The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual. Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms, Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.
Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis.
To subscribe to this list, click here.
The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.
To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website.
You may obtain a free download from
Click on the project names below to view the one(s) which interest you.
This project consists of stockpiling and delivering on demand various gradations of stone to the Hartwick Marina and incidental work as required by the Specifications and/or the DNR Construction Inspector
This project consists of site preparation, removal of the existing drawdownpipe and concrete spillway, construcation of groundwater drains, a 72-inch diameter reinforced concrete piincipal spillwau pipe, a reinforced concrete drop inlet structure, a reinforced concrete impact basin outlet strucure, a gated 36-inch reinforced concrete drawdown pipe, earth grading, placement of riprap and other erosion control features and incidental work as required by the drawings, specifications, the DNR Inspector and/or the Construction Representative.
This project consists of lining approximately 5,550 linear feet of 6 to 8 inchs diameter sewer line by cured-in-place pipe liner at Backbone State Park.
Repair bank erosion along Mississippi River at Fairport State Fish Hatchery near Muscatine. Work Items include:
1 LUMP SUM of Bank Shaping
645 SQ YD of Engineering Fabric
486 TON of Iowa DOT Class E Revetment
The scope of this project involves the removal of siding and roofing materials that have been found to contain asbestos. The project involves two separate buildings, one in Dickinson County and one in O'Brien County in northwest Iowa.
Repair of erosion of shoreline and jetties at Lake Sugema, 5 miles SW of Keosauqua.
Work items include:
__ Class 10 Excavation, 94 CU YD
__ Engineering Fabric, 804 SQ YD
__ Iowa DOT Class E Revetment, 554 TON
__ Granular Surfacing, Class A Crushed Stone, 167 TON
Construction and materials shall follow Iowa DOT Standard Specifications, Series 2009.
Work consists of placing revetment along scoured bank and extend spillway revetment, excavate aroud outlet control structure to check on possible damage, backfill scour & place revetment at outlet pipe, and place soil borrow material to level dike roadway.
Work consists of removing existing riprap east of boat ramp down to approximately 1 foot above lake water level, grading a 6-foot wide sub grade for the new sidewalk and creating a fishing bump out area, placing a granular sub-base, and placing 6-inch PCC sidewalk.
Repair of riverbank erosion at DNR McCausland Access on Wapsipinicon River. Project location is off County Road Z30 north of McCausland.
Bank repair is for 130 linear ft of riverbank.
Construction and materials shall follow Iowa DOT Standard Specifications, Series 2009.
Project quantities:
Class 10 Excavation, 87 CU YD
Class E Revetment, 260 TON
Engineering Fabric, 232 SQ YD
Concrete Grout for Revetment, 52 CU YD
This project consists of repairing an existing earthen dike, creating shallow water excavations and incidental work as required by the Plans and/or the DNR Construction Inspector.
This project is designed to improve and add additional elements to the Winkle Tract of the Luton Wetland Complex in Woodbury County. Work under this project includes excavations, earthfill (dike construction), and a shallow water crossing.
This project consists of providing an 18" thick rock pad and stubbing out utilities for a precast concrete water treatment building in AA Call State Park.