PROJECTS LETTING -  August , 2023

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

JONES 18-06-53-04 Wapsipinicon State Park - Culvert and Bridge Repair-2023-08-17   Bid Completion detail
APPANOOSE 22-05-04-02 Red Haw State Park - Design Guide Shelter-2023-08-24   Bid Completion detail
BREMER 21-03-09-02 Sweet Marsh Wildlife Management Area - HMA Pavement Maintenance-2023-08-24   Bid Completion detail
CLINTON 23-06-23-01 Goose Lake Wildlife Management Area - Boat Access and Water Control Structure-2023-08-24   Bid Completion detail
WARREN 23-05-91-01 Lake Ahquabi State Park - Pond 5A Outlet Replacement-2023-08-24   Bid Completion detail




APPANOOSE -- PROJECT # 22-05-04-02                8/24/2023                Large Project Letting
RED HAW STATE PARK
DESIGN GUIDE SHELTER
Proposal Guarantee: $12,500
Completion Date: 5/17/2024

   Red Haw State Park was hit by a tornado in the spring of 2021. A few of the shelters were destroyed in this storm and this project will replace some of that lost infrastructure. This project will demolish two building slabs and foundations, and the large concrete beach building in it's entirety. This project is for a new Parks Design Guide shelter and ADA parking at the nearest possible location with a short sidewalk to the shelter location.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Demolition and Salvage     1 L.S.
    Construction Staking     1 L.S.
    Grading     1 L.S.
    Design Guide Shelter (all inclusive)     1 L.S.
    6" Reinforced PCC Shelter Slab and Subbase     155 S.Y.
    5" Reinforced PCC Sidewalks and Subbase     190 S.Y.
    ADA Parking Area and Accessories     1 L.S.
    Grill and Slab     1 Each
    Electrical     1 L.S.
    Class A Road Stone     100 Tons
    Site Restoration (fill, seeding, and fertilizing)     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




CLINTON -- PROJECT # 23-06-23-01                8/24/2023                Large Project Letting
GOOSE LAKE WILDLIFE MANAGEMENT AREA
BOAT ACCESS AND WATER CONTROL STRUCTURE
Proposal Guarantee: $6,250
Completion Date: 5/17/2024

   This project consists of constructing a gravel parking lot and boat ramp with a PCC parking space and removing the existing CMP water control structure and installing a reinforced concrete water control structure and pipe.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Traffic Control     1 L.S.
    Silt Fence     400 L.F.
    Clearing and Grubbing     0.4 Acres
    Site Preparation     1 L.S.
    Culvert, 18" CMP     40 L.F.
    Macadam Stone, 6" Depth     354 Tons
    Class A Road Stone, 3" Depth     160 Tons
    PCC Parking, 6" Depth, Reinforced     95 S.Y.
    Granular Subbase, 6" Depth     34 Tons
    Striping     1 L.S.
    Demolition of Water Control Structure and Pipe     1 L.S.
    Water Control Structure     1 Each
    Aluminum Stop Logs     11 Each
    Culvert, 36" RCP     45 L.F.
    Flared End Section, 36" RCP     1 Each
    Core Trench - Import (Clay)     74 C.Y.
    Bentonite Liner     178 S.Y.
    Engineering Fabric     178 S.Y.
    Revetment, Class E     120 Tons
    Site Restoration     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JONES -- PROJECT # 18-06-53-04                8/17/2023                Small Project Letting
WAPSIPINICON STATE PARK
CULVERT AND BRIDGE REPAIR
Proposal Guarantee:
Completion Date: 12/22/2023

   Wapsipinicon State Park has a historic bridge near Dutch Creek Shelter. The bridge needs shoring up at the abutment and a decorative abutment turret needs repair. This project will armor the shoreline beneath the bridge, repair the turret with non-shrink grout, and clean all of the masonry. There is also a Culvert that needs to be Repaired and armored and this project shall include this work also.

Contact:
Mark Moeller
515-214-9532
mark.moeller@dnr.iowa.gov




BREMER -- PROJECT # 21-03-09-02                8/24/2023                Small Project Letting
SWEET MARSH WILDLIFE MANAGEMENT AREA
HMA PAVEMENT MAINTENANCE
Proposal Guarantee: $0
Completion Date: 6/15/2024

   THIS PROJECT CONSISTS OF HMA TRANSVERSE JOINT REPAIR AND FOG SEALING ON ROAD OFF OF 165TH ST AT SWEET MARSH WILDLIFE MANAGEMENT AREA.

Contact:
Kenneth Howe
319-240-3553
Kenneth.howe@dnr.iowa.gov




WARREN -- PROJECT # 23-05-91-01                8/24/2023                Small Project Letting
LAKE AHQUABI STATE PARK
POND 5A OUTLET REPLACEMENT
Proposal Guarantee: $0
Completion Date: 5/31/2024

   This project consists of replacing a 48" diameter pond outlet pipe and other work described in the plans. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov