PROJECTS LETTING -  October , 2022

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

APPANOOSE 22-05-04-09 Rathbun Wildlife Unit - Sedan Bottoms Office Utilities REBID-2022-10-20   Bid Completion detail
BUENA VISTA 23-01-11-01 Storm Lake Marina - Dock Installation and Site Repairs-2022-10-20   Bid Completion detail
CLAY 23-01-21-03 Dewey's Pasture WMA - Smith Slough Road Maintenance-2022-10-20   Bid Completion detail
DICKINSON 22-01-30-05 Trappers Bay State Park - Shelter Restoration-2022-10-20   Bid Completion detail
JACKSON 23-02-49-02 Bellevue State Park, Dyas Unit - Pavement Maintenance-2022-10-20   Bid Completion detail
JASPER 21-05-50-03 Rock Creek State Park - Sanitary Sewer Liner-2022-10-20   Bid Completion detail
MONONA 21-01-67-04 Lewis and Clark State Park - Visitor Center Repairs - REBID-2022-10-20   Bid Completion detail
WASHINGTON 23-06-92-01 Lake Darling State Park - Lodge HVAC Replacement-2022-10-20   Bid Completion detail
WEBSTER 23-02-94-02 Brushy Creek Recreation Area - Dust collection system-2022-10-27   Bid Completion detail
ALLAMAKEE 23-03-03-01 Yellow River State Forest - Fire Tower Road 2021 Flood Repair-2022-11-03   Bid Completion detail
DALLAS 23-02-25-01 Saylorville WMA - Sub-1 Road Maintenance-2022-11-17   Bid Completion detail
DELAWARE 21-03-28-02 Backbone State Park - Cabin and Museum Road Reconstruction-2022-11-17   Bid Completion detail
LINN 22-06-57-04 Troy Mills - Rapids Repair-2022-11-17   Bid Completion detail
VAN BUREN 22-06-89-01 Lake Sugema Wildlife Management Area - Mercer Wetland Water Control Structure Replacement-2022-11-17   Bid Completion detail




BUENA VISTA -- PROJECT # 23-01-11-01                10/20/2022                Large Project Letting
STORM LAKE MARINA
DOCK INSTALLATION AND SITE REPAIRS
Proposal Guarantee: $12,500
Completion Date: 5/12/2023

   Storm Lake Marina was constructed in 2008 and the current dock system is original. This dock system is old and in need of replacement. A new dock system by EZ Dock shall be installed in this project with new electrical panels, site lighting, sidewalks and stoop footing approaches.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Demolition     1 L.S.
    Concrete Stoops and Sidewalks     1 L.S.
    Dock Installation and All Associated Items     1 L.S.
    Site Lighting, Bases, and All Associated Items     3 Each
    Electrical, Panels, and All Associated Items     1 L.S.
    Iowa DOT Class D Revetment     10 Tons

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




CLAY -- PROJECT # 23-01-21-03                10/20/2022                Large Project Letting
DEWEY'S PASTURE WMA
SMITH SLOUGH ROAD MAINTENANCE
Proposal Guarantee: $12,500
Completion Date: 6/30/2023

   This project consists of HMA pavement maintenance; crack cleaning/filling/sealing, transverse joint repair, patching and fog sealing.

ESTIMATED QUANTITIES:
    2102 - EXCAVATION, CL 10, RDWY+BORROW     29 C.Y.
    2115 - MODIFIED SUBBASE     53 Tons
    2306 - ASPH EMULSION-FOG SEAL (PAV'T)     635 GAL.
    2518 - SAFETY CLOSURE     2 Each
    2528 - TRAFFIC CONTROL     1 L.S.
    2529 - PATCHES, FULL-DEPTH FINISH, BY AREA. 6" HMA     174 S.Y.
    2529 - PATCHES, FULL-DEPTH FINISH, 6-IN., BY COUNT, HMA     7 Each
    2533 - MOBILIZATION     1 L.S.
    2541 - CRACK AND JOINT CLEANING AND SEALING (HMA SURFACES)     1.41 MI.
    2541 - SEALER MATERIAL (HMA SURFACES)     1,033 LB.
    2543 - TRANSVERSE JOINT REPAIR     71 Tons

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JACKSON -- PROJECT # 23-02-49-02                10/20/2022                Large Project Letting
BELLEVUE STATE PARK, DYAS UNIT
PAVEMENT MAINTENANCE
Proposal Guarantee: $12,500
Completion Date: 7/31/2023

   This project consists of pavement preservation; crack cleaning and filling, patching, and fog sealing at Bellevue State Park, Dyas Unit.

