PROJECTS LETTING -  February , 2022

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

CLAYTON 21-03-22-01 Pikes Peak - Campground Upgrade Project-2022-02-17   Bid Completion detail
CLAYTON 21-03-22-01 Pikes Peak - Campground Upgrade Project-2022-02-17   Bid Completion detail
DICKINSON 22-01-30-07 Gull Point State Park - Stone Entry Portal-2022-02-17   Bid Completion detail
JACKSON 22-06-49-01 Maquoketa Caves State Park - Stone Entry Portal-2022-02-17   Bid Completion detail
LOUISA 21-06-58-04 Odessa Wildlife Unit - Flood Damage Repairs REBID-2022-02-17   Bid Completion detail
LUCAS 22-05-59-01 Red Haw State Park - Shoreline Stabilization & Water Control structure replacement -2022-02-17   Bid Completion detail
POLK 21-02-77-10 Big Creek State Park - Derecho Repairs-2022-02-17   Bid Completion detail
UNION 22-04-88-04 Green Valley - main boat ramp vault replacemen-2022-02-17   Bid Completion detail
UNION 21-04-88-02 Green Valley State Park - Campground Pavement Maintenance-2022-02-17   Bid Completion detail
WARREN 22-05-91-08 Lake Ahquabi - Fishing Pier Renovations - REBID-2022-02-17   Bid Completion detail
WARREN 22-05-91-06 Lake Ahquabi State Park and Hooper Lake - Boat Docks-2022-02-17   Bid Completion detail
WEBSTER 22-02-94-03 Brushy Creek State Rec Area - Stone Entry Portal-2022-02-17   Bid Completion detail
WINNESHIEK 19-03-96-04 Coon Creek WMA - Streambank Stabilization-2022-02-17   Bid Completion detail
DAVIS 22-05-26-01 Lake Wapello State Park - Boy Scout Pond Outlet Replacement-2022-02-24   Bid Completion detail
CERRO GORDO 21-03-17-02 McIntosh Woods - Pull off- decontamination stn-2022-03-03   Bid Completion detail
DELAWARE 22-03-28-01 Backbone State Park - Camp Lagoon and Cabin Sand Filter Sampling Manholes-2022-03-03   Bid Completion detail
JACKSON 22-06-49-02 Maquoketa Caves State Park - Stone Entry Portal (REBID)-2022-03-03   Bid Completion detail
WARREN 22-05-91-05 Lake Ahquabi State Park - Spillway Joint Repairs-2022-03-03   Bid Completion detail
JASPER 21-05-50-04 Rock Creek State Park - Shower Building Roof Repairs-2022-03-10   Bid Completion detail
WARREN 22-05-91-10 Lake Ahquabi State Park - Sluice Gate Repair-2022-03-10   Bid Completion detail




CLAYTON -- PROJECT # 21-03-22-01                2/17/2022                Large Project Letting
PIKES PEAK
CAMPGROUND UPGRADE PROJECT
Proposal Guarantee: $125,000
Completion Date: 5/1/2023

   This project consists of removal of the existing asphalt roads, campground camp pads, electric service lines, disposal station and any remaining trees and vegetation within the work zone and installing a new Portland Cement Concrete roadway, new gravel camp pads, electric services, sanitary sewer services, installing 2 new disposal stations and seeding and mulching all disturbed areas located at Pikes Peak State Park in Clayton County, Iowa.

ESTIMATED QUANTITIES:
    Clearing and Grubbing     1 L.S.
    Tree Clearing/Stump Grinding     1 L.S.
    Full Depth Saw Cut     325 L.F.
    HMA Pavement Removal     12,800 S.Y.
    PCC Removal     529.4 S.Y.
    Grading     1 L.S.
    12-inch Filter Sock     3,160 L.F.
    Sanitary Sewer Connections to Existing Manhole     2 Each
    Type SW-301 48" Diameter Sanitary Manhole w/Type 'A' Casting     1 Each
    6-inch Sanitary Sewer (PVC SDR 23.5)     228 L.F.
    4-inch Sanitary Sewer Service (PVC SDR 23.5)     242 L.F.
    Disposal Station RV Cleanout Connection     2 Each
    RV Sanitary Sewer Cleanout Connection     6 Each
    6"x4" PVC Schedule 40 Service Wye     6 Each
    2"x2"x2"x2" HDPE Cross     1 Each
    1-inch HDPE Pipe     1,128 L.F.
    2-inch HDPE Pipe     1,195 L.F.
    2-Inch Valve     3 Each
    Woodford Model S-3 Sanitary Yard Hydrant w/Drain Down Pit (or Approved Equal)     16 Each
    Woodford Model S-3 Sanitary Yard Hydrant w/o Drain Down Pit (or Approved Equal)     2 Each
    Woodford Model S-4H ADA Sanitary Yard Hydrant w/Drain Down Pit (or Approved Equal)     2 Each
    Woodford Model S-4H ADA Sanitary Yard Hydrant w/o Drain Down Pit (or Approved Equal)     2 Each
    1"x1"x1" HDPE Tee     2 Each
    2"x2"x1" HDPE Tee     14 Each
    2"x2"x2" HDPE Tee     3 Each
    2"x1" HDPE Reducer     5 Each
    WellXTrol Model WX-452C Pressure Tanks (or Approved Equal)     2 Each
    Pressure Tank Installation and Removal of 2 Old Tanks     1 L.S.
    Water Connection     2 Each
    Disinfection     1 L.S.
    Type SW-512 Circular Area Intake W/Type 3A Casting     8 Each
    Type SW-513 open Sided Area Intake W/Type G Casting     4 Each
    12-inch RCP Class III     505.7 L.F.
    15-inch RCP Class III     415.4 L.F.
    12-inch RCP Class III FES     1 Each
    15-inch RCP Class III FES     1 Each
    Class 'D' Riprap     100 Tons
    Primary Electric Service To Distribution Panels     1 L.S.
    Single Campsite Outlet Post-30 Amp     1 Each
    Single Campsite Outlet Post-50 Amp     60 Each
    No. 2 AWG Grounding Conductor Cable, Type THW or USE     4,359 L.F.
    No. 4 AWG Grounding Conductor Cable, Type THW or USE     822 L.F.
    No. 350 MCM Single Conductor Cable, Type USE     837 L.F.
    No. 300 MCM Single Conductor Cable, Type USE     1,386 L.F.
    No. 250 MCM Single Conductor Cable, Type USE     2,640 L.F.
    No. 4/0 AWG Single Conductor Cable, Type USE     8,214 L.F.
    No. 3/0 AWG Single Conductor Cable, Type USE     1,656 L.F.
    No. 2/0 AWG Single Conductor Cable, Type USE     810 L.F.
    Roadway Crossing 3-Inch Conduit-Schedule 80 PVC     90 L.F.
    Roadway Crossing 2.5-inch Conduit-Schedule 80 PVC     290 L.F.
    Roadway Crossing 2-inch Conduit-Schedule 80 PVC     25 L.F.
    Detectable Warning Tape, 3" Electric     4,116 L.F.
    Trench, Single Circuit Secondary     4,521 L.F.
    200 Amp Circuit Breaker     9 Each
    175 Amp Circuit Breaker     1 Each
    150 Amp Circuit Breaker     1 Each
    600 Amp Distribution Panel     1 Each
    400 Amp Distribution Panel     1 Each
    Electrical Connection To Check-in Kiosk and LED Light     1 L.S.
    Special Backfill/Granular Base     4,658.3 Tons
    6-inch Non-Reinforced PCC     3,625.3 S.Y.
    7-inch Nylon Reinforced PCC     10,747.3 S.Y.
    Disposal Station Island Pavement     2 Each
    Granular Base-Sidewalks     32.1 Tons
    5-inch Non-Reinforced PCC Sidewalks     160.4 S.Y.
    Engineering Fabric     7,770 S.Y.
    Macadam Stone     1,515 Tons
    Class 'A' Crushed Stone     1,129 Tons
    4'x4'x5.5" Reinforced PCC Fire Ring     60 Each
    Traffic Control     1 L.S.
    Seeding, Fertilizing and Mulching     5 Acres
    Street Signage     1 L.S.
    Handicap Parking Signage     1 L.S.
    Street Pavement Markings     1 L.S.
    Parking Space Pavement Striping, Handicap Parking Cross Hatch Markings     1 L.S.
    6' Concrete Parking Wheel Stops     27 Each
    8' Concrete Parking Wheel Stops     13 Each
    Snow Fence Barrier W/Archeological Area     440 L.F.
    Construction Survey Staking and As-Built Survey     1 Each
    NPDES General Permit #2 & SWPPP     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




