PROJECTS LETTING -  April , 2016

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

APPANOOSE 15-05-04-10 Stephens State Forest, Unionville Unit - Pond Spillway Repair-2016-04-28   Bid Completion detail
CERRO GORDO 16-03-17-04 Lekwa Marsh, Clear Lake State Park - Lekwa Access Development-2016-04-28   Bid Completion detail
CLAY 16-01-21-03 Prairie Lakes Wildlife Unit Headquarters - Prairie Lakes Wildlife HQ - Storage Building Relocation-2016-04-28   Bid Completion detail
FREMONT 16-04-36-02 Nishnabotna Wildlife Unit - Riverton Dike Fix-2016-04-28   Bid Completion detail
WASHINGTON 15-06-92-07 Lake Darling State Park - Cabin Road Construction - PCC Testing-2016-04-28   Bid Completion detail
APPANOOSE 15-05-04-06 Honey Creek Resort - Storm Water Improvements & Raingarden-2016-05-12   Bid Completion detail
JOHNSON 16-06-52-02 Lake Macbride State Park - Spillway Fish Barrier Replacement-2016-05-12   Bid Completion detail
JONES 16-06-53-02 Wapsipinicon State Park - Hale Bridge PCC Access Drive-2016-05-12   Bid Completion detail
SCOTT 16-06-82-03 Lost Grove Lake WMA - PCC Testing-2016-05-12   Bid Completion detail
DICKINSON 14-01-30-05 Hinshaw Bridge Access - Hinshaw Bridge Boat Ramp Replacement-2016-05-19   Bid Completion detail
VAN BUREN 13-06-89-02 Lake Sugema Wildlife Unit - CMP Replacement-2016-05-19   Bid Completion detail
BOONE 16-02-08-06 Boone Wildlife Research Station - Roof Replacements-2016-05-26   Bid Completion detail
JACKSON 16-06-49-01 Green Island WMA - Fish Lake Road Culvert Replacement-2016-05-26   Bid Completion detail
LOUISA 16-06-58-01 Odessa Wildlife Unit - Storm Sewer Extension-2016-05-26   Bid Completion detail
MONONA 13-01-67-03 Lewis and Clark - Water Treatment Building-2016-05-26   Bid Completion detail
MONONA 13-01-67-04 Lewis and Clark - Water Treatment System-2016-05-26   Bid Completion detail
WINNEBAGO 16-02-95-01 Rice Lake - Building Demolition-2016-05-26   Bid Completion detail




MONONA -- PROJECT # 13-01-67-03                5/26/2016                Large Project Letting
LEWIS AND CLARK
WATER TREATMENT BUILDING
Proposal Guarantee: $5,000
Completion Date: 9/30/2016

   This project consists of constructing a 22'x38' CMU building, along with associated site grading and electrical work.

ESTIMATED QUANTITIES:
    MOBILIZATION     1 L.S.
    CLEARING & GRUBBING     1 L.S.
    38’ X 22’ WATER TREAMENT BUILDING COMPLETE WITH GRADING     1 L.S.
    COMPLETE BUILDING ELECTRICAL AND EJECTOR PUMP CONTROLS INCLUDING 200 AMP CONTROL PANEL, LIGHITING, HEATER, EXAUST FAN AND OUTLETS FOR OTHER EQUIPMENT      1 L.S.
    NEW ELECTRICAL SERVICE TO THE BULDING FROM 70 FT. WITH DISCONECT.     1 L.S.
    SUMP AND SUBMERSIBLE PUMP INSIDE THE BUILDING, COMPLETE     1 L.S.
    STUB OUTS 10’ BEYOND FOUNDATION AS SHOWN IN DRAWINGS     1 L.S.
    SEED ALL DISTURBED AREAS     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




MONONA -- PROJECT # 13-01-67-04                5/26/2016                Large Project Letting
LEWIS AND CLARK
WATER TREATMENT SYSTEM
Proposal Guarantee: $10,000
Completion Date: 3/31/2017

   Project consists of developing a new well, a new water treatment system including, demolition of old building and underground water storage tank and plugging the existing well.

ESTIMATED QUANTITIES:
    MOBILIZATION     1 L.S.
    CLEARING & GRUBBING     1 L.S.
    158 GALLONS WX-451 AMTROL PRESSURE TANK     2 Each
    STORAGE BUILDING MANIFOLD: WATER METER, VALVES, PRESSURE SWITCH, PRESSURE GAUGE, SCH. 80 PVC PIING ETC.     1 L.S.
    CHLORINE FEED SYSTEM WITH ONE PUMP, 20 GALLON TANK AND SPILL PALLET COMPLETE     1 L.S.
    TRIPLEX MULTI-MEDIA IRON FILTER SYSTEM COMPLETE WITH CHLORINE INJECTION PUMP, COMPLETE     1 L.S.
    DUPLEX AUTOMAIC SOFTENER SYSTEM WITH BRINE TANK COMPLETE     1 L.S.
    3" DIA. HDPE (DR 11) WATERMAIN, BORED OR TRENCHED IN PLACE TO SETTLING BASIN     150 L.F.
    SETTLING BASIN     1 L.S.
    3" DIA. HDPE DR 11 WATERMAIN TRANCHED OR BORED IN PLACE     200 L.F.
    TRACER WIRE #12 OR 3" DETACTABLE "WATER " TAPE     350 L.F.
    SYSTEM DISINFECTION     1 L.S.
    DRILL 12" HOLE, FURNISH 6" PVC SDR 21 WELL CASING PIPE AND PCC GROUT     80 L.F.
    6" DIA X 20’ OF PVC SLOTTED WELL SCREEN WITH GRAVEL PACK IN 12" HOLE     20 L.F.
    2"X 60’ SCH 120 PVC DROP PIPE     80 L.F.
    5 HP 3PH SUBMERSIBLE VARIABLE SPEED PUMP RATED TO PROVIDE 65 GPM AT 70 PSI AT SURFACE. INCLUDING 3PH WIRING TO THE VFD TO TREATMENT BUILDING     1 L.S.
    PITLESS ADAPTER UNIT     1 Each
    STATIC WATER PRESSURE LINE AND GUAGE     1 L.S.
    INSTALL WELL BELOW-OFF ASSEMBLY & PVC CL 160 WATER LINE FROM WELL TO BUILDING     1 L.S.
    DEVELOP WELL AND TEST PLUMBING     1 L.S.
    DISINFECTION AND CHEMICAL ANALYSIS     1 L.S.
    GRADE AREA AROUND WELL HEAD AS SHOWN AND SEED     1 L.S.
    DRILL 12" HOLE AND 6" PVC SDR 21 WELL CASING AND GROUT FOR ADDITONAL DEPTH     1 L.F.
    REMOVE PUMP & PLUG EXISTING WELL     1 L.S.
    DEMOLISH APP. 28’X28’ EXSTNG TREAT. BLDNG INC. ASBESTOS ABTMNT, REMOVE PRESSURE TANKS, MIXING TANKS, INTERNAL PIPING ETC. HAUL AND DISPOSE OFF SITE     1 L.S.
    DEMOLISH 28’X24’X10’ DEEP CONCRETE STORAGE TANK AND 145’ LONG ADJUCENT FENCING, HAUL AND DISPOSE OFF SITE     1 L.S.
    SEED ALL DISTURBED AREAS     1 L.S.
    INSTALL A NEW 6’ HIGH COMMERCIAL GRADE CHAIN LINK FENCE     155 L.F.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




APPANOOSE -- PROJECT # 15-05-04-10                4/28/2016                Small Project Letting
STEPHENS STATE FOREST, UNIONVILLE UNIT
POND SPILLWAY REPAIR
Proposal Guarantee: $0
Completion Date: 7/31/2016

   This project includes placement of 370 CY of contractor supplied fill dirt, engineering fabric, and 140 tons class E revetment. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




CERRO GORDO -- PROJECT # 16-03-17-04                4/28/2016                Small Project Letting
LEKWA MARSH, CLEAR LAKE STATE PARK
LEKWA ACCESS DEVELOPMENT
Proposal Guarantee: $0
Completion Date: 6/17/2016

   Project consists of furnishing and placing field stone riprap (80 ton), fill material (280 CY), and crushed stone surfacing (180 ton); some minor bank shaping & seeding disturbed areas on Clear Lakes south shore near Lekwa Marsh at Clear Lake State Park. Proposal & site plan may be obtained by emailing name, address, and phone number.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




CLAY -- PROJECT # 16-01-21-03                4/28/2016                Small Project Letting
PRAIRIE LAKES WILDLIFE UNIT HEADQUARTERS
PRAIRIE LAKES WILDLIFE HQ - STORAGE BUILDING RELOCATION
Proposal Guarantee: $0
Completion Date: 6/24/2016

   The scope of this contract is to relocate a 55' x 110' pole style storage building approximately 9 miles from its existing location to the Prairie Lakes Wildlife Unit Headquarters in Clay County, Iowa. Work includes but is not limited to; preparing the building for relocation, moving the building with all necessary permits, law enforcement/utility coordination, and resetting the building on a pre-prepared pad.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




FREMONT -- PROJECT # 16-04-36-02                4/28/2016                Small Project Letting
NISHNABOTNA WILDLIFE UNIT
RIVERTON DIKE FIX
Proposal Guarantee: $0
Completion Date: 6/17/2016

   Repair slough areas and one hole in the south dike at the Riverton WMA using fill material at the site. Seeding of all disturbed areas required when earthwork completed.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov




WASHINGTON -- PROJECT # 15-06-92-07                4/28/2016                Small Project Letting
LAKE DARLING STATE PARK
CABIN ROAD CONSTRUCTION - PCC TESTING
Proposal Guarantee:
Completion Date: 6/30/2016

   Daily testing of PCC being placed for an Iowa DOT funded roadway project at Lake Darling State Park in Washington County, Iowa.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




APPANOOSE -- PROJECT # 15-05-04-06                5/12/2016                Small Project Letting
HONEY CREEK RESORT
STORM WATER IMPROVEMENTS & RAINGARDEN
Proposal Guarantee: $0
Completion Date: 7/31/2016

   This project consists of construction of a rain garden and other stormwater improvements at Honey Creek Resort. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




JOHNSON -- PROJECT # 16-06-52-02                5/12/2016                Small Project Letting
LAKE MACBRIDE STATE PARK
SPILLWAY FISH BARRIER REPLACEMENT
Proposal Guarantee: $0
Completion Date: 7/29/2016

   Project includes installation of a 155' long fish barrier across the Lake Macbride spillway. Fish barrier is made up of galvanized steel posts and rails, 4' high.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




JONES -- PROJECT # 16-06-53-02                5/12/2016                Small Project Letting
WAPSIPINICON STATE PARK
HALE BRIDGE PCC ACCESS DRIVE
Proposal Guarantee:
Completion Date:

   Project includes placing 638 SY of PCC pavement (6" thick) on an existing gravel access drive serving the Hale Bridge Trail within Wapsipinicon State Park.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




SCOTT -- PROJECT # 16-06-82-03                5/12/2016                Small Project Letting
LOST GROVE LAKE WMA
PCC TESTING
Proposal Guarantee: $0
Completion Date: 9/30/2016

   Daily Testing of PCC for an Iowa DOT funded roadway project at Lost Grove Lake Wildlife Management Area in Scott County, Iowa. Testing per Iowa DOT Specifications.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




DICKINSON -- PROJECT # 14-01-30-05                5/19/2016                Small Project Letting
HINSHAW BRIDGE ACCESS
HINSHAW BRIDGE BOAT RAMP REPLACEMENT
Proposal Guarantee: $0
Completion Date: 11/15/2016

   This project is designed to replace an existing PCC boat ramp with a new 26'x70' grooved PCC boat ramp at the Hinshaw access (Lower Gar Lake, Arnolds Park) in Dickinson County, Iowa. Work includes removal of the existing ramp sections, subgrade preparation, base material installation, 6" reinforced PCC boat ramp, and riprap protection of the ramp

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




VAN BUREN -- PROJECT # 13-06-89-02                5/19/2016                Small Project Letting
LAKE SUGEMA WILDLIFE UNIT
CMP REPLACEMENT
Proposal Guarantee: $0
Completion Date: 9/30/2016

   This project involves replacing 129 LF of deteriorated corrugated metal pipe and a water control structure with new polymer coated corrugated metal pipe and other incidental work as required by the DNR Construction Inspector.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




BOONE -- PROJECT # 16-02-08-06                5/26/2016                Small Project Letting
BOONE WILDLIFE RESEARCH STATION
ROOF REPLACEMENTS
Proposal Guarantee: $0
Completion Date: 6/30/2016

   This project consists of replacing two metal roofs at the Boone Wildlife Research Station.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov




JACKSON -- PROJECT # 16-06-49-01                5/26/2016                Small Project Letting
GREEN ISLAND WMA
FISH LAKE ROAD CULVERT REPLACEMENT
Proposal Guarantee: $0
Completion Date: 7/8/2016

   Project includes replacement of approximately 140 LF of 42" dia. CMP culverts with aprons at Fish Lake Road in the Green Island Wildlife Management Area, Jackson County, Iowa.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




LOUISA -- PROJECT # 16-06-58-01                5/26/2016                Small Project Letting
ODESSA WILDLIFE UNIT
STORM SEWER EXTENSION
Proposal Guarantee: $0
Completion Date: 9/16/2016

   Project includes a 150 L.F. extension of a 15" Dia RCP storm sewer including a storm sewer manhole in the Odessa Wildlife Unit in Louisa County, Iowa.

Contact:
Michael Dufoe

Michael.dufoe@dnr.iowa.gov




WINNEBAGO -- PROJECT # 16-02-95-01                5/26/2016                Small Project Letting
RICE LAKE
BUILDING DEMOLITION
Proposal Guarantee: $0
Completion Date: 8/31/2016

   This project consists of miscellaneous demolition at Rice Lake, as directed by the DNR Field Engineer.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov