PROJECTS LETTING -  August , 2023

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

APPANOOSE 22-05-04-02 Red Haw State Park - Design Guide Shelter-2023-08-24   Bid Completion detail
BREMER 21-03-09-02 Sweet Marsh Wildlife Management Area - HMA Pavement Maintenance-2023-08-24   Bid Completion detail
CLINTON 23-06-23-01 Goose Lake Wildlife Management Area - Boat Access and Water Control Structure-2023-08-24   Bid Completion detail
WARREN 23-05-91-01 Lake Ahquabi State Park - Pond 5A Outlet Replacement-2023-08-24   Bid Completion detail
BUTLER 20-03-12-03 Shell Rock Bend WMA - Road Maintenance-2023-09-21   Bid Completion detail
MARION 23-05-63-04 Red Rock WMU/Lake Keomah - Road Maintenance-2023-09-21   Bid Completion detail
MONONA 24-01-67-02 Tieville Bend WMA - Pump Replacement-2023-09-21   Bid Completion detail
TAMA 24-05-86-01 Hickory Hills Park - Casey Lake Restoration-2023-09-21   Bid Completion detail




APPANOOSE -- PROJECT # 22-05-04-02                8/24/2023                Large Project Letting
RED HAW STATE PARK
DESIGN GUIDE SHELTER
Proposal Guarantee: $12,500
Completion Date: 5/17/2024

   Red Haw State Park was hit by a tornado in the spring of 2021. A few of the shelters were destroyed in this storm and this project will replace some of that lost infrastructure. This project will demolish two building slabs and foundations, and the large concrete beach building in it's entirety. This project is for a new Parks Design Guide shelter and ADA parking at the nearest possible location with a short sidewalk to the shelter location.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Demolition and Salvage     1 L.S.
    Construction Staking     1 L.S.
    Grading     1 L.S.
    Design Guide Shelter (all inclusive)     1 L.S.
    6" Reinforced PCC Shelter Slab and Subbase     155 S.Y.
    5" Reinforced PCC Sidewalks and Subbase     190 S.Y.
    ADA Parking Area and Accessories     1 L.S.
    Grill and Slab     1 Each
    Electrical     1 L.S.
    Class A Road Stone     100 Tons
    Site Restoration (fill, seeding, and fertilizing)     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




CLINTON -- PROJECT # 23-06-23-01                8/24/2023                Large Project Letting
GOOSE LAKE WILDLIFE MANAGEMENT AREA
BOAT ACCESS AND WATER CONTROL STRUCTURE
Proposal Guarantee: $6,250
Completion Date: 5/17/2024

   This project consists of constructing a gravel parking lot and boat ramp with a PCC parking space and removing the existing CMP water control structure and installing a reinforced concrete water control structure and pipe.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Traffic Control     1 L.S.
    Silt Fence     400 L.F.
    Clearing and Grubbing     0.4 Acres
    Site Preparation     1 L.S.
    Culvert, 18" CMP     40 L.F.
    Macadam Stone, 6" Depth     354 Tons
    Class A Road Stone, 3" Depth     160 Tons
    PCC Parking, 6" Depth, Reinforced     95 S.Y.
    Granular Subbase, 6" Depth     34 Tons
    Striping     1 L.S.
    Demolition of Water Control Structure and Pipe     1 L.S.
    Water Control Structure     1 Each
    Aluminum Stop Logs     11 Each
    Culvert, 36" RCP     45 L.F.
    Flared End Section, 36" RCP     1 Each
    Core Trench - Import (Clay)     74 C.Y.
    Bentonite Liner     178 S.Y.
    Engineering Fabric     178 S.Y.
    Revetment, Class E     120 Tons
    Site Restoration     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BUTLER -- PROJECT # 20-03-12-03                9/21/2023                Large Project Letting
SHELL ROCK BEND WMA
ROAD MAINTENANCE
Proposal Guarantee: $4,000
Completion Date: 7/30/2024

   This project consists of granular roadway maintenance - blading/shaping, spreading new rock, ditch cleaning, shoulder work, the replacement of one culvert and the installation of one new culvert.

ESTIMATED QUANTITIES:
    2102 - SPECIAL BACKFILL     6 Tons
    2125 - RESHAPING DITCHES - CULVERTS     4 STA.
    2125 - RESHAPING DITCHES - SWAIL     2.5 STA.
    2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING ROADWAY     25.9 STA.
    2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING SHOULDERS     25.9 STA.
    2312 - GRANULAR SURFACING ON ROAD, 3-INCH MINUS     633 Tons
    2416 - CULV, CONC RDWY PIPE, 18"     42 L.F.
    2507 - ENGINEERING FABRIC     100 S.Y.
    2507 - EROSION STONE     40 Tons
    2518 - SAFETY CLOSURE     1 Each
    2528 - TRAFFIC CONTROL     1 L.S.
    2533 - MOBILIZATION     1 L.S.
    2601 - SEED+FERTILIZE (RURAL)     1 Acres

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




MARION -- PROJECT # 23-05-63-04                9/21/2023                Large Project Letting
RED ROCK WMU/LAKE KEOMAH
ROAD MAINTENANCE
Proposal Guarantee: $12,500
Completion Date: 9/30/2024

   This projects consists of granular roadway maintenance. Blading/shaping, culvert replacement, ditch cleaning and spreading new rock.

ESTIMATED QUANTITIES:
    2125 - RESHAPING/CLEANING DITCHES     5 STA.
    2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING     205 STA.
    2210 - MACADAM STONE BASE     857 Tons
    2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE 1-1/4"     535 Tons
    2312 - GRANULAR SURFACING ON ROAD, CRUSHED STONE 3-INCH MINUS     3,038 Tons
    2416 - APRON, CONC, 18"     2 Each
    2416 - CULV, CONC RDWY PIPE, 18"     24 L.F.
    2507 - ENGINEERING FABRIC     20 S.Y.
    2507 - EROSION STONE     16 Tons
    2518 - SAFETY CLOSURE     7 Each
    2528 - TRAFFIC CONTROL     1 L.S.
    2533 - MOBILIZATION     1 L.S.
    2552 - REPLACEMENT OF UNSUITABLE BACKFILL MAT'L (CLASS II PIPE BEDDING)      5 C.Y.
    2601 - SEED+FERTILIZE (RURAL)     0.5 Acres

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




MONONA -- PROJECT # 24-01-67-02                9/21/2023                Large Project Letting
TIEVILLE BEND WMA
PUMP REPLACEMENT
Proposal Guarantee: $6,250
Completion Date: 5/30/2024

   This project consists of installing one 90 HP axial propeller pump into the existing pump station. Installation includes all necessary hardware, wire, and connections to the existing motor control center.

ESTIMATED QUANTITIES:
    Pump, Complete     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




TAMA -- PROJECT # 24-05-86-01                9/21/2023                Large Project Letting
HICKORY HILLS PARK
CASEY LAKE RESTORATION
Proposal Guarantee: $150,000
Completion Date: 3/15/2025

   This project consists of constructing five sediment ponds, three in-lake forebays, mechanically dredging the main lake basin, shoreline armoring, streambank stabilization, and modifying the principal spillway stoplog system.

ESTIMATED QUANTITIES:
    Mobilization & Demobilization     1 L.S.
    Site Preparation and Clearing     1 L.S.
    SWPPP Management     1 L.S.
    Over-Excavation, Core Trench     950 C.Y.
    Over-Excavation, Embankment Top     1,548 C.Y.
    Excavation, Stream Bank Excavation, Haul to BMP 17     1,138 C.Y.
    Topsoil, Strip, Stockpiling & Respread     4,898 C.Y.
    Existing Structure Removal, BMP 3     1 L.S.
    Existing Structure Removal, BMP 7     1 L.S.
    Existing Structure Removal, BMP 12     1 L.S.
    Earthfill, Embankment & Structure Removal Excavation Fill     20,140 C.Y.
    Excavation, Mechanical Dredging Existing BMP – Hardbottom & Soft Sediment     8,306 C.Y.
    6" PVC, Anti Seep Collars, and Trash Racks     119 L.F.
    10" CMP, Anti Seep Collars, and Trash Racks     372 L.F.
    18" CMP & Anti Seep Collars     111 L.F.
    36" CMP Riser and Trash Rack     3 Each
    10" Knife Gate Valves, Stainless Steel     3 Each
    Agridrain Inlet Water Control Structure, 4’ Height, 6" Pipe Connections     1 L.S.
    Agridrain Inlet Water Control Structure, 5’ Height, 10" Pipe Connections     1 L.S.
    Rip Rap, Class ‘E’ with Geotextile Fabric     465 Tons
    Choke/Chink Stone, 1" to 5", Well Graded     80 Tons
    Boulders, Step Pool, 600 to 900 Lb.     80 Tons
    Granular Surfacing, Staging Area     160 Tons
    Composite Bentonite Coated Aggregate     5 Tons
    RECO – 400 G Coir     175 S.Y.
    RECP – Type 2B     2,425 S.Y.
    Erosion Control Silt Fence     1,940 L.F.
    Live Stakes, Harvest on Site     1,000 Each
    Temporary Seeding     5.1 Acres
    Lake Drawdown/Dewatering     1 L.S.
    Excavation, Mechanical Dredging     138,831 C.Y.
    Earthfill, Embankment and Lake Bottom Fill     33,768 C.Y.
    Topsoil Strip, Salvage, and Respread     3,800 C.Y.
    Rip Rap, Class ‘C’ – Jetties and Shoreline Armoring     2,748 Tons
    Salvage Existing Rip Rap     480 Tons
    Granular Surfacing, Boat Launch and Parking Area     450 Tons
    Tied Concrete Block Mat, Shoreline Armoring and Overflows, 12’ Wide Roll     1,828 S.Y.
    Lake Riser Structure Modifications, Aluminum Bulkhead, Stoplogs, and 18" x 18" Slide Gate     1 L.S.
    12" PPHP Pipe     330 L.F.
    12" Hickenbottom Riser     4 Each
    Reinforced Concrete Arch Pipe, 42" Equivalent (51" x 31")     128 L.F.
    Reinforced Concrete Arch Flared End Section, 42" Equivalent (51" x 31")     6 Each
    Stone Terrace     1 L.S.
    Shoreline Fishing Node, 18’ x 10’     4 Each
    Seeding, Type 1     3.8 Acres
    Seeding, Type 2     5.9 Acres
    Seeding, Type 4 (Temporary)     9.4 Acres
    Erosion Control Silt Fence     5,000 L.F.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BREMER -- PROJECT # 21-03-09-02                8/24/2023                Small Project Letting
SWEET MARSH WILDLIFE MANAGEMENT AREA
HMA PAVEMENT MAINTENANCE
Proposal Guarantee: $0
Completion Date: 6/15/2024

   THIS PROJECT CONSISTS OF HMA TRANSVERSE JOINT REPAIR AND FOG SEALING ON ROAD OFF OF 165TH ST AT SWEET MARSH WILDLIFE MANAGEMENT AREA.

Contact:
Kenneth Howe
319-240-3553
Kenneth.howe@dnr.iowa.gov




WARREN -- PROJECT # 23-05-91-01                8/24/2023                Small Project Letting
LAKE AHQUABI STATE PARK
POND 5A OUTLET REPLACEMENT
Proposal Guarantee: $0
Completion Date: 5/31/2024

   This project consists of replacing a 48" diameter pond outlet pipe and other work described in the plans. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov