PROJECTS LETTING -  June , 2026

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

DICKINSON 26-01-30-01 Great Lakes Wildlife Unit - Hodge WPA Wetland Restoration -2026-06-11   
ALLAMAKEE 25-03-03-01 Yellow River State Forest - Paint Creek Streambank Improvements - Phase 2-2026-06-18   
CASS 25-04-15-01 Lake Anita State Park - Sewer Improvements-2026-06-18   
DAVIS 26-05-26-01 Lake Wapello State Park - Wastewater Improvements-2026-06-18   
DICKINSON 25-01-30-05 Dickinson County Wildlife Areas and State Parks - Road Maintenance-2026-06-18   
GUTHRIE 21-04-39-01 Springbrook Education Center - Complex Demolition-2026-06-18   
GUTHRIE 25-04-39-02 Springbrook State Park - Accessibility Improvements-2026-06-18   
JACKSON 25-06-49-05 Green Island and Princeton WMA - Flood Repair-2026-06-18   
BUCHANAN 23-03-10-02 Cedar Rock State Park - Road Maintenance REBID-2026-06-25   




ALLAMAKEE -- PROJECT # 25-03-03-01                6/18/2026                Large Project Letting
YELLOW RIVER STATE FOREST
PAINT CREEK STREAMBANK IMPROVEMENTS - PHASE 2
Proposal Guarantee: $6,250
Completion Date: 12/11/2026

   This project includes re-establishing eroded streambanks and placement of cross vanes, bendway weirs and revetment armoring on a section of Paint Creek within Yellow River State Forest.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Clearing and Grubbing     1 L.S.
    Class 10 Excavation     2,540 C.Y.
    Wattles, 9"     550 L.F.
    Revetment, Class E     330 Tons
    Revetment, Class B     480 Tons
    Large Boulders     100 Each
    Erosion Matting     2,048 S.Y.
    Temporary Seeding     0.5 Acres
    Permanent Seeding     0.5 Acres
    Mobilizations, Emergency Erosion Control     1 Each

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




CASS -- PROJECT # 25-04-15-01                6/18/2026                Large Project Letting
LAKE ANITA STATE PARK
SEWER IMPROVEMENTS
Proposal Guarantee: $37,500
Completion Date: 4/30/2027

   This project primarily consists of removing 4" VCP sewers, installing 8" PVC sewers, and replacing sanitary sewer manholes in the campground. Some water main will be removed and replaced. Some water mains, sewers, manholes, and one septic tank will be abandoned and removed. The project also includes full depth patches, seeding, an NPDES General Permit #2, and a SWPPP. All work, except seeding, shall be completed between September 8, 2026 and the intermediate completion date of March 31, 2027.

ESTIMATED QUANTITIES:
    2010, 1.08, A - Clearing & Grubbing - Tree Removal     297 Units
    3010, 1.08, F - Trench Compaction Testing     1 L.S.
    4010, 1.08, A - Sanitary Sewer Gravity Main, Trenched, 8"     1,990 L.F.
    4010, 1.08, A - Sanitary Sewer Gravity Main, Trenched, C900, 8"     50 L.F.
    4010, 1.08, H - Removal of Sanitary Sewer     1,530 L.F.
    4010, 1.08, K - Sanitary Sewer Abandonment, Plug, 4"     26 Each
    4060, 1.08, A - Sanitary Sewer Video Inspection     540 L.F.
    5010, 1.08, A - Water Main, Trenched, 3"     50 L.F.
    5010, 1.08, F - Water Main Abandonment, Cap, LE 3"     6 Each
    5010, 1.08, H - Water Main Removal     50 L.F.
    6010, 1.08, A - Manhole, SW-301, 48"     3 Each
    6010, 1.08, A - Manhole, SW-303, 48"     5 Each
    6010, 1.08, G - Connection to Existing Manhole     3 Each
    6010, 1.08, H - Remove Manhole, 48"     19 Each
    7040, 1.08, A - Full Depth Patches, PCC     13 S.Y.
    7040, 1.08, A - Full Depth Patches, HMA     178 S.Y.
    8030, 1.08, A - Temporary Traffic Control     1 L.S.
    9010, 1.08, A - Seeding and Mulching for Conventional Seeding, Native Seed Mix     0.55 Acres
    9010, 1.08, B - Seeding, Fertilizing, and Mulching for Hydraulic Seeding, Type 1 Seed Mix     0.6 Acres
    9040, 1.08, A - SWPPP Preparation & NPDES General Permit #2     1 L.S.
    9040, 1.08, A - SWPPP Management     1 L.S.
    9040, 1.08, D - Filter Sock, Installation, 8"     1,990 L.F.
    9040, 1.08, D - Filter Sock, Removal, 8"     1,990 L.F.
    11,010, 1.08, A - Construction Survey     1 L.S.
    11,020, 1.08, A - Mobilization     1 L.S.
    Remove Existing Septic Tank     1 Each
    Investigate MH 1061     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




DAVIS -- PROJECT # 26-05-26-01                6/18/2026                Large Project Letting
LAKE WAPELLO STATE PARK
WASTEWATER IMPROVEMENTS
Proposal Guarantee: $25,000
Completion Date: 6/30/2027

   This wastewater treatment improvement projeect includes baffle installation, aeration upgrades, installation of chlorination and de-chlorination chemical treatment systems, and flume and sampling manholes at the lagoons. Electrical work is also included.

ESTIMATED QUANTITIES:
    Excavation, Class 10     30 C.Y.
    Sanitary Sewer Gravity Main, Trenched, PVC, 6"     62 L.F.
    Removal of Sanitary Sewer, 4"     16 L.F.
    Manhole, SW-301, 48"     1 Each
    Sanitary Sewer, Valve, Plug, 6"     2 Each
    Baffle Curtain     1 Each
    Aeration Equipment     1 L.S.
    Chemical Tablet Feeder     2 Each
    Composite Sampling Manhole     1 Each
    Flow Meter and Manhole     1 Each
    Septic Tank, 1,250-gal     2 Each
    Chain Link Fence, Commercial     21 L.F.
    Removal of Fence     238 L.F.
    Erosion Control     1 L.S.
    Site Restoration     1 L.S.
    Mobilization      1 L.S.
    Electrical, Complete     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




DICKINSON -- PROJECT # 25-01-30-05                6/18/2026                Large Project Letting
DICKINSON COUNTY WILDLIFE AREAS AND STATE PARKS
ROAD MAINTENANCE
Proposal Guarantee: $50,000
Completion Date: 5/15/2027

   This project consists of pavement and rock road maintenance in various parks and wildlife areas in Dickinson County.

ESTIMATED QUANTITIES:
    Binder Bitumen, MC-3000     35,610 GAL.
    Aggregate, Roadway Cover, 3/8"     1,544 Tons
    Preparation of Surface - Microsurfacing     1.73 MI.
    Emulsified Asphalt - Microsurfacing     4,976 GAL.
    Aggregate - Microsurfacing, L-2     174 Tons
    Slurry Level     0.15 MI.
    Preparation of Surface - Slurry     0.15 MI.
    Emulsified Asphalt - Slurry Level, Wedge, Treatment     69 GAL.
    Clean and Fill Crack (HMA Surfaces)     6.35 MI.
    Sealer Material (HMA Surfaces)      6,350 LB.
    Crack and Joint Clean and Fill (PCC Pavement)     0.11 MI.
    Sealer Material (PCC Surfaces)      10 LB.
    Patch, Full-Depth Finish, 6-inch, by Area, HMA     461.5 S.Y.
    Patch, Full-Depth Finish, by Area (Greater than 50 ft in length)     106.7 S.Y.
    Patch, Full-Depth Finish, 6-inch, by Count, HMA     23 Each
    Patch, Partial-Depth Repair, by Area, HMA     27.9 S.Y.
    HMA (Partial Depth Patch Material)     1 Tons
    Patch By Count (Repair) HMA     3 Each
    Subbase (Patch)     174 S.Y.
    Longitudinal Joint Repair     1,679 L.F.
    Curb and Gutter, 2.0'     13 L.F.
    Concrete Ditch     80 S.Y.
    Pavement Scarification     1,204 S.Y.
    Hot Mix Asphalt, Thin Lift Surface, 3/8 In. Mix     68 Tons
    Hot Mix Asphalt, Standard Traffic, Intermediate Course, 1/2"     133 Tons
    Asphalt Binder, PG 64-34E+     5.5 Tons
    Asphalt Binder, PG 58-28S     7 Tons
    Blade and Shape Shoulder Material     1.35 STA.
    Reconstruction of Roadbed, Blade and Shape     78.16 STA.
    Granular Surface On Road, Class A     2,050 Tons
    Granular Shoulder, Type B     9 Tons
    Revetment, Class E     28 Tons
    Culvert, Concrete Roadway Pipe, 12"     38 L.F.
    Apron, Concrete, 12"     2 Each
    Remove Culvert Less Than or Equal To 36"     38 L.F.
    Painted Pavement Marking, High-Build Waterborne     86.7 STA.
    Reshaping Ditch     2 STA.
    Excavation, Class 13, Widen     3.8 C.Y.
    Base Widening, 6" HMA     11.2 S.Y.
    Modified Subbase     1.9 C.Y.
    Clearing and Grubbing     1 Units
    Traffic Control     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




GUTHRIE -- PROJECT # 21-04-39-01                6/18/2026                Large Project Letting
SPRINGBROOK EDUCATION CENTER
COMPLEX DEMOLITION
Proposal Guarantee: $12,500
Completion Date: 3/26/2027

   This project includes demolition of the Springbrook Education Center complex and restoring the site to a natural state. Asbestos survey and abatement has been completed on the entire complex. Also included the demolition of four (4) auxiliary maintenance sheds.

ESTIMATED QUANTITIES:
    2401-6745650 Sited 1: Education Center Complex Demolition     1 L.S.
    2401-6745650 Site 2: Maintenance Shed Demolition     1 L.S.
    2401-6745650 Site 3: Three (3) Park Office Maintenance Shed Demolitions     1 L.S.
    NPDES Permit #2 and SWPPP     1 L.S.
    2601-2634100 Mulching     4.6 Acres
    2601-2636015 Native Grass Seeding     4.5 Acres
    2601-2636044 Seeding and Fertilizing (Urban)     0.1 Acres
    2601-2636054 Wildflower Seeding     4.5 Acres
    2602-0000309 Perimeter and Slope Sediment Control Device, 12 In. Dia.     3,260 L.F.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




GUTHRIE -- PROJECT # 25-04-39-02                6/18/2026                Large Project Letting
SPRINGBROOK STATE PARK
ACCESSIBILITY IMPROVEMENTS
Proposal Guarantee: $6,250
Completion Date: 10/30/2026

   This project includes constructing ADA-compliant PCC sidewalk, parking stall, and pit latrine at the CCC Shelter.

ESTIMATED QUANTITIES:
    2102-0425070 Special Backfill     26 Tons
    2102-2710070 Excavation, Cl 10, Roadway and Borrow     60 C.Y.
    2105-8425015 Topsoil, Strip, Salvage and Spread     17 C.Y.
    2401-6745650 Removal of Existing Structures     2 Each
    2511-7526005 Sidewalk, Reinforced PCC, 5 In.     57 S.Y.
    2515-2475006 Parking Stall, Reinforced PCC, 6 In.     36 S.Y.
    2526-8285000 Construction Survey     1 L.S.
    2527-9263209 ADA Striping and Van Parking Sign     1 L.S.
    2533-4980005 Mobilization     1 L.S.
    2601-2634105 Mulching, Bonded Fiber Matrix     0.15 Acres
    2601-2636044 Seeding and Fertilizing (Urban)     0.15 Acres
    2602-0000309 Perimeter & Slope Sediment Control Device, 9 In. Dia.     165 L.F.
    Single Precast Concrete Pit Latrine     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




JACKSON -- PROJECT # 25-06-49-05                6/18/2026                Large Project Letting
GREEN ISLAND AND PRINCETON WMA
FLOOD REPAIR
Proposal Guarantee: $250,000
Completion Date: 5/28/2027

   This project will repair flood damage within the Green Island WMA and Princeton Reserve WMA. Repairs include placement of articulated concrete mat, importing embankment material, placement of revetment, installation of pipe and water control structures, and other minor repairs noted in the plans.

ESTIMATED QUANTITIES:
    CLEARING AND GRUBBING     1 L.S.
    CLASS 10 EXCAVATION     3,781 C.Y.
    EMBANKMENT IN PLACE     12,870 C.Y.
    GRANULAR SURFACING, CLASS A CRUSHED STONE     2,670 Tons
    REMOVAL OF EXISTING PIPE     1 L.S.
    36 INCH CONCRETE PIPE APRONS     4 Each
    48 INCH CORRUGATED METAL PIPE APRON     8 Each
    48 INCH CORRUGATED METAL PIPE     200 L.F.
    8 INCH CORRUGATED INTAKE RISER FOR WATER CONTROL STRUCTURE     2 Each
    36 INCH REINFORCED CONCRETE PIPE     186 L.F.
    HIGH STRENGTH GROUT FOR MUDJACKING     10 C.Y.
    EROSION STONE     50 Tons
    REVETMENT, CLASS B     6,388 Tons
    REVETMENT, CLASS E     22,646 Tons
    MOBILIZATION     1 L.S.
    ARTICULATED CONCRETE MATTING     31,900 S.Y.
    REMOVAL OF DEBRIS     1 L.S.
    48 INCH PRECAST WATER CONTROL STRUCTURE     1 L.S.
    WOOD EXCELSIOR MAT     4,810.1 SQ.
    MULCH     11.3 Acres
    SEEDING, TEMPORARY STABILIZING CROP     11.3 Acres
    SEEDING     11.3 Acres

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BUCHANAN -- PROJECT # 23-03-10-02                6/25/2026                Large Project Letting
CEDAR ROCK STATE PARK
ROAD MAINTENANCE REBID
Proposal Guarantee: $2,000
Completion Date: 11/6/2026

   The project consists of granular roadway maintenance - Blading/ Shaping the roadway, shoulder work pothole repair, minor ditch cleaning, spreading/blading/rolling new rock, and the replacement of one culvert. The contract period will be based on an approximate start date and working days, defined by Iowa DOT Standard Specifications, Series 2023, Section 1108, Prosecution and Progress. The approximate start date is September 30, 2026. There are 25 working days.

ESTIMATED QUANTITIES:
    2125 - RESHAPING DITCHES - CLEANING     0.5 STA.
    2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING - ROADWAY     29.4 STA.
    2127 - RECONSTRUCTION OF ROADBED - BLADING/SHAPING - SHOULDERS     29.4 STA.
    2312 - GRANULAR SURFACING ON ROAD, CLASS A CRUSHED STONE     343 Tons
    2402 - GRANULAR BACKFILL     3 Tons
    2416 - APRON, CONC, 18"     2 Each
    2416 - CULV, CONC RDWY PIPE, 18"     16 L.F.
    2507 - EROSION STONE     10 Tons
    2518 - SAFETY CLOSURE     1 Each
    2528 - TRAFFIC CONTROL     1 L.S.
    2533 - MOBILIZATION     1 L.S.
    2601 - SEED+FERTILIZE (RURAL)     0.25 Acres

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




DICKINSON -- PROJECT # 26-01-30-01                6/11/2026                Small Project Letting
GREAT LAKES WILDLIFE UNIT
HODGE WPA WETLAND RESTORATION
Proposal Guarantee: $0
Completion Date: 11/27/2026

   This project is designed to restore four wetland pool areas located on the Hodge Wildlife Protection Area (WPA), Dickinson County, Iowa. Work under this project includes embankment (dike construction), excavation (spillway & borrow), tile investigation, tile breaks, and water control structures with associated piping. Email jeff.felts@dnr.iowa.gov for plans and bid documents

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov