PROJECTS LETTING -  June , 2013

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

DES MOINES 12-06-29-01 Geode State Park - Sewage Treatment-2013-06-20   Bid Completion detail
DICKINSON 12-01-30-13 Great Lakes Wildlife Unit - Okoboji View Wetlands Restoration-2013-06-20   Bid Completion detail
DUBUQUE 13-03-31-01 Mines of Spain Recreation Area - Woodland Walk Kiosk at EB Lyons-2013-06-20   Bid Completion detail
LUCAS 13-05-59-01 Colyn WMA - Rathbun Headquarters Addition-2013-06-20   Bid Completion detail
TAMA 12-05-86-05 Iowa River Wildlife Unit - Otter Creek WMA HQ Remodeling-2013-06-20   Bid Completion detail
FREMONT 12-04-36-02 Waubonsie State Park - Boat Ramp & Shoreline Armoring-2013-06-27   Bid Completion detail
UNION 12-04-88-03 Green Valley State Park - Trail Construction REBID-2013-07-09   Bid Completion detail
UNION 12-04-88-03 Green Valley State Park - Trail Construction REBID - Duplicate-2013-07-09   Bid Completion detail
BENTON 13-06-06-01 Cedar Rock Visitors Center - Construct & Develop New Public Water Well-2013-07-11   Bid Completion detail
CERRO GORDO 12-03-17-07 Clear Lake Dredge Spoil Site - Lower Containment Dikes-2013-07-11   Bid Completion detail
APPANOOSE 13-05-04-01 Stephens State Forest - Sediment Basin-2013-07-18   Bid Completion detail
JACKSON 12-06-49-01 Big Mill WMA - Big Mill Creek Restoration-2013-07-18   Bid Completion detail
LUCAS 11-05-59-01 Red Haw State Park - Sediment Basins-2013-07-18   Bid Completion detail
POLK 12-02-77-13 Big Creek State Park - Pump Station & Force Main-2013-07-18   Bid Completion detail




DICKINSON -- PROJECT # 12-01-30-13                6/20/2013                Large Project Letting
GREAT LAKES WILDLIFE UNIT
OKOBOJI VIEW WETLANDS RESTORATION
Proposal Guarantee: $25,000
Completion Date: 12/7/2013

   Construction of a new wetland complex containing 19 basin areas consisting of new water control structures, sheet pile dikes, earthen dikes, farm tile day lighting, excavation, compaction, seeding & mulching on the west side of West Lake Okoboji in Dickinson County as shown in the project documents and as directed by the DNR Inspector.

ESTIMATED QUANTITIES:
Basin 1 
    Site Preparation     1 L.S.
    Inline WCS w/Stoplogs - 11' x 15" PVC     1 Each
    Protective Casing on WCS     1 Each
    15" Dual-Walled HDPE Culvert     126 L.F.
    18" CMP Culvert     40 L.F.
    Anti-seep Collar     1 Each
    18" Animal Guard on CMP     1 Each
    18" Heavy Duty Bar Guard on CMP     1 Each
    Class "E" Revetment     300 Tons
    Revetment Mortar     56 C.Y.
    PZ-22 Sheet Piling 3/8"     2,800 S.F.
    Sheet Pile Cap     2,750 LB.
    Tile Break     1 Each
    Tile Investigation     100 L.F.
    Earth Fill & Compaction     3,200 C.Y.
    36" HDPE Culvert     258 L.F.
    Class "E" Revetment     7 Tons
    Engineering Fabric     518 S.Y.
Basin 2 
    Clearing & Grubbing Trees     50 Each
    5" PCC Spillway     227 S.Y.
    Earth Fill & Compaction     1,560 C.Y.
    Tile Break     1 Each
    Tile Investigation     100 L.F.
    Inline WCS w/ Stoplogs-4'x24" PVC     1 Each
    Protective Casing on WCS     1 Each
    30" Animal Guard on CMP     1 Each
    30" Heavy Duty Bar Guard on CMP     1 Each
    10" Heavy Duty Bar Guard on Tile     1 Each
    24" Dual-Walled HDPE Culvert     28 L.F.
    30" CMP     34 L.F.
    Anti-seep Collar     1 Each
    Class E Revetment     7 Tons
    Engineering Fabric     18 S.Y.
Basin 3 
    Aluminum Toewall Drop Spillway     1 Each
    18" Dual-Walled HDPE Culvert     49 L.F.
    21" CMP Culvert     34 L.F.
    Anti-seep Collar     1 Each
    Protective Casing on WCS     1 Each
    21" Animal Guard on CMP      1 Each
    21" Animal Guard on CMP      1 Each
    Class E Revetment     7.5 Tons
    Engineering Fabric     20 S.Y.
    Excelsior Matting & Seeding     750 S.F.
    Earth Fill & Compaction     10,400 C.Y.
    Inline WCS w/ Stoplogs-10'x18" PVC     1 Each
    Tile Break     2 Each
    Tile Investigation     300 L.F.
Basin 4 
    Earth Fill & Compaction     700 C.Y.
    Tile Break     2 Each
    Tile Investigation     300 L.F.
    10" CMP     16 L.F.
Basin 5 
    Aluminum Toewall Drop Spillway     1 Each
    Earth Fill & Compaction     1,900 C.Y.
    Excelsior Matting & Seeding     380 S.F.
    Tile Break     2 Each
    Tile Investigation     200 L.F.
Basin 6 
    Earth Fill & Compaction     2,600 C.Y.
    12" Non-Perforated, Dual Walled HDPE Tubing     564 L.F.
    Tile Break     3 Each
    Tile Investigation     300 L.F.
Basin 7 
    Earth Fill & Compaction     2,100 C.Y.
    Excelsior Matting & Seeding     4,104 S.F.
    Tile Break     1 Each
    Tile Investigation     400 L.F.
Basin 8 
    Aluminum Toewall Drop Spillway     1 Each
    Class E Revetment     10 Tons
    Engineering Fabric     19 S.Y.
    Excelsior Matting & Seeding     150 S.F.
    Earth Fill & Compaction     3,400 C.Y.
    Tile Break     2 Each
    Tile Investigation     200 L.F.
    15" Dual Walled Perforated HDPE Tubing     667 L.F.
    6" Dual Walled Perforated HDPE Tubing     234 L.F.
    18" Dual-Walled HDPE Culvert     37 L.F.
    Anti-seep Collar     1 Each
    Protective Casing on WCS     1 Each
    21" Animal Guard on CMP      1 Each
    21" Heavy Duty Bar Guard on CMP     1 Each
    21" CMP Culvert     38 L.F.
    Inline WCS w/ Stoplogs-5'x18" PVC     1 Each
Basin 9 
    Earth Fill & Compaction     1,100 C.Y.
    Tile Break     1 Each
    Tile Investigation     100 L.F.
Basin 10 
    Earth Fill & Compaction     500 C.Y.
    Tile Break     2 Each
    Tile Investigation     200 L.F.
Basin 11 
    Earth Fill & Compaction     650 C.Y.
    Excelsior Matting & Seeding     90 S.F.
    Tile Break     2 Each
    Tile Investigation     200 L.F.
    12" Hickenbottom Surface Inlet     1 Each
    8" Dual Walled, Non-Perforated HDPE Tubing     403 L.F.
Basin 15 
    Earth Fill & Compaction     400 C.Y.
    Tile Break     1 Each
    Tile Investigation     100 L.F.
Basin16 
    Earth Fill & Compaction     2,000 C.Y.
    Tile Break     1 Each
    Tile Investigation     200 L.F.
Basin 17 
    Aluminum Toewall Drop Spillway     1 Each
    8" Dual Walled, Non-Perforated HDPE Pipe     430 L.F.
    18" Dual-Walled Non-Perforated HDPE Pipe     1,250 L.F.
    18" Dual-Walled HDPE Culvert     54 L.F.
    21" CMP Culvert     40 L.F.
    Protective Casing on WCS     1 Each
    21" Animal Guard on CMP      1 Each
    21" Heavy Duty Bar Guard on CMP     1 Each
    Anti-seep Collar     1 Each
    Class E Revetment     7 Tons
    Engineering Fabric     19 S.Y.
    Earth Fill & Compaction     2,700 C.Y.
    Inline WCS w/ Stoplogs-6'x18" PVC     1 Each
    Tile Break     2 Each
    Tile Investigation     100 L.F.
    24" CMP     16 L.F.
    24" Animal Guard on CMP     1 Each
Basin 18 
    6" Perforated HDPE Tubing     1,535 L.F.
    Tile Break     1 Each
    Tile Investigation     100 L.F.
Basin 19 
    Class E Revetment     7 Tons
    Engineering Fabric     19 S.Y.
    Earth Fill & Compaction     3,100 C.Y.
    Excelsior Matting & Seeding     370 S.F.
    Tile Break     2 Each
    Tile Investigation     200 L.F.
    Inline WCS w/ Stoplogs-5'x18" PVC     1 Each
    Protective Casing on WCS     1 Each
    21" Animal Guard on CMP      1 Each
    21" Heavy Duty Bar Guard on CMP     1 Each
    18" Dual-Walled HDPE Culvert     25 L.F.
    Anti-seep Collar     1 Each
    21" CMP Culvert     40 L.F.
Basin 20 
    Earth Fill & Compaction     1,100 C.Y.
    Excelsior Matting & Seeding     1,258 S.F.
    Tile Break     1 Each
    Tile Investigation     100 L.F.
Basin 21 
    Tile Break     1 Each
    Tile Investigation     100 L.F.
Basin 22 
    Earth Fill & Compaction     3,130 C.Y.
    Excelsior Matting & Seeding     200 S.F.
    Tile Break     1 Each
    Tile Investigation     400 L.F.
    Inline WCS w/ Stoplogs-8'x10" PVC     1 Each
    Protective Casing on WCS     1 Each
    12 HDPE Culvert     93 L.F.
    Anti-seep Collar     1 Each
    12" Heavy Duty Bar Guard on CMP     1 Each
    12" CMP     16 L.F.
    12" Animal Guard on CMP     1 Each
SWPPP 
    Install & Monitor     1 Each
    Silt Fence     3,500 L.F.
Additional Costs 
    Construction Entrance     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




LUCAS -- PROJECT # 13-05-59-01                6/20/2013                Large Project Letting
COLYN WMA
RATHBUN HEADQUARTERS ADDITION
Proposal Guarantee: $5,000
Completion Date:

   Rathbun Wildlife Headquarters is located at the Colyn WMA, near the town of Lucas in Lucas County, IA. This project consists of the construction of a one story, pre-engineered S.I.P. (structural insulated panel) building addition with a metal roof and metal siding, approximately 24'-0" x 40'-0", including one heated bay with an overhead door, egress door and a tool storage closet. Project number 13-05-59-01

ESTIMATED QUANTITIES:
 
    4" PVC SDR 23.5     20 L.F.
    30" PRECAST CONCRETE SPLASH BLOCKS     1 Each
    4" RAT GUARD (AGRI DRAIN RG04, OR EQUAL)     1 Each
    1" PE WATER LINE     32 L.F.
    YARD HYDRANT (WOODFORD MODEL S-3, OR EQUAL)     1 Each
    6" REINFORCED PCC     64 S.Y.
    8" FILTER SOCK     80 L.F.
    LP TANK (PER LOCAL LP SUPPLIER RECOMMENDATIONS) 5" CONCRETE PAD, 5'-0"X10'-0" AND LP SUPPLY LINE TO BUILDING ADDITION     1 L.S.
    GRADING     1 L.S.
    PAD GRANULAR BASE     1 L.S.
    SEEDING     1 L.S.
    CONSTRUCTION STAKING     1 L.S.
    BUILDING AND ALL ASSOCIATED EQUIPMENT (ARCHITECTURAL, MECHANICAL & ELECTRICAL)     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




TAMA -- PROJECT # 12-05-86-05                6/20/2013                Large Project Letting
IOWA RIVER WILDLIFE UNIT
OTTER CREEK WMA HQ REMODELING
Proposal Guarantee: $5,000
Completion Date: 1/31/2014

   OTTER CREEK HEADQUARTERS IS SITUATED ALONG THE OTTER CREEK WILDLIFE MANAGEMENT AREA IN TAMA COUNTY, IOWA. THE CURRENT OFFICE / SHOP AREA WAS BUILT IN THE 1960'S AND IS IN NEED OF RENOVATION AND RECONFIGURATION FOR CURRENT STAFF NEEDS. ONE OF THE GARAGE BAYS WILL BE TURNED INTO A CONFERENCE / BREAK AREA, AS WELL AS A NEW SUPERVISOR'S OFFICE AND ADA COMPLIANT RESTROOM. THE CURRENT OFFICE / KITCHENETTE WILL BE RENOVATED INTO A NEW OPEN OFFICE LAYOUT. A NEW MECHANICAL AND ELECTRICAL SERVICE WILL BE INCLUDED IN THIS PACKAGE AS WELL.

ESTIMATED QUANTITIES:
    ALL BUILDING RENOVATIONS SHOWN IN PLAN, INCLUDING ARCHITECTURAL, MECHANICAL AND ELECTRICAL CHANGES     1 L.S.
ALTERNATE#1 
Alternate
    REPLACE ALL WINDOWS AS SHOWN ON PLANS     1 L.S.
ALTERNATE#2 
Alternate
    INSTALL NEW OVERHEAD RADIANT HEATING SYSTEM IN SHOP 107 AND MOVE AND REINSTALL EXISTING OVERHEAD FORCED AIR FURNACE IN STORAGE 108     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




UNION -- PROJECT # 12-04-88-03                7/9/2013                Large Project Letting
GREEN VALLEY STATE PARK
TRAIL CONSTRUCTION REBID
Proposal Guarantee: $30,000
Completion Date: 6/1/2014

   To install an 8-foot wide 5-inch thick reinforced PCC recreational trail (3.48 miles in total length: 3.13 miles of actual construction and 0.35 miles of shared roadway) for Green Valley State Park, Union County, Iowa. This project includes, but is not limited to: clearing, demolition, grading, culvert pipes, PCC trail construction, seeding/fertilizing/mulching disturbed areas, signage.

ESTIMATED QUANTITIES:
 
    Clearing and Grubbing     1 L.S.
    Demolition     1 L.S.
    Grading     1 L.S.
    Seeding, Fertilizing and Mulching     1 L.S.
    8-inch Filter Sock     720 L.F.
    Granular Base     2,672 C.Y.
    5-inch Reinforced PCC Pavement     14,814 S.Y.
    12-inch CMP     216 L.F.
    12-inch CMP FES     15 Each
    15-inch CMP     272 L.F.
    15-inch CMP FES     19 Each
    18-inch CMP     57 L.F.
    18-inch CMP FES     4 Each
    18-inch 45-Degree CMP Bend     1 Each
    21-inch Arch CMP     224 L.F.
    21-inch Arch CMP FES     16 Each
    24-inch Arch CMP     84 L.F.
    24-inch Arch CMP FES     6 Each
    48-inch Arch CMP     128 L.F.
    48-inch RCP Class III     64 L.F.
    Class 'E' Riprap     775 Tons
    Pipe Bollards     7 Each
    Precast Concrete Parking Wheel Stops     10 Each
    Bicycle Traffic Signage     1 L.S.
    Traffic Control     1 L.S.
    Construction Staking     1 L.S.
    NPDES Permit & SWPPP     1 L.S.
    Mobilization     1 L.S.
Alternate
    Clearing and Grubbing     1 L.S.
Alternate
    Demolition      1 L.S.
Alternate
    Grading     1 L.S.
Alternate
    Seeding, Fertilizing and Mulching     1 L.S.
Alternate
    8-inch Filter Sock      770 L.F.
Alternate
    Granular Base     2,801 C.Y.
Alternate
    5-inch Reinforced PCC Pavement     15,741 S.Y.
Alternate
    12-inch CMP     216 L.F.
Alternate
    12-inch CMP FES     15 Each
Alternate
    15-inch CMP     272 L.F.
Alternate
    15-inch CMP FES     19 Each
Alternate
    18-inch CMP     99 L.F.
Alternate
    18-inch CMP FES     7 Each
Alternate
    18-inch 45-Degree CMP Bend     1 Each
Alternate
    21-inch Arch CMP     224 L.F.
Alternate
    21-inch Arch CMP FES     16 Each
Alternate
    24-inch Arch CMP     84 L.F.
Alternate
    24-inch Arch CMP FES     6 Each
Alternate
    48-inch Arch CMP     128 L.F.
Alternate
    48-inch RCP Class III     64 L.F.
Alternate
    Class 'E' Riprap     775 Tons
Alternate
    Pipe Bollards     7 Each
Alternate
    Precast Concrete Parking Wheel Stops     10 Each
Alternate
    Bicycle Traffic Signage     1 L.S.
Alternate
    Traffic Control     1 L.S.
Alternate
    Construction Staking     1 L.S.
Alternate
    NPDES Permit & SWPPP     1 L.S.
Alternate
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JACKSON -- PROJECT # 12-06-49-01                7/18/2013                Large Project Letting
BIG MILL WMA
BIG MILL CREEK RESTORATION
Proposal Guarantee: $5,000
Completion Date: 11/30/2013

   This project consists of excavation, streambank restoration, and incidental work as required by the Plans and/or the DNR Construction Inspector.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    EXCAVATION, SPOIL     12,000 C.Y.
    SEED & MULCH     7.25 Acres
    PLANTING, SWAMP WHITE OAK SAPLING      50 Each
    PLANTING, COTTONWOOD SAPLING     50 Each
    SILT FENCE     1,200 L.F.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




LUCAS -- PROJECT # 11-05-59-01                7/18/2013                Large Project Letting
RED HAW STATE PARK
SEDIMENT BASINS
Proposal Guarantee: $7,000
Completion Date: 11/30/2013

   CONSTRUCTION OF GRADE STABILIZATION STRUCTURES, SEDIMENT BASINS, AND OTHER INCIDENTAL WORK AS REQUIRED BY THE IDNR CONSTRUCTION INSPECTOR.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    CLEARING & GRUBBING     15.8 Acres
    SEEDING     12 Acres
    CORE TRENCH EXCAVATION     4,600 C.Y.
    STRUCTURE EXCAVATION     1,625 C.Y.
    EARTH FILL     34,320 C.Y.
    DIVERSION     1,230 L.F.
    6" SMOOTH STEEL PIPE     273 L.F.
    10" SMOOTH STEEL PIPE     330 L.F.
    12" SMOOTH STEEL PIPE     194 L.F.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POLK -- PROJECT # 12-02-77-13                7/18/2013                Large Project Letting
BIG CREEK STATE PARK
PUMP STATION & FORCE MAIN
Proposal Guarantee: $25,000
Completion Date:

   The project consists of construction of a new wastewater pump station and 3-inch diameter force main on the east side of Big Creek Lake as shown in the project documents and as directed by the DNR Inspector.

ESTIMATED QUANTITIES:
    Submersible Pump Package     1 L.S.
    3" HDPE Force Main     11,975 L.F.
    Wet Well Structure     11 L.F.
    Flow Meter Structure     7 L.F.
    New Air Relief Valves     6 Each
    Connect Existing AR Valves to New Force Main     3 Each
    Magnetic Flow Meter and Data Logger     1 L.S.
    Open Trench Installation of Force Main     3,840 L.F.
    Open Trench Installation of 12" HDPE Gravity Sewer     20 L.F.
    Trenchless Installation of Force Main     400 L.F.
    Installation of 3" Force Main inside Existing 6" Carrier Pipe     7,735 L.F.
    Electric Service     1 L.S.
    Manual Transfer Switch     1 L.S.
    Generator Receptacle     1 L.S.
    Fencing with Gates     1,340 L.F.
    Seeding, Fertilizing & Mulching     2 Acres
    Traffic Control     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




DES MOINES -- PROJECT # 12-06-29-01                6/20/2013                Small Project Letting
GEODE STATE PARK
SEWAGE TREATMENT
Proposal Guarantee:
Completion Date: 8/31/2013

   The project involves replacing pumps in an existing Lift Station and directional boring a 2500 ft. of 2" HDPE Forcemain and connecting to an existing manhole.