ESTIMATED QUANTITIES:
    Bituminous Fog Seal (HMA Pavement) (2306)     3,402 GAL.
    Patches, Full-Depth Finish, 5-inch, By Area, HMA (2529)     186 S.Y.
    Patches, Full-Depth Finish, 5-inch, By Count, HMA (2529)     9 Each
    Transverse Joint Repair (2543)     67 Tons
    Cleaning and Filling Cracks (HMA Surfaces) (2541)     2.23 MGAL
    Sealer Material (HMA Surfaces) (2541)     2,230 LB.
    Modified Subbase (2115)     31 C.Y.
    Traffic Control     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JASPER -- PROJECT # 21-05-50-03                10/20/2022                Large Project Letting
ROCK CREEK STATE PARK
SANITARY SEWER LINER
Proposal Guarantee: $12,500
Completion Date: 11/30/2023

   This project consists of rehabilitating gravity sewer lines by CIPP lining and replacement.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    CIPP Sewer lining     2,549 L.F.
    Point Repairs     10 Each
    Replace pipe with 6 inch PVC SDR 35     38 L.F.
    Site Restoration & Seeding     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




DALLAS -- PROJECT # 23-02-25-01                11/17/2022                Large Project Letting
SAYLORVILLE WMA
SUB-1 ROAD MAINTENANCE
Proposal Guarantee: $12,500
Completion Date: 6/30/2023

   This project consists of granular roadway maintenance - blading/shaping, spreading new rock, ditch cleaning, placement of rip rap, the installation of rock/ditch checks a new RCP culvert.

ESTIMATED QUANTITIES:
    2101 - CLEARING     1 L.S.
    2104 - EXCAVATION, CL 10, CHANNEL     280 C.Y.
    2125 - RESHAPING DITCHES     22.8 STA.
    2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING     88 STA.
    2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE      2,294 Tons
    2312 - GRANULAR SURFACING ON ROAD, CRUSHED STONE, 1.5-INCH     102 Tons
    2312 - GRANULAR SURFACING ON ROAD, CRUSHED STONE, 3-INCH     268 Tons
    2416 - APRON, CONC, 24"     2 Each
    2416 - CULV, CONC RDWY PIPE, 24"     24 L.F.
    2507 - ENGINEERING FABRIC     40 S.Y.
    2507 - REVETMENT, CLASS E     126 Tons
    2507 - EROSION STONE     20 Tons
    2518 - SAFETY CLOSURE     2 Each
    2528 - TRAFFIC CONTROL     1 L.S.
    2533 - MOBILIZATION     1 L.S.
    2601 - SEED+FERTILIZE (RURAL)     1 Acres
    2602 - ROCK CHECK DAM     132 L.F.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




DELAWARE -- PROJECT # 21-03-28-02                11/17/2022                Large Project Letting
BACKBONE STATE PARK
CABIN AND MUSEUM ROAD RECONSTRUCTION
Proposal Guarantee: $100,000
Completion Date: 8/31/2023

   This project consists of removing the existing asphalt roadways and parking lots and constructing new Portland Cement Concrete roadways and parking lots, replacing 6 sanitary sewer manholes, adjusting the rim on 1 sanitary sewer manhole, replacing 1 intake and 2 culverts, installing 1 new intake and culvert and inspecting the condition on 2 intakes at Backbone State Park in Delaware County, Iowa.

ESTIMATED QUANTITIES:
    Clearing and Grubbing     6.8 Acres
    Removal of Existing Pavement and Base     7,799 S.Y.
    Removal of Existing Sidewalk and Base     31 S.Y.
    Removal of Existing Parking Lot and Base     148 S.Y.
    Removal of Intake     1 Each
    Removal of Sanitary Sewer Manhole     6 Each
    Removal of Existing Reinforced Concrete Pipe < 36"     63 L.F.
    Removal of Existing Corrugated Metal Pipe < 36"     65 L.F.
    Removal of Headwall     1 L.S.
    Removal of Existing Gate     1 L.S.
    Manhole, Sanitary Sewer, SW-303, 48"     6 Each
    Manhole Adjustment, Minor     1 Each
    Intake, SW-513     2 Each
    Intake Investigation     2 Each
    Tile Investigation     50 L.F.
    Intake Grate     1 Each
    Roadway Pavement, 7" PCC     10,725 S.Y.
    Parking Lot Pavement, 7" PCC     606 S.Y.
    Sidewalk, 6" PCC     26 S.Y.
    Special Backfill     4,209 Tons
    Granular Shoulder, Type A     606 Tons
    Reinforced Concrete Pipe, 18"     72 L.F.
    Reinforced Concrete Pipe, 24"     40 L.F.
    Reinforced Concrete Pipe, 30"     90 L.F.
    Apron, Conc, 18"     1 Each
    Apron, Conc, 30"     1 Each
    Footing for Concrete Pipe Apron     2 Each
    Pipe Apron Guard, 18"     1 Each
    Pipe Apron Guard, 24"     1 Each
    Pipe Apron Guard, 30"     1 Each
    Erosion Control Mat, RECP Type 2.C     24 S.Y.
    Excavation, Class 10, Roadway and Borrow     869 C.Y.
    Embankment-In-Place     4,059 C.Y.
    Revetment, Class E     25 Tons
    Painted Pavement Mark, High-Build Waterborne     1 L.S.
    Precast Concrete Parking Wheel Stops     16 Each
    Detectable Warning Panel     40 S.F.
    Seeding, Fertilizing, and Mulching     6.8 Acres
    Filter Sock, 8"     9,310 L.F.
    Signing     10 Each
    NPDES General Permit #2 & SWPPP     1 Each
    Construction Staking     1 L.S.
    Traffic Control     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




VAN BUREN -- PROJECT # 22-06-89-01                11/17/2022                Large Project Letting
LAKE SUGEMA WILDLIFE MANAGEMENT AREA
MERCER WETLAND WATER CONTROL STRUCTURE REPLACEMENT
Proposal Guarantee: $12,500
Completion Date: 8/15/2023

   This project consists of removing the existing CMP water control structure and installing a reinforced concrete box drop inlet and smooth metal pipe spillway.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Site Restoration     1 L.S.
    Intake Structure     1 L.S.
    48" Smooth Metal Pipe     177.5 L.F.
    Reinforced Concrete Footing And Pad     1 L.S.
    6" Smooth Metal Pipe     79.5 L.F.
    Fine Drainfill     130 Tons
    Aluminum Stoplogs     1 L.S.
    Sediment Log     216 L.F.
    Demolition     1 L.S.
    Class E Revetment     65 Tons

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




APPANOOSE -- PROJECT # 22-05-04-09                10/20/2022                Small Project Letting
RATHBUN WILDLIFE UNIT
SEDAN BOTTOMS OFFICE UTILITIES REBID
Proposal Guarantee: $0
Completion Date: 4/30/2023

   This project consists of utility services for a new office including water, electricity, septic system, and ADA parking. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




DICKINSON -- PROJECT # 22-01-30-05                10/20/2022                Small Project Letting
TRAPPERS BAY STATE PARK
SHELTER RESTORATION
Proposal Guarantee: $0
Completion Date: 7/28/2023

   This project is the first phase of the restoration of a CCC shelter at Trappers Bay State Park, Dickinson County, IA. Demo work includes the removal of all roofing, underlayment, and flashing. Following demo, inspection of purlins and beams for rot, trimming of purlins as necessary, power-washing, and staining of all wood will be required. New 2x6 T&G roof decking along with asphalt shingles and new copper flashing is also included under this contract. Contact Jeff Felts to obtain contract documents.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




MONONA -- PROJECT # 21-01-67-04                10/20/2022                Small Project Letting
LEWIS AND CLARK STATE PARK
VISITOR CENTER REPAIRS - REBID
Proposal Guarantee: $0
Completion Date: 5/19/2023

   This project is designed to replace all of the exterior siding and address issues with veneer stone on the Visitor Center at Lewis & Clark State Park. The scope of work includes siding and veneer stone removal and replacement, new building wrap, new exterior flashing, 1 window replacement, and other minor repairs on the exterior of the building. Contact Jeff Felts to obtain plans and specifications.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




WASHINGTON -- PROJECT # 23-06-92-01                10/20/2022                Small Project Letting
LAKE DARLING STATE PARK
LODGE HVAC REPLACEMENT
Proposal Guarantee: $0
Completion Date: 3/31/2023

   The Lake Darling Lodge was constructed in 2008 with a Geo-Thermal HVAC system. This HVAC system was configured differently than what would be installed today and the system has lived beyond it's expected life. This project will remove all existing HVAC equipment and glycol solution, the existing duct work and geo-thermal wells shall remain in place. The contractor shall install new HVAC air-handlers, geo circulation pumps, buffer tanks, all new copper piping with armaflex insulation, aquastat controls and new CPU, and flush and refill entire Glycol water mixture.

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov




WEBSTER -- PROJECT # 23-02-94-02                10/27/2022                Small Project Letting
BRUSHY CREEK RECREATION AREA
DUST COLLECTION SYSTEM
Proposal Guarantee: $0
Completion Date: 4/7/2023

   This project is for the addition of a central dust collection system for the seed harvest area of the Prairie Resource Center at Brushy Creek SRA in Webster County. This entails the installation of the main unit as well as ductwork, fittings and start-up to make a complete unit, and other work as directed by the DNR Engineer.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov




ALLAMAKEE -- PROJECT # 23-03-03-01                11/3/2022                Small Project Letting
YELLOW RIVER STATE FOREST
FIRE TOWER ROAD 2021 FLOOD REPAIR
Proposal Guarantee: $0
Completion Date: 12/16/2022

   This project consists of contractor furnish and place revetment at various locations, crushed stone surfacing, and shape & blade damaged section of the Fire Tower Road in the Yellow River State Forest, Allamakee Co. Proposal may be obtained by emailing name, address, and phone number.

Contact:
Kenneth Howe
319-240-3553
Kenneth.howe@dnr.iowa.gov




LINN -- PROJECT # 22-06-57-04                11/17/2022                Small Project Letting
TROY MILLS
RAPIDS REPAIR
Proposal Guarantee: $0
Completion Date: 9/30/2023

   This project will repair rapids in the Wapsipinicon River at the Troy Mills Bridge by constructing stone weirs consisting of Class E and Class B revetment (provided by Owner) and 75 boulders (to be provided by the Contractor).

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov