PROJECTS LETTING -  December , 2010

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

CERRO GORDO 10-03-17-03 Clear Lake McIntosh Woods State Park - Shoreline stabilization-2010-12-23   Bid Completion detail
APPANOOSE 11-05-04-11 Honey Creek Resort - beach construction-2010-12-30   Bid Completion detail
APPANOOSE 11-05-04-07 Rathbun Fish Hatchery - Reshingle 3 Residences-2010-12-30   Bid Completion detail
LUCAS 11-05-59-03 Chariton Research Center - Boat Barn - Roof Replacement-2011-01-13   Bid Completion detail
BOONE 11-02-08-06 Ledges State Park - Debris and Sediment Removal FHWA - Site 1-2011-01-20   Bid Completion detail
BOONE 11-02-08-08 Ledges State Park - Debris & Sediment Removal FHWA - Sites 3 and 4-2011-01-20   Bid Completion detail
DICKINSON 10-01-30-05 Gull Point - Dump Station & Sewer Lines-2011-01-20   Bid Completion detail




CERRO GORDO -- PROJECT # 10-03-17-03                12/23/2010                Small Project Letting
CLEAR LAKE MCINTOSH WOODS STATE PARK
SHORELINE STABILIZATION
Proposal Guarantee:
Completion Date: 5/15/2011

   Stabilize 1550 LF critical areas of Clear Lake shoreline using engineered fabric and armor with native fieldstone revetment. 850 LF will be done from the lake side due to cultural resources and high wooded banks along one section of the project using approximatly one half of the needed 1854 ton of revetment.

Contact:
Mel Pacovsky
319-240-3553
[email protected]




APPANOOSE -- PROJECT # 11-05-04-11                12/30/2010                Small Project Letting
HONEY CREEK RESORT
BEACH CONSTRUCTION
Proposal Guarantee:
Completion Date: 3/31/2011

   This project consists of excavation and spreading of spoil material, and construction of a beach with washed sand.

Contact:
Jason Kruse
(515) 250-3707
[email protected]




APPANOOSE -- PROJECT # 11-05-04-07                12/30/2010                Small Project Letting
RATHBUN FISH HATCHERY
RESHINGLE 3 RESIDENCES
Proposal Guarantee:
Completion Date: 6/30/2011

   This project consists of stripping off old shingles and replacing on three houses at the Rathbun Fish Hatchery.

Contact:
Jason Kruse
(515) 250-3707
[email protected]




LUCAS -- PROJECT # 11-05-59-03                1/13/2011                Small Project Letting
CHARITON RESEARCH CENTER
BOAT BARN - ROOF REPLACEMENT
Proposal Guarantee:
Completion Date: 5/31/2011

   This project consists of replacing the steel roof and perlons and replacing sliding doors on a steel shed.

Contact:
Jason Kruse
(515) 250-3707
[email protected]




BOONE -- PROJECT # 11-02-08-06                1/20/2011                Small Project Letting
LEDGES STATE PARK
DEBRIS AND SEDIMENT REMOVAL FHWA - SITE 1
Proposal Guarantee:
Completion Date: 2/28/2011

   This project is for silt and debris removal from flood damage in 2010 at the damaged culverts along a portion of Ledges State Park Lower Road, Site 1. Tree debris shall be burned on site at a designated location and aluminum culverts to be removed for salvage.

Contact:
Don Labate
515-250-3714
[email protected]




BOONE -- PROJECT # 11-02-08-08                1/20/2011                Small Project Letting
LEDGES STATE PARK
DEBRIS & SEDIMENT REMOVAL FHWA - SITES 3 AND 4
Proposal Guarantee:
Completion Date: 2/28/2011

   This project is for debris removal and culvert cleaning from flood damage in 2010 along the south portion of Ledges State Park Lower Road, Sites 3 and 4.

Contact:
Don Labate
515-250-3714
[email protected]




DICKINSON -- PROJECT # 10-01-30-05                1/20/2011                Small Project Letting
GULL POINT
DUMP STATION & SEWER LINES
Proposal Guarantee: $0
Completion Date: 7/1/2011

   Work under this project includes installation of water and sewer piping to a new RV dump station, installation of a new 6" PCC road section (excavation & embankment) to access the dump station, and installation of approximately 730 ft of 6" PVC sewer line to replace a failing line in another area of the park.

Contact:
Jeff Felts
515-250-3712
[email protected]