The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual. Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms, Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.
Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis.
To subscribe to this list, click here.
The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.
To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website.
You may obtain a free download from 


Plans can be ordered by following this link: http://bit.ly/IADNRPlans 
|
|
MARION -- PROJECT # 11-05-63-11 8/16/2012 Small Project Letting
|
ELK ROCK STATE PARK
|
| SEWER & LIFT STATION REHABILITATION |
Proposal Guarantee: $0
|
Completion Date: 4/30/2013
|
| | This project consists of rehabilitation of 1261' of sanitary sewer, lift station controls & pump, and 1195' of fencing around the lagoons.
|
Contact: Jason Kruse [email protected]
|
|
BOONE -- PROJECT # 13-02-08-02 8/23/2012 Small Project Letting
|
SALYLORVILLE WMU AT BOONE RESEARCH STATION
|
| REPLACE ROOF ON STORAGE BUILDING |
Proposal Guarantee: $0
|
Completion Date: 10/31/2012
|
| | This project entails the removal and replacement of a metal roof and gutters on a 4:12 sloped 30'x80' pole building at Boone Research Station in Ledges State Park in Boone County.
|
Contact: Don Labate 515-250-3714 [email protected]
|
|
KOSSUTH -- PROJECT # 12-02-55-01 8/23/2012 Small Project Letting
|
EAGLE LAKE
|
| INSTALL VARIABLE CREST WCS |
Proposal Guarantee: $0
|
Completion Date: 11/16/2012
|
| | This project is designed to improve the existing water level control capabilities for the Eagle Lake Wildlife Area. Work under this project includes dewatering of the basin (+-3' on 80 acres), removal of the existing outlet tile, new 15" tile installation, two new tile inlets, and a new water control structure.
|
Contact: Jeff Felts [email protected]
|
|
BOONE -- PROJECT # 12-02-08-03 8/30/2012 Small Project Letting
|
LEDGES STATE PARK
|
| ELECTRICAL UPGRADES |
Proposal Guarantee: $0
|
Completion Date: 11/1/2012
|
| | This project entails upgrading the host campsite from a 30 amp service to a 50 amp service, adding receptacles and conduit in the Park shop for garage door openers and misc. electrical upgrades at Ledges State Park in Boone County, Iowa.
|
Contact: Don Labate 515-250-3714 [email protected]
|
|
BOONE -- PROJECT # 12-02-08-05 8/30/2012 Small Project Letting
|
LEDGES STATE PARK
|
| SEWER AND WATER UPGRADES |
Proposal Guarantee: $0
|
Completion Date: 9/28/2012
|
| | This project entails upgrading the host campsite with sewer and water hook ups, repairing curb stops, repairing a water main leak, replacing a yard hydrant and other plumbing upgrades at Ledges State Park in Boone County, Iowa.
|
Contact: Don Labate 515-250-3714 [email protected]
|
|
LUCAS -- PROJECT # 11-05-59-06 8/30/2012 Small Project Letting
|
STEPHENS STATE FOREST WHITEBREAST UNIT
|
| ROBERT'S CROSSING |
Proposal Guarantee: $0
|
Completion Date: 11/30/2012
|
| | This project includes replacement of a ford style stream crossing.
|
Contact: Jason Kruse [email protected]
|
|
POLK -- PROJECT # 13-02-77-02 8/30/2012 Small Project Letting
|
BIG CREEK STATE PARK
|
| BEACH AREA DEMOLITION |
Proposal Guarantee: $0
|
Completion Date: 10/15/2012
|
| | This project includes the demolition and removal of three shelters and two latrines and associated foundations and utilities, including an outside shower structure, at the beach complex at Big Creek State Park in Polk County, Iowa. All structures are constructed of timber framing with concrete masonry walls and concrete foundations.
|
Contact: Don Labate 515-250-3714 [email protected]
|
|
BOONE -- PROJECT # 11-02-08-11 9/6/2012 Small Project Letting
|
SAYLORVILLE WILDLIFE UNIT
|
| HEADQUARTERS BUILDING DATA LINE |
Proposal Guarantee: $0
|
Completion Date: 10/1/2012
|
| | Data Line tio be bored from the Research Station to the new Wildlife HQ Building at teh Saylorville Unit at Ledges State Park in Boone, IA.
|
Contact: Don Labate 515-250-3714 [email protected]
|
|
DICKINSON -- PROJECT # 13-01-30-07 9/6/2012 Small Project Letting
|
DUGOUT CREEK WETLAND COMPLEX
|
| SYNCO WETLAND RT |
Proposal Guarantee: $0
|
Completion Date: 11/16/2012
|
| | This project is designed to provide two additional wetland pool areas to the wetland area known as Synco WPA in Dickinson County. Work under this project includes excavation, earthfill, tile investigation, tile breaks, and tile installation.
|
Contact: Jeff Felts [email protected]
|
|
POTTAWATTAMIE -- PROJECT # 12-04-78-11 9/6/2012 Small Project Letting
|
LAKE MANAWA STATE PARK
|
| SEDIMENT REMOVAL & PARKING LOT |
Proposal Guarantee: $0
|
Completion Date: 11/4/2012
|
| | Remove and dispose of the sediment in the river boat ramp parking area and place new gravel in the parking area and seed disturbed areas.
|
Contact: Mark Johnson 515-250-3713 [email protected]
|
|
POTTAWATTAMIE -- PROJECT # 12-04-78-14 9/6/2012 Small Project Letting
|
LAKE MANAWA STATE PARK
|
| REPAIR RETAINING WALL BY BEACH |
Proposal Guarantee: $0
|
Completion Date: 11/4/2012
|
| | Remove and dispose of the damaged sections of concrete seawall and replace with new and seed disturbed areas.
|
Contact: Mark Johnson 515-250-3713 [email protected]
|
|
POTTAWATTAMIE -- PROJECT # 12-04-78-06 9/6/2012 Small Project Letting
|
WILSON ISLAND RECREATION AREA
|
| DEMOLITION OF BUILDINGS |
Proposal Guarantee: $0
|
Completion Date: 11/4/2012
|
| | Remove and dispose of 5 buildings damaged by floodwaters.
|
Contact: Mark Johnson 515-250-3713 [email protected]
|
|
POTTAWATTAMIE -- PROJECT # 12-04-78-05 9/6/2012 Small Project Letting
|
WILSON ISLAND STATE RECREATION AREA
|
| RESTORE RIVERFRONT AREA |
Proposal Guarantee: $0
|
Completion Date: 11/4/2012
|
| | Remove and dispose of the sediment in the river boat ramp parking area and surrounding ares and place new gravel in the parking area and seed disturbed areas.
|
Contact: Mark Johnson 515-250-3713 [email protected]
|
|
ADAMS -- PROJECT # 13-04-02-01 9/13/2012 Small Project Letting
|
MOUNT AYR FISHERIES MANAGEMENT UNIT
|
| GATE REPAIR AT LAKE ICARIA |
Proposal Guarantee: $0
|
Completion Date: 12/4/2012
|
| | Replace the lift stem and remount the lift stem support brackets in the drawdown structure.
|
Contact: Mark Johnson 515-250-3713 [email protected]
|
|
CERRO GORDO -- PROJECT # 13-03-17-02 9/13/2012 Small Project Letting
|
CLEAR LAKE STATE PARK
|
| SHOWER FLOOR REPLACEMENT |
Proposal Guarantee:
|
Completion Date: 10/12/2012
|
| | Project consists of removing a minimum of 1/2" of existing concrete floor in 4 shower stalls, placing a concrete overlay that will slope toward drains, and paint floors with a slip resistant paint system.
|
Contact: Mel Pacovsky 319-240-3553 [email protected]
|
|
DELAWARE -- PROJECT # 13-03-28-01 9/13/2012 Small Project Letting
|
BACKBONE STATE PARK
|
| REPLACE BARN SIDING AND WINDOWS |
Proposal Guarantee:
|
Completion Date: 11/30/2012
|
| | Project consists of placing stell siding and replacing window units on Park Office/Headquarters barn building.
|
Contact: Mel Pacovsky 319-240-3553 [email protected]
|
|
SAC -- PROJECT # 13-01-81-02 9/13/2012 Small Project Letting
|
BLACKHAWK LAKE
|
| BLACKHAWK LAKE CONCRETE WEIR REPAIR |
Proposal Guarantee: $0
|
Completion Date: 10/26/2012
|
| | This project is designed to repair deteriorated and delaminated concrete on the outlet weir of Blackhawk Lake in Sac County. Work under this project includes removal of the existing deteriorated/delaminated concrete and replacement with the specified repair mortar.
|
Contact: Jeff Felts [email protected]
|
|
WEBSTER -- PROJECT # 12-02-94-01 9/13/2012 Small Project Letting
|
DOLLIVER STATE PARK
|
| RV DUMP STATION & OTHER UPGRADES |
Proposal Guarantee: $0
|
Completion Date: 11/15/2012
|
| | This project entails the construction of a new RV dump station, camp pad and upgrades to the host camp site. Also included are plumbing repairs, new yard hydrants and a 50A service to the new camp site. Removal of the existing dump station and septic tank are a part of this project at Dolliver State Park in Webster County, Iowa.
|