all ballast on the roof, then remove the entire EPDM membrane and all associated items. Existing rigid insulation to remain. Clean entire roof, add new 1/4" dens deck prime and, if needed, new wood substrate. Contractor to install new PVC membrane roof following all manufacturer's instructions for install and create new drainage flow as shown on plans. Contractor to install new pipe, vent and curb flashing, boots and drainage items. Contractor to install new curb and scupper flashing and two new head box downspouts. Contractor must demonstrate a minimum of ten (10) previous projects installing fully-adhered PVC, TPO or EPDM membrane projects similar to the scope of this project.

ESTIMATED QUANTITIES:
    DEMOLITION - COMPLETE DEMO OF ROOF     1 L.S.
    NEW FULLY ADHERED PVC ROOFING AND ALL ASSOCIATED ITEMS     1 L.S.
    MOBILIZATION     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BLACK HAWK -- PROJECT # 17-03-07-04                12/28/2017                Small Project Letting
GEORGE WYTH STATE PARK
REVETMENT REPAIR
Proposal Guarantee: $0
Completion Date: 3/31/2018

   The project consists of furnishing and placing revetment, Class D riprap, (300Ton) along river shoreline at G Wyth State Park, Blackhawk County Iowa. Completion date March 31,2018. Proposal may be obtained by emailing name, address, and pho ne number.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




EMMET -- PROJECT # 18-01-32-03                12/28/2017                Small Project Letting
4 MILE LAKE
WETLAND CHANNEL EXCAVATION
Proposal Guarantee: $0
Completion Date: 3/23/2018

   This project is designed to widen and deepen an existing boat channel through the wetland marsh on the west side of 4 Mile Lake in Emmet County, Iowa. Work under this project includes excavation of a 10' bottom channel with 2:1 side slopes for a distance of 700'. The material will be removed from the marsh and spoiled in an adjacent crop field.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




BREMER -- PROJECT # 18-03-09-02                1/18/2018                Small Project Letting
SWEET MARSH WMA
RAILROAD DIKE REPAIR
Proposal Guarantee: $0
Completion Date: 5/31/2018

   The project consists of removal & disposal of trees and brush from the dike mainly on the eat end, scarification and reshaping existing dike (approx. 2900 LF) by placing material from along side of the dike or from an off site borrow resulting with a 10' top and 3:1 side slope dike, and seeding a stabilizing crop on the disturbed areas near Tripoli, Iowa, Sweet Marsh WMA, Bremer County. Proposal may be obtained by emailing name, address, and phone number.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




BREMER -- PROJECT # 18-03-09-03                1/18/2018                Small Project Letting
SWEET MARSH WMA
MEYER POND DIKE REPAIR
Proposal Guarantee: $0
Completion Date:

   Project consists of scarification and reshaping of existing dike (approx. 500 LF) by placing material from borrow resulting with a dike with 10 foot top and 6:1 side slopes on Sweet Marsh WMA, Bremer county near Tripoli, Iowa. Proposal may be obtained by e-mailing name, address, and phone number.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




DICKINSON -- PROJECT # 18-01-30-03                1/18/2018                Small Project Letting
GULL POINT LAW ENFORCEMENT
STORAGE BUILDING RENOVATION
Proposal Guarantee: $0
Completion Date: 6/1/2018

   The intent of this project is to renovate the exterior of an existing storage facility located at the Gull Point State Park Law Enforcement Complex in Dickinson County, IA. Work will involve the demolition and removal of all the existing roofing siding, sheeting, windows and doors followed by the installation of new materials per specification. Also included is some miscellaneous electrical/lighting work and the construction of a wood loading dock.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




BREMER -- PROJECT # 18-03-09-04                1/25/2018                Small Project Letting
SWEET MARSH WMA
ALBRIGHT WETLAND DEVELOPMENT
Proposal Guarantee: $0
Completion Date: 6/1/2018

   Project consists of excavation (54,314 CY) creating 7 wetlands, furnishing and installing 3 water control structures, furnishing and installing non-perforated tile (565 LF), and stabilizing crop seeding (1/2 Ac.) at Sweet Marsh WMA, Bremer Co., near Frederika, Iowa. Estimated cost $96,000. Completion Date June 1,2018. Proposal may be obtained by e-mailing name, address, and phone number.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




SAC -- PROJECT # 18-01-81-02                1/25/2018                Small Project Letting
BLACK HAWK LAKE
ICE HOUSE POINT SHORELINE ARMOR
Proposal Guarantee: $0
Completion Date: 3/23/2018

   This project is designed to add erosion protection via fieldstone revetment to the shoreline of Black Hawk Lake in the public area known as Ice House Point in Sac County, IA. Work under this contract involves supply and installation of 450 TN of fieldstone along approximately 450 lineal feet of shoreline.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov