The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual. Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms, Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.
Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis.
To subscribe to this list, click here.
The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.
To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website.
You may obtain a free download from
Click on the project names below to view the one(s) which interest you.
This project is more than just a renewable energy pilot. It will give the public hands-on witness to the power of renewable energy. The average state park visitor will get an opportunity to spend a period of time living in a space powered with renewables plus the means for personal exploration about how to make renewables work well. At the same time, measurable energy and cost savings accrue at an important, innovative state facility.
Project consists of construction of a sediment retention dam, Construction of a fishing jetty, rebuilding an existing sediment retention dam, construction of two in-lake silt dams, shoreline armoring, mechanical dredging of the lake bed and incidental works as required by the DNR construction inspector.
EXISTING BRICK VENEER IS IN DISREPAIR AND IS CLOSE TO CATASTROPHIC FAILURE. MULTIPLE MOISTURE ISSUES ARE TO BLAME, THE ROOF IS PONDING WATER, INTERNAL WATER FROM THE HATCHERY AND GROUND WATER FROM THE HIGH WATER TABLE SURROUNDING THE LAKES. ALL OF THESE FACTORS HAVE COME TO CREATE THE CURRENT ISSUES ON THIS BUILDING, WHICH WAS CONSTRUCTED IN 1963. THE PAST 50 YEARS HAVE TAKEN ITS TOLL AND THE FACADE AROUND PUBLIC ACCESS AREAS HAVE TO BE REMOVED TO AVOID FUTURE INCIDENTS AND TO REMAIN SAFE AND ATTRACTIVE FOR YEARS TO COME. A RE-ROOF JOB WILL ALSO BE IN THE PRIORITY LIST AS IT WILL AID IN MAINTAINING A DRY BUILDING.
This project consists of the installation of 34 single camp pad electrical hookup pedestals, one 400 amp distribution panel, one 600 amp distribution panel, trenching and electrical wiring at the Volga River Recreation Area South Equestrian Campground, Fayette County, Iowa, as required by the Plans and/or the DNR Construction Inspector.
ESTIMATED QUANTITIES:
Trench, Single Circuit Secondary
3,067 L.F.
No. 12 Solid Tracer Wire
3,067 L.F.
Detectable Warning Tape, 3" Electric
3,067 L.F.
Security light, as specified
2 Each
Single Campsite Outlet Post (Metallic Power Center) 50 Amp
34 Each
No. 1 AWG Single Conductor Cable, Type USE
1,119 L.F.
No. 2 AWG Single Conductor Cable, Type TWH Or USE
611 L.F.
No. 4 AWG Single Conductor Cable, Type TWH Or USE
2,181 L.F.
No. 6 AWG Single Conductor Cable, Type TWH Or USE
643 L.F.
No. 1/0 AWG Single Conductor Cable, Type USE
810 L.F.
No. 2/0 AWG Single Conductor Cable, Type USE
3,666 L.F.
No. 3/0 AWG Single Conductor Cable, Type USE
2,877 L.F.
No. 8/2 With Ground Type UF Cable
241 L.F.
No. 300 MCM Single Conductor Cable, Type USE
1,833 L.F.
Pad Mounted 400 Amp Distribution Panel and Connections
1 Each
Pad Mounted 600 Amp Distribution Panel and Connections
This project consists of construction of compacted earthfill roadways, parking areas, and other related work as required by the Plans and/or the DNR Construction Inspector and as described in the Specifications for Springbrook State Park, in Guthrie County, Iowa.
ESTIMATED QUANTITIES:
Clearing and Grubbing
1.48 Acres
Excavation, Class 10, Roadway and Borrow
2,616 C.Y.
Special Backfill
917 Tons
Subgrade Stabilization Material, Polymer Grid
3,170 S.Y.
Granular Shoulder, Type A
196 Tons
Standard or Slip Form PCC Pavement, Class C, Class 2 Durability, 6"
This project is designed to create wetland elements on the Thu Tract of the Dewey’s Pasture Wetland Complex in Palo Alto County. Work under this project includes tree removal, excavations, earthfill (dike construction), tile breaks, tile/pipe installation (multiple sizes), water control structures, a toewall structure, and seeding.
This project is designed to provide an extra 10 feet of paving length to the boat ramp area maneuvering spaces at the Storm Lake State Marina. Work will involve sawcutting and removal of pavement, sub-grade preparation, 6” PCC paving with integral curb, site restoration, and seeding.
Project consists of reshaping & resurfacing parking lots, repairing AC pavement, and repairing erosion area. This work is between the Flats area & North Entrance.
This project is intended to restore all mechanical and plumbing services to the Lewis & Clark Visitor Center. These services were disconnected in preparation for Missouri River flooding this summer. Additional work to insulate all cold water and well field piping inside the building will also be included.
This project is intended to restore all removed electrical components in the Lewis & Clark Visitor Center. These components were disconnected/removed in preparation for Missouri River flooding this summer. The contractor will be responsible for furnishing all labor, equipment, and materials necessary to complete the project as specified.
Project consists of repairing & placing crushed stone surfacing on approximately 1535 LF of trails over 7 areas, repairing floating trail bridge , constructing & repairing sream crossings, and removal of dedris. Potential bidders are required to attend a pre-bid site visit on September 13, 2011 at 10 AM. Meeting will start at the Julian Dubuque parking lot.
This project is designed to expand the wetland complex known as Garlock Slough in Dickinson County. The majority of the work is on the newly purchased Graff Tract with a portion on the existing Ortmeier Tract. Work under this project includes excavations, earthfill (dike construction), tile breaks, tile installation (multiple sizes), 3 water control structures, and seeding.
This project is designed to create wetland elements on the Wallace Tract of the Santee Prairie Wildlife Management Area in Dickinson County. Work under this project includes earthfill (dike construction), tile investigation, tile breaks, an aluminum toewall structure, and seeding.
Televised inspection and light cleaning of sanitary sewer ranging in diameter between 4 inches and 8 inches. Project includes heavy cleaning for removal of grit, sludge, and debris using a combination jet/vac, and root cutting if necessary to complete televised inspection.