LOUISA -- PROJECT # 21-06-58-04                2/17/2022                Large Project Letting
ODESSA WILDLIFE UNIT
FLOOD DAMAGE REPAIRS REBID
Proposal Guarantee: $12,500
Completion Date: 9/30/2022

   This project involves clearing and grubbing, grading, placing fill, placing erosion mat, seeding and fertilizing FEMA repair areas in Louisa County in the Odessa Wildlife Unit.

ESTIMATED QUANTITIES:
    Earthwork, Fill Hauled and Placed, Clean Sand (Site 1)     297 C.Y.
    Erosion Control Mat, RECP Type 2.A (Site 1)     112 S.Y.
    Seeding and Fertilizing (Site 1)     0.1 Acres
    Earthwork, Fill Hauled and Placed, Clay (Site 2)     3,260 C.Y.
    Erosion Control Mat, RECP Type 2.C (Site 2)     4,889 S.Y.
    Seeding and Fertilizing(Site 2)     1.5 Acres
    Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 3)     5 C.Y.
    Erosion Control Mat, RECP Type 2.C (Site 3)     14 S.Y.
    Seeding and Fertilizing (Site 3)     0.1 Acres
    Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 4)     3 C.Y.
    Erosion Control Mat, RECP Type 2.C (Site 4)     9 S.Y.
    Seeding and Fertilizing (Site 4)     0.1 Acres
    Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 5)     3 C.Y.
    Erosion Control Mat, RECP Type 2.C (Site 5)     9 S.Y.
    Seeding and Fertilizing (Site 5)     0.1 Acres
    Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 6)     1 C.Y.
    Erosion Control Mat, RECP Type 2.C (Site 6)     3 S.Y.
    Seeding and Fertilizing (Site 6)     0.1 Acres
    Earthwork, Fill Hauled and Placed, Clay and Clean Sand (Site 7)     17 C.Y.
    Erosion Control Mat, RECP Type 2.C (Site 7)     51 S.Y.
    Seeding and Fertilizing (Site 7)     0.1 Acres
    Seeding and Fertilizing (Construction Road)     3.1 Acres
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




LUCAS -- PROJECT # 22-05-59-01                2/17/2022                Large Project Letting
RED HAW STATE PARK
SHORELINE STABILIZATION & WATER CONTROL STRUCTURE REPLACEMENT
Proposal Guarantee: $25,000
Completion Date: 2/15/2023

   This project involves 3,670 linear feet of shoreline stabilization by placing class 'E' revetment on 2:1 slope; replacing water control structure, seeding mulching and fertilizing all disturbed areas.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Class E Riprap     4,620 Tons
    24" Dia. SMP Culvert     30 L.F.
    Water Control Structure Replacement (Complete)     1 L.S.
    Silt Fence     200 L.F.
    Seeding, Mulching and Fertilizing      1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POLK -- PROJECT # 21-02-77-10                2/17/2022                Large Project Letting
BIG CREEK STATE PARK
DERECHO REPAIRS
Proposal Guarantee: $6,250
Completion Date: 8/31/2022

   The Derecho of 2020 damaged the office building roof and many shelters and restrooms throughout Big Creek State Park. This project will be to demolish the Model Airplane and Firefly Restrooms, repair the roofs at Cadet Restroom and Shelter, Jolly Boat Shelter, and the office at Big Creek SP. The office will also receive new gutters and downspouts.

ESTIMATED QUANTITIES:
    Restroom Demolitions     2 Each
    Roofing Demolition     1 L.S.
    4x8 OSB Roof Sheathing     10 Each
    Asphalt Roofing and Underlayment     1 L.S.
    Office Gutters, and Downspouts     1 L.S.
    Restroom, and Shelter Siding and Associated Items     3 Each
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




UNION -- PROJECT # 21-04-88-02                2/17/2022                Large Project Letting
GREEN VALLEY STATE PARK
CAMPGROUND PAVEMENT MAINTENANCE
Proposal Guarantee: $200
Completion Date: 8/31/2022

   This project consists of pavement preservation; crack cleaning and filling, patching, fog sealing, double chip sealing, placement of shoulder rock, grading for drainage, installation of a roadway culvert and seeding, fertilizing and mulching.

ESTIMATED QUANTITIES:
    Clearing and Grubbing     1 L.S.
    Removal of Existing Camp Pad     279 S.Y.
    Remove and Dispose Existing Electric Campsite Pedestals     2 Each
    Relocate Electric Lines     120 L.F.
    Relocate Water Line     70 L.F.
    Bituminous Fog Seal (HMA Pavement) (2306)     1,460 GAL.
    Patches, Full-Depth Finish, 5-inch, By Area, HMA (2529)     161 S.Y.
    Patches, Full-Depth Finish, 5-inch, By Count, HMA (2529)     9 Each
    Transverse Joint Repair (2543)     200 Tons
    Cleaning and Filling Cracks (HMA Surfaces) (2541)     1.2 MI.
    Sealer Material (HMA Surfaces) (2541)     4,000 LB.
    Aggregate, Roadway Cover, 1/2" (2307)     11 Tons
    Binder Bitumen, CRS-2P (2307)     245 GAL.
    Modified Subbase (2115)     27 C.Y.
    Granular Shoulder, Type A (2121)     70 Tons
    Excavation, Class 10, Roadway and Borrow (2102)     336 C.Y.
    Excavation, Class 10, Waste (2102)     336 C.Y.
    Excavation, CL 20, Roadway Pipe Culvert (2404)     56 C.Y.
    Culvert, Concrete Roadway Pipe, 12" (2417)     72 L.F.
    Apron, Concrete, 12" (2416)     2 Each
    Seeding, Fertilizing, and Mulching     0.4 Acres
    Traffic Control     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




WARREN -- PROJECT # 22-05-91-08                2/17/2022                Large Project Letting
LAKE AHQUABI
FISHING PIER RENOVATIONS - REBID
Proposal Guarantee: $12,500
Completion Date: 8/31/2022

   The existing fishing pier at Lake Ahquabi was built in the early 1990s. The pier needs a renovation as the decking boards, shelter, and handrails are in poor condition and need to be replaced. This project will remove the enclosed shelter, add structural steel to the superstructure and a new, open air, steel shelter will be installed. New treated wood floor joists, composite decking, treated wood handrails, fish cleaning stations, and electrical will be installed. The adjacent boardwalk, concrete building slab, and asphalt trail will be removed and replaced with a new accessible seawall sidewalk to the pier.

ESTIMATED QUANTITIES:
    Demolition     1 L.S.
    Mobilization     1 L.S.
    5" PCC Seawall Sidewalk, Subbase, and Curbing     78 S.Y.
    Pier Structural Wood, Handrails, and Composite Decking     1 L.S.
    Pier Shelter and Structural Steel     1 L.S.
    Electrical and Lighting     1 L.S.
    Fish Cleaning Tables     2 Each
    Picnic Tables     4 Each
    Boardwalk Benches     2 Each
    Site Restoration     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




WINNESHIEK -- PROJECT # 19-03-96-04                2/17/2022                Large Project Letting
COON CREEK WMA
STREAMBANK STABILIZATION
Proposal Guarantee: $6,250
Completion Date: 7/30/2022

   This project consists of placing streambank erosion protection.

ESTIMATED QUANTITIES:
    Mobilization     1 L.S.
    Class E Revetment     521 Tons
    Class B Revetment Mod.     1,043 Tons
    Flexamat     5,295 S.F.
    Excavation     588 C.Y.
    Seeding     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




DICKINSON -- PROJECT # 22-01-30-07                2/17/2022                Small Project Letting
GULL POINT STATE PARK
STONE ENTRY PORTAL
Proposal Guarantee: $0
Completion Date: 6/10/2022

   This project is designed to replace an existing park entrance sign with a stone entry portal at the entrance of Gull Point State Park in Dickinson County, Iowa. The existing sign is aged and inadequate per park standards. Work under this project includes earthen grading, concrete footings, structural concrete, stone work, and a timber sign support with steel brackets. Email jeff.felts@dnr.iowa.gov for plans and specifications.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




JACKSON -- PROJECT # 22-06-49-01                2/17/2022                Small Project Letting
MAQUOKETA CAVES STATE PARK
STONE ENTRY PORTAL
Proposal Guarantee: $0
Completion Date: 6/10/2022

   Project includes installation of a Stone Entry Portal (entry sign with decorative stone base) at the Maquoketa Caves State Park entrance.

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov




UNION -- PROJECT # 22-04-88-04                2/17/2022                Small Project Letting
GREEN VALLEY
MAIN BOAT RAMP VAULT REPLACEMEN
Proposal Guarantee: $0
Completion Date: 9/22/2022

   This project is designed to remove and replace the existing pit latrine at the main boat ramp with a new single stall precast concrete latrine. Building removal to include pumping of pit under existing building and removal of the pine tree east of the building. Protect existing underground wire to fishing pier and reconnect to wire from power pole after existing building is removed. Compacted Class "A" stone is to be used under new building as base and as backfill around new building. Site Restoration is required on all disturbed grass areas.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov




WARREN -- PROJECT # 22-05-91-06                2/17/2022                Small Project Letting
LAKE AHQUABI STATE PARK AND HOOPER LAKE
BOAT DOCKS
Proposal Guarantee: $0
Completion Date: 11/30/2022

   This project consists of construction of two aluminum docks and one concrete dock. There is a bid alternate for one additional aluminum dock. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




WEBSTER -- PROJECT # 22-02-94-03                2/17/2022                Small Project Letting
BRUSHY CREEK STATE REC AREA
STONE ENTRY PORTAL
Proposal Guarantee: $0
Completion Date: 6/10/2022

   Project includes installation of a Stone Entry Portal (entry sign with decorative stone base) at the north entrance to Brushy Creek SRA.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov




DAVIS -- PROJECT # 22-05-26-01                2/24/2022                Small Project Letting
LAKE WAPELLO STATE PARK
BOY SCOUT POND OUTLET REPLACEMENT
Proposal Guarantee: $0
Completion Date: 7/31/2022

   This project consists of replacement of a pond outlet structure and pipe. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




CERRO GORDO -- PROJECT # 21-03-17-02                3/3/2022                Small Project Letting
MCINTOSH WOODS
PULL OFF- DECONTAMINATION STN
Proposal Guarantee: $0
Completion Date: 6/30/2022

   THIS PROJECT CONSISTS OF CONSTRUCTING A PULL OFF DECONTAMINATION STATION AND AOSSOCIATED WORK AS DESCRIBED IN THE PROJECT PLANS & SPECIFICATIONS.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




DELAWARE -- PROJECT # 22-03-28-01                3/3/2022                Small Project Letting
BACKBONE STATE PARK
CAMP LAGOON AND CABIN SAND FILTER SAMPLING MANHOLES
Proposal Guarantee: $0
Completion Date: 6/30/2022

   Project consists of constructing 2 sampling manholes, flow meters & instrumental connections and the furnishing sampling equipment at Backbone State Park near Dundee, Delaware County Iowa

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




JACKSON -- PROJECT # 22-06-49-02                3/3/2022                Small Project Letting
MAQUOKETA CAVES STATE PARK
STONE ENTRY PORTAL (REBID)
Proposal Guarantee: $0
Completion Date: 6/10/2022

   Project includes installation of a Stone Entry Portal (entry sign with decorative stone base), and architectural site lighting at the Maquoketa Caves State Park entrance.

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov




WARREN -- PROJECT # 22-05-91-05                3/3/2022                Small Project Letting
LAKE AHQUABI STATE PARK
SPILLWAY JOINT REPAIRS
Proposal Guarantee: $0
Completion Date: 9/30/2022

   This project consists of cleaning and sealing concrete joints in the spillway. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




JASPER -- PROJECT # 21-05-50-04                3/10/2022                Small Project Letting
ROCK CREEK STATE PARK
SHOWER BUILDING ROOF REPAIRS
Proposal Guarantee: $0
Completion Date: 7/31/2022

   This project consists of roofing replacement on the shower building at Rock Creek State Park. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




WARREN -- PROJECT # 22-05-91-10                3/10/2022                Small Project Letting
LAKE AHQUABI STATE PARK
SLUICE GATE REPAIR
Proposal Guarantee: $0
Completion Date: 8/31/2022

   This project consists of repair of a sluice gate. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov