PROJECTS LETTING -  July , 2011

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

APPANOOSE 11-05-04-18 DesJardins Renewable energy project - OEI demonstration grant- Wind and PV (REJECTED)-2011-07-21   Bid Completion detail
APPANOOSE 11-05-04-19 DesJardins Renewable energy project - OEI demonstration grant- PV (REJECTED)-2011-07-21   Bid Completion detail
APPANOOSE 11-05-04-20 DesJardins Renewable energy project - Honey Creek Vertical Wind Turbine (REJECTED)-2011-07-21   Bid Completion detail
CASS 12-04-15-01 Lake Anita State Park - Pave bicycle trail-2011-07-21   Bid Completion detail
JOHNSON 11-06-52-01 Lake Macbride State Park - New Boat House-2011-07-21   Bid Completion detail
POLK 11-05-77-07 Walnut Woods State Park - Lodge Interior Remodel-2011-07-21   Bid Completion detail
POLK 11-05-77-11 Walnut Woods State Park - Lodge Exterior Repairs-2011-07-21   Bid Completion detail
SHELBY 10-04-83-03 Prairie Rose State Park - Water control structures(duplicate)-2011-07-21   Bid Completion detail
WASHINGTON 11-06-92-06 Lake Darling - Low Water Crossing(re-bid)-2011-07-21   Bid Completion detail
WASHINGTON 10-06-92-13 Lake Darling - Jetty Reconstruction-2011-08-04   Bid Completion detail
WOODBURY 11-01-97-03 Waller WRP - Wetland Restoration-2011-08-04   Bid Completion detail
TAMA 12-05-86-02 Union Grove State Park - Removal of Storm Debris (Trees)-2011-08-10   Bid Completion detail
BLACK HAWK 09-03-07-14 George Wyth State Park - FEMA Repairs at Beach and Dike-2011-08-18   Bid Completion detail
BOONE 10-02-08-02 Ledges State Park - Henning Shelter Restoration-2011-08-18   Bid Completion detail
GREENE 12-02-37-01 Dunbar Slough - mod 2 struct + add channels-2011-08-18   Bid Completion detail
KOSSUTH 09-03-55-03 A.A. Call State Park - Cabin and Portal Restoration and Repair-2011-08-18   Bid Completion detail
POLK 12-02-77-03 Solar Light Installation at 4 State Parks - Install solar lights-2011-08-18   Bid Completion detail
WARREN 11-05-91-01 Ahquabi State Park - Shoreline Stabilization-2011-08-18   Bid Completion detail
WEBSTER 11-02-94-11 Brushy Creek SRA - 2010 FEMA Repairs-2011-08-18   Bid Completion detail




APPANOOSE -- PROJECT # 11-05-04-18                7/21/2011                Large Project Letting
DESJARDINS RENEWABLE ENERGY PROJECT
OEI DEMONSTRATION GRANT- WIND AND PV (REJECTED)
Proposal Guarantee: $5,000
Completion Date: 11/30/2011

   This project is more than just a renewable energy pilot. It will give the public hands-on witness to the power of renewable energy. The average state park visitor will get an opportunity to spend a period of time living in a space powered with renewables plus the means for personal exploration about how to make renewables work well. At the same time, measurable energy and cost savings accrue at an important, innovative state facility. Lewis and Clark: 5.52kW PV array and associated equipment.................Lump Sum 10kW horizontal axis wind turbine and 80 ft self supporting lattice tower and associated equipment...................Lump Sum Energy measurement system with interactive touch screen..Lump Sum Honey Creek Resort: One (1) 10kW horizontal axis wind turbine and 80 ft self supporting lattice tower and associated equipment........Lump Sum Five (5) 1.38kW PV arrays mounted to cabin roofs.........Lump Sum Energy measurement system with interactive touch screen..Lump Sum

ESTIMATED QUANTITIES:
    Wind & PV @ Honey Creek and Lewis and Clark SP     1 L.S.
Alternate
    Additional PV @ Lewis and Clark     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




APPANOOSE -- PROJECT # 11-05-04-19                7/21/2011                Large Project Letting
DESJARDINS RENEWABLE ENERGY PROJECT
OEI DEMONSTRATION GRANT- PV (REJECTED)
Proposal Guarantee: $5,000
Completion Date: 11/30/2011

   This project is more than just a renewable energy pilot. It will give the public hands-on witness to the power of renewable energy. The average state park visitor will get an opportunity to spend a period of time living in a space powered with renewables plus the means for personal exploration about how to make renewables work well. At the same time, measurable energy and cost savings accrue at an important, innovative state facility. E.B. Lyons: 2.76kW roof mounted PV array and associated equipment....Lump Sum Lake Darling: 2.76kW roof mounted PV array and associated equipment....Lump Sum Alternate: Additional 2.76kW roof mounted PV array and associated equipment....Lump Sum

ESTIMATED QUANTITIES:
    PV @ L.Darling and EB Lyons     1 L.S.
Alternate
    Additional PV @ EB Lyons     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




APPANOOSE -- PROJECT # 11-05-04-20                7/21/2011                Large Project Letting
DESJARDINS RENEWABLE ENERGY PROJECT
HONEY CREEK VERTICAL WIND TURBINE (REJECTED)
Proposal Guarantee: $5,000
Completion Date: 11/30/2011

   This project will demonstrate the difference in bat mortality between horizontal and vertical wind turbines. Appanoose county is in the Indiana Bat zone, which is a protected species, and the DNR would like to see if installing these towers lowered the rate of incident. Honey Creek Resort: One (1) 12kW horizontal axis wind turbine and 80 ft self supporting lattice tower and associated equipment........Lump Sum

ESTIMATED QUANTITIES:
    Vertical Wind Turbine and associated equipment     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




CASS -- PROJECT # 12-04-15-01                7/21/2011                Large Project Letting
LAKE ANITA STATE PARK
PAVE BICYCLE TRAIL
Proposal Guarantee: $20,000
Completion Date: 4/1/2012

   This project consists of blading and shaping over two miles of previously laid subgrade, paving of the subgrade including reinforcement steel, and shouldering with approximately 1317 tons of rock.

ESTIMATED QUANTITIES:
    Blading, Shaping, Rolling Subgrade     2.2 MI.
    Granular Surfacing, Class "A" Crushed Stone     1,317 Tons
    PCC Concrete Paving, 5" Depth     10,035 S.Y.
    Reinforcing Steel, Grade 40     30,159 LB.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JOHNSON -- PROJECT # 11-06-52-01                7/21/2011                Large Project Letting
LAKE MACBRIDE STATE PARK
NEW BOAT HOUSE
Proposal Guarantee: $10,000
Completion Date: 5/18/2012

   This project will consist of the demolition and removal of the existing boathouse/concession building, sidewalk and boardwalk as described in the documents. Construction of a new boathouse/concession building with adjacent site improvements. Utility work as described in the construction documents.

ESTIMATED QUANTITIES:
    Boat House Construction     1 L.S.
    Remove & Replace Unsatisfactory Foundation Soils     340 C.Y.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




SHELBY -- PROJECT # 10-04-83-03                7/21/2011                Large Project Letting
PRAIRIE ROSE STATE PARK
WATER CONTROL STRUCTURES(DUPLICATE)
Proposal Guarantee: $10,000
Completion Date: 5/15/2012

   This project consists of the construction of two concrete water control structures, two rip rap rock chutes with stoplog water control structures and incidental work as required by the Plans and/or the DNR Construction Inspector. Each of these is located at its own site making this project have four separate job sites, all located at Prairie Rose State Park in Shelby County, Iowa

ESTIMATED QUANTITIES:
    Site 1     1 Units
    Site Preparation     1 L.S.
    Concrete, Class "C" Structural     9.6 C.Y.
    Reinforcement, Grade 40     640 LB.
    6" Diameter Helical Intake     1 L.S.
    Site 2     1 Units
    Earthfill     1,939 C.Y.
    Core Trench Excavation     822 C.Y.
    Common Excavation -Rip-Rap     1,829 C.Y.
    Common Excavation- Inlet Channel     225 C.Y.
    Common Excavation -Pipe     195 C.Y.
    30" Diameter C.M.P. Stoplog Riser     1 L.S.
    Culvert, 18" Diameter C.M.P.     108 L.F.
    Revetment, Class "E" Rip Rap     1,941 Tons
    Geotextile Fabric     2,480 S.Y.
    Rip Rap Grout     400 C.Y.
    Seeding, Fertilizing, and Mulching     1 L.S.
    Site 3     1 Units
    Earthfill     350 C.Y.
    Core Trench Excavation     852 C.Y.
    Common Excavation- Rip Rap     3,315 C.Y.
    Common Excavation- Inlet Channel     267 C.Y.
    Common Excavation- Pipe     169 C.Y.
    30" Diameter C.M.P. Stoplog Riser     1 L.S.
    Culvert, 18" Diameter C.M.P.     98 L.F.
    Revetment, Class "E" Rip Rap     2,397 Tons
    Geotextile Fabric     2,965 S.Y.
    Rip Rap Grout     500 C.Y.
    Seeding, Fertilizing, and Mulching     1 L.S.
    Site 4     1 Units
    Site Preparation     1 L.S.
    Concrete, Class "C" Structural     3.3 C.Y.
    Reinforcement, Grade 40     262 LB.
    6" Diameter Helical Intake     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




TAMA -- PROJECT # 12-05-86-02                8/10/2011                Large Project Letting
UNION GROVE STATE PARK
REMOVAL OF STORM DEBRIS (TREES)
Proposal Guarantee: $7,500
Completion Date: 11/30/2011

   This project consists of removal of trees damaged by a July 11 windstorm within identified areas of the park and incidental work as required by the Plans and/or the DNR Construction Inspector.

ESTIMATED QUANTITIES:
    Tree Removal     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BLACK HAWK -- PROJECT # 09-03-07-14                8/18/2011                Large Project Letting
GEORGE WYTH STATE PARK
FEMA REPAIRS AT BEACH AND DIKE
Proposal Guarantee: $5,000
Completion Date: 12/1/2011

   This project consists of repairs to an existing beach and earthfill dike, construction of a concrete access roadway and parking area, buried electrical transmission line and incidental work as required by the Plans and/or the DNR Construction Inspector.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Earthfill, Borrow, Off Site     1,500 C.Y.
    Concrete Rubble Removal     20 C.Y.
    Concrete Pavement Removal     305 S.Y.
    Beach Sand, Furnish and Place     1,000 Tons
    P.C. Concrete Roadway and Parking, 6"     510 S.Y.
    P.C. Concrete Walks, 6"     110 S.Y.
    2" Black/Red Stripe Poly Inner Duct     960 L.F.
    2" X 36" 90 Degree Sweeps     2 Each
    2" Duraline Comfit Couplings     2 Each
    Distribution Panel, 200 Amp     1 L.S.
    Inspect Water and Sewer Lines     1 L.S.
    Clean and Inspect Lift Station     1 L.S.
    Topsoil, Furnish and Place     60 C.Y.
    Remove/Dispose of Existing Fence     370 L.F.
    Chain Link Fence, 6' Height     370 L.F.
    Chain Link Gate, 6' H X 8' W     1 Each
    Seed, Fertilize and mulch     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




GREENE -- PROJECT # 12-02-37-01                8/18/2011                Large Project Letting
DUNBAR SLOUGH
MOD 2 STRUCT + ADD CHANNELS
Proposal Guarantee: $5,000
Completion Date: 12/1/2012

   This project consists of the addition of fish "fingers" and fish "bars" to limit rough fish access to the slough, new overflow additions to existing structures, wetland restoration of the channel between pools and incidental work as required by the Plans and/or the DNR Construction Inspector.

ESTIMATED QUANTITIES:
    Excavation, Channel     9,271 C.Y.
    Excavation, Structural     274 C.Y.
    Concrete, Structural     26 C.Y.
    Culvert, Precast RCB, 12' X 4'     24 L.F.
    Structural Steel, Framing     1 L.S.
    Structural Steel, Vert. Channels & Bars     1 L.S.
    Structural Aluminum, Fingers & Bars Assys.     1 L.S.
    Stoplog, Aluminum, As Per Plan     113 Each
    Grating, Steel, Galvanized     610 S.F.
    Handrail, Steel Tube, Galvanized     334 L.F.
    Revetment, Class "D" Riprap     110 Tons

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




WARREN -- PROJECT # 11-05-91-01                8/18/2011                Large Project Letting
AHQUABI STATE PARK
SHORELINE STABILIZATION
Proposal Guarantee: $5,000
Completion Date: 12/15/2011

   This project consists of the placement of riprap revetment along portions of the lake shoreline, and incidental work as required by the Plans and/or the DNR Construction Inspector.

ESTIMATED QUANTITIES:
    Revetment, Class "D" Riprap     5,025 Tons
    Enginering Fabric     6,304 S.Y.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POLK -- PROJECT # 11-05-77-07                7/21/2011                Small Project Letting
WALNUT WOODS STATE PARK
LODGE INTERIOR REMODEL
Proposal Guarantee:
Completion Date: 2/29/2012

   This project consists of the remodeling of the interior of the lodge, and other items designated by the plans and specifications, and or the DNR Construction Inspector.

Contact:
Jason Kruse
(515) 250-3707
[email protected]




POLK -- PROJECT # 11-05-77-11                7/21/2011                Small Project Letting
WALNUT WOODS STATE PARK
LODGE EXTERIOR REPAIRS
Proposal Guarantee:
Completion Date: 11/15/2011

   This project consists of the re-pointing of damaged brick and stone mortor, replacement of damaged flashing, joint sealer, and other items designated by the plans and specifications, and or the DNR Construction Inspector.

Contact:
Jason Kruse
(515) 250-3707
[email protected]




WASHINGTON -- PROJECT # 11-06-92-06                7/21/2011                Small Project Letting
LAKE DARLING
LOW WATER CROSSING(RE-BID)
Proposal Guarantee:
Completion Date: 9/15/2011

   construction of a low water stream crossing consisting of two 18" culverts covered by macadam stone and concrete.

Contact:
David Heer
(515) 250-3719
[email protected]




WASHINGTON -- PROJECT # 10-06-92-13                8/4/2011                Small Project Letting
LAKE DARLING
JETTY RECONSTRUCTION
Proposal Guarantee:
Completion Date: 9/30/2011

   This project consists of the raising five existing fishing jetties two feet above their current elevation, along with any incidental work as required by plans and/or DNR inspector.

Contact:
David Heer
(515) 250-3719
[email protected]




WOODBURY -- PROJECT # 11-01-97-03                8/4/2011                Small Project Letting
WALLER WRP
WETLAND RESTORATION
Proposal Guarantee: $0
Completion Date: 11/28/2011

   This project involves the restoration of several wetland pool areas through use of ditch plugs, and shallow water excavation. This project is located on the Waller Tract of the Table Marsh WMA (near Hornick, IA) Work under this project includes earthfill, excavation, and seeding.

Contact:
Jeff Felts
515-250-3712
[email protected]




BOONE -- PROJECT # 10-02-08-02                8/18/2011                Small Project Letting
LEDGES STATE PARK
HENNING SHELTER RESTORATION
Proposal Guarantee:
Completion Date: 11/17/2011

   HENNING SHELTER IS A LANDMARK WITHIN LEDGES STATE PARK AND HAS RECENTLY UNDERGONE A COMPLETE DISMANTLEING, RELOCATION OUT OF THE FLOOD PLAIN. SINCE THIS RELOCATION SOME OF THE WOOD STRUCTURAL MEMBERS HAVE GONE INTO DISREPAIR AND NEED TO BE RESTORED BACK TO THEIR FORMER APPEARANCE AS WELL AS HAVE PREVENTATIVE MEASURES DESIGNED SO THAT THIS DOES NOT HAPPEN IN THE FUTURE. THE LOG EXPOSED RAFTER AND PURLIN TAILS HAVE ROTTED AWAY AND WILL BE CAREFULLY REPLACED. ALSO, THE WOOD COLUMNS SUPPORTING THE WOOD BEAM LINTELS WILL BE TRIMMED AND PLACED ON A CONCRETE CURB TO ALLOW MOISTURE TO PASS BELOW.

Contact:
Don Labate
515-250-3714
[email protected]




KOSSUTH -- PROJECT # 09-03-55-03                8/18/2011                Small Project Letting
A.A. CALL STATE PARK
CABIN AND PORTAL RESTORATION AND REPAIR
Proposal Guarantee:
Completion Date: 10/27/2011

   AMBROSE A. CALL STATE PARK IS THE ORIGINAL LOCATION OF AMBROSE'S CLAIM IN IOWA. THE CURRENT CABIN IS NOT THE ORIGINAL CALL CABIN BUT ONE OF THE HISTORIC PERIOD AND IS SITED APPROXIMATELY ON THE VERY LOCATION CALL PLACED HIS CABIN. THE CABIN NEEDS MAJOR RESTORATION IN THE FORM OF NEW CHINKING AND DAUBING, THE WOOD NEEDS CLEANING AND SEALING, THE FOUNDATION NEEDS TO BE REMOVED AND REPLACED AND THE ROOF NEEDS REPLACEMENT.

Contact:
Don Labate
515-250-3714
[email protected]




POLK -- PROJECT # 12-02-77-03                8/18/2011                Small Project Letting
SOLAR LIGHT INSTALLATION AT 4 STATE PARKS
INSTALL SOLAR LIGHTS
Proposal Guarantee:
Completion Date: 9/29/2011

   Installation of 11 solar lights at four locations. The contractor will need to go through a certified training/testing provided by the Inovous company by CD and online testing to insure the integrity of the warranty.

Contact:
Don Labate
515-250-3714
[email protected]




WEBSTER -- PROJECT # 11-02-94-11                8/18/2011                Small Project Letting
BRUSHY CREEK SRA
2010 FEMA REPAIRS
Proposal Guarantee:
Completion Date: 10/27/2011

   Scope of work includes the repair of trails and placement of rock surfacing and riprap at Brushy Creek State Recreation Area.

Contact:
Don Labate
515-250-3714
[email protected]