PROJECTS LETTING -  December , 2012

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

POLK 13-02-77-06 Big Creek State Park - Waterline Replacement at Spillway Channel-2012-12-27   Bid Completion detail
ADAMS 12-04-02-01 Zimmerman Pool at lake Icaria - Fix dam of wetland-2013-01-17   Bid Completion detail
DES MOINES 09-06-29-01 geode state park - replace culvert under road-2013-01-17   Bid Completion detail
JOHNSON 09-06-52-9 Sutliff Boat Ramp - Repair undermining-2013-01-17   Bid Completion detail
JONES 12-06-53-04 Muskrat Slough - Dike Design and Construction-2013-01-17   Bid Completion detail
SAC 13-01-81-03 Black Hawk - Shoreline stabilization-2013-01-24   Bid Completion detail




ADAMS -- PROJECT # 12-04-02-01                1/17/2013                Large Project Letting
ZIMMERMAN POOL AT LAKE ICARIA
FIX DAM OF WETLAND
Proposal Guarantee: $15,000
Completion Date: 6/1/2013

   Removal and replacement of existing rock rip rap with grouted class 'E' rip rap and the construction of a new CMP outlet structure and incidental items as required by the contract douments and the DNR Inspector.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Earthfill     411 C.Y.
    Excavation     411 C.Y.
    Rip Rap, Grizzled Class E     3,441 Tons
    Rip Rap Concrete Grout     695 C.Y.
    Geotextile Fabric     3,410 S.Y.
    42" Stoplog Riser     1 L.S.
    30" Diameter CMP Pipe     80 L.F.
    Seeding     1 L.S.
    Site Dewatering     1 L.S.
    Rip Rap Removal     1 L.S.
    Regrade Rip Rap Base     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POLK -- PROJECT # 13-02-77-06                12/27/2012                Small Project Letting
BIG CREEK STATE PARK
WATERLINE REPLACEMENT AT SPILLWAY CHANNEL
Proposal Guarantee: $0
Completion Date: 1/18/2013

   This project includes the directional boring of a 6" HDPE water pipe for approximately 300 feet under the spillway channel at Big Creek State Park. The existing water pipe lays on the lake/spillway floor. The new pipe will be connected to 6" PVC water mains on each end with appropriate fittings.

Contact:
Don Labate
515-250-3714
[email protected]




DES MOINES -- PROJECT # 09-06-29-01                1/17/2013                Small Project Letting
GEODE STATE PARK
REPLACE CULVERT UNDER ROAD
Proposal Guarantee: $0
Completion Date: 3/15/2013

   This project consists of removing and replacing 160 LF of 24" CMP underneath an existing roadway; roadway to be removed.

Contact:
Heath Delzell

[email protected]




JOHNSON -- PROJECT # 09-06-52-9                1/17/2013                Small Project Letting
SUTLIFF BOAT RAMP
REPAIR UNDERMINING
Proposal Guarantee: $0
Completion Date: 5/15/2013

   This project consists of site preperation and placing approximatlely 100 TN of class D rip rap, along with flowable grout armoring, along an existing boat ramp.

Contact:
Bruce Flippin

[email protected]




JONES -- PROJECT # 12-06-53-04                1/17/2013                Small Project Letting
MUSKRAT SLOUGH
DIKE DESIGN AND CONSTRUCTION
Proposal Guarantee: $0
Completion Date: 5/31/2013

   Construction of an approximately 550 CY impoundment, including the installation of a water control structure.

Contact:
Bruce Flippin

[email protected]




SAC -- PROJECT # 13-01-81-03                1/24/2013                Small Project Letting
BLACK HAWK
SHORELINE STABILIZATION
Proposal Guarantee: $0
Completion Date: 3/29/2013

   This project is designed to add erosion protection via fieldstone revetment to the windward side of Cottonwood Point in Black Hawk Lake, Sac County, IA. Work under this contract involves supply and installation of 1,000 TN of fieldstone along approximately 1,110 lineal feet of shoreline.

Contact:
Jeff Felts

[email protected]