Contact:
Bruce Flippin
515-689-8009
bruce.flippin@dnr.iowa.gov




DUBUQUE -- PROJECT # 13-03-31-01                6/20/2013                Small Project Letting
MINES OF SPAIN RECREATION AREA
WOODLAND WALK KIOSK AT EB LYONS
Proposal Guarantee: $0
Completion Date: 8/16/2013

   THIS INTERPRETIVE KIOSK WILL ASSIST PARK VISITORS WITH WAY-FINDING, INTERPRETIVE ANALYSIS AND EXPLANATION OF PARK FEATURES. THIS NEW DESIGN IS PART OF THE NEW PARKS DESIGN GUIDE WHICH WILL FIT WITH THE NEW PARK IMAGE FOR IOWA. THESE WILL BE LOCATED AT EB LYONS NATURE CENTER ON THE NEW WOODLAND WALK TRAIL IN DUBUQUE COUNTY, IOWA. CONTRACTOR SHALL BE PRESENT ON SITE FOR THE DAY OF THE BUILD WITH THEIR MASON (SEPTEMBER 4, 2013 FROM 12:00PM - FINISH). CONTRACTOR SHALL PROVIDE ALL TOOLS, MATERIALS AND EQUIPMENT NECESSARY TO COMPLETE THE PROJECT ON THE "BUILD DAY". THE CONTRACTOR SHALL CONSTRUCT THE KIOSK AND DISASSEBLE PRIOR TO THE "BUILD DAY" TO ENSURE QUALITY CONSTRUCTION. COORDINATE WITH FIELD INSPECTOR AND ARCHITECT FOR PRECISE LOCATION OF KIOSK

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




FREMONT -- PROJECT # 12-04-36-02                6/27/2013                Small Project Letting
WAUBONSIE STATE PARK
BOAT RAMP & SHORELINE ARMORING
Proposal Guarantee: $0
Completion Date: 10/31/2013

   This project involves paving a boat ramp, placement of riprap near the boat ramp, and incidental items as required by the project documents and the IDNR Construction Inspector at Waubonsie State Park in Fremont County, Iowa.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov




BENTON -- PROJECT # 13-06-06-01                7/11/2013                Small Project Letting
CEDAR ROCK VISITORS CENTER
CONSTRUCT & DEVELOP NEW PUBLIC WATER WELL
Proposal Guarantee:
Completion Date: 9/13/2013

   Project consists of constructing and developing a new public water well, install new water and electrical services from well to Visitors Center and connecting new system to existing inside the Visitors Center. Plug existing well & disconnect existing services.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




CERRO GORDO -- PROJECT # 12-03-17-07                7/11/2013                Small Project Letting
CLEAR LAKE DREDGE SPOIL SITE
LOWER CONTAINMENT DIKES
Proposal Guarantee: $0
Completion Date: 9/20/2013

   Project consists of lowering (approximatelly 5') & reshaping 7300 LF of dikes; removing,salvaging & stockpiling 8 steel drain pipes, and removing outflow structure. Disturbed areas will be seeded with a stabilizing crop seeding.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




APPANOOSE -- PROJECT # 13-05-04-01                7/18/2013                Small Project Letting
STEPHENS STATE FOREST
SEDIMENT BASIN
Proposal Guarantee: $0
Completion Date: 10/15/2013

   This project consists of construction of a sediment basin in the Stephens State Forest northeast of Unionville, Iowa. Send an email to request plans & specifications.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov