PROJECTS LETTING -  January , 2017

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

WARREN 17-05-91-02 Lake Ahquabi State Park - Campground Pit Vault Restroom-2017-01-26   Bid Completion detail
CASS 17-04-15-02 Lake Anita - single pit vault, demo of old -2017-02-02   Bid Completion detail
HARDIN 17-02-42-02 Pine Lake State Park - Emergency Road Repair Phase 1 of 2-2017-02-09   Bid Completion detail
ALLAMAKEE 17-03-03-02 Yellow River State Forest - rock on Fire tower road and oth-2017-02-16   Bid Completion detail
BOONE 17-02-08-01 Barkley State Forest - Pavement Repair-2017-02-16   Bid Completion detail
BUENA VISTA 14-01-11-01 Storm Lake - Island Stablization-2017-02-16   Bid Completion detail
BUENA VISTA 14-01-11-01 Storm Lake - Island Stablization - Contract-2017-02-16   Bid Completion detail
JONES 17-06-53-01 Wapsipinicon State Park - 2017 Stream Bank Repairs-2017-02-16   Bid Completion detail
LUCAS 17-05-59-04 Brown's Slough - Replace Bridge Deck-2017-02-16   Bid Completion detail
MARION 15-05-63-05 Honey Creek Resort SP - Entrance Portal (REBID)-2017-02-16   Bid Completion detail
POLK 17-02-77-04 Big Creek State Park - Restroom Building Replacement-2017-02-16   Bid Completion detail
POTTAWATTAMIE 16-04-78-01 Lake Manawa - Picnic Area-2017-02-16   Bid Completion detail
MUSCATINE 16-06-70-03 Fairport Fisheries Management Unit - Replace 12 Inch Reservoir Vavle-2017-02-17   Bid Completion detail
DICKINSON 17-01-30-06 Gull Point State Park - Cold Storage Building Exterior Steel Replacement-2017-02-23   Bid Completion detail
LINN 17-06-57-05 Palisades-Kepler State Park - Washout Repair-2017-02-23   Bid Completion detail




BOONE -- PROJECT # 17-02-08-01                2/16/2017                Large Project Letting
BARKLEY STATE FOREST
PAVEMENT REPAIR
Proposal Guarantee: $2,500
Completion Date: 6/30/2017

   This project consists of 10, full-depth HMA patches, totalling approximately 920 SY. A fog seal on all HMA pavement is also part of this project.

ESTIMATED QUANTITIES:
    2102 - Special Backfill     5 Tons
    2306 - Bituminous Fog Seal (Pavement)     557 GAL.
    2528 - Traffic Control     1 L.S.
    2529 - Patches, Full-Depth Repair     920 S.Y.
    2529 - Patches By Count (Repair)     10 Each
    2533 - Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




BUENA VISTA -- PROJECT # 14-01-11-01                2/16/2017                Large Project Letting
STORM LAKE
ISLAND STABLIZATION
Proposal Guarantee: $20,000
Completion Date: 11/12/2017

   This project involves stabilizing of existing Island 2 by installing a riprap embankment ring around the deteriorated island and salvaging material around the Island to be used as fill to restore the Island to its original elevation.

ESTIMATED QUANTITIES:
    MOBILIZATION     1 L.S.
    CLASS `E' FIELD STONE REVETMENT( SOLID FIELD STONE ARMORING)     5,565 Tons
    ENGINEERING FABRIC     950 S.Y.
    EXCAVATION & ISLAND FILL     4,472 C.Y.
    6" TOP SOIL     821 C.Y.
    SEEDING & ROLLED EROSION MATTING     2,000 S.Y.
    STAGING AREA PREPARATION & RESTORATION      1 L.S.
Alternate
    CLASS `E' FIELD STONE REVETMENT(FACING MATERIAL FOR LIMESTONE CORE ARMORING)     2,933 Tons
Alternate
    CLASS `E' QUARRY STONE REVETMENT (CORE MATERIAL FOR LIMESTONE CORE ARMORING)     2,632 Tons

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




MARION -- PROJECT # 15-05-63-05                2/16/2017                Large Project Letting
HONEY CREEK RESORT SP
ENTRANCE PORTAL (REBID)
Proposal Guarantee: $5,000
Completion Date: 6/30/2017

   HONEY CREEK RESORT STATE PARK WILL BE RECEIVING AN IOWA DEPARTMENT OF NATURAL RESOURCES DESIGN GUIDE ENTRANCE PORTAL. IT WILL HAVE REAL STONE BRICKING (LIMESTONE), STEEL BRACKETING AND GLULAM TIMBER SUPPORTS AS WELL AS LIMESTONE CAPSTONES.

ESTIMATED QUANTITIES:
    GRADING & DEMOLITION     1 L.S.
    SEEDING, FERTILIZING AND MULCHING     1 L.S.
    ELECTRIC     1 L.S.
    ENTRANCE PORTAL     1 Each
    CONSTRUCTION STAKING     1 L.S.
    MOBILIZATION     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POLK -- PROJECT # 17-02-77-04                2/16/2017                Large Project Letting
BIG CREEK STATE PARK
RESTROOM BUILDING REPLACEMENT
Proposal Guarantee: $10,000
Completion Date: 6/30/2017

   This project consists of the demolition of two (2) existing restroom buildings at the East and West boat ramps and installing new precast concrete restroom buildings in the same location. This includes installing ADA sidewalks for access to the new buildings, all earthwork, supplying and installing the new structures and incidental work as required by the project documents and the DNR Inspector at Big Creek State Park in Polk County, IA.

ESTIMATED QUANTITIES:
    GRADING     1 L.S.
    SEEDING, FERTILIZING AND MULCHING     1 L.S.
    WATER SERVICE     1 L.S.
    4" SCHEDULE 40 PVC SANITARY SEWER AND CLEANOUTS     1 L.S.
    5" REINFORCED PCC SIDEWALK & GRANULAR SUBBASE     1,250 S.F.
    DEMOLITION     1 L.S.
    ELECTRICAL SERVICE     1 L.S.
    PRECAST 2-HOLE CONCRETE RESTROOM     1 Each
    PRECAST 4-HOLE CONCRETE RESTROOM     1 Each
    MOBILIZATION     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




POTTAWATTAMIE -- PROJECT # 16-04-78-01                2/16/2017                Large Project Letting
LAKE MANAWA
PICNIC AREA
Proposal Guarantee: $70,000
Completion Date: 9/15/2017

   This project involves the removal of the existing roadways, camp pads, utilities, restroom and shower building in the campground to construct a picnic area. Construction includes a new road, parking lot, modern restroom, shelter and utilities at Lake Manawa State Park, Pottawattamie County, Iowa.

ESTIMATED QUANTITIES:
    Clearing and Grubbing     1 L.S.
    Remove Existing Roadway Pavement     9,973 S.Y.
    Remove Existing Trail     17 S.Y.
    Remove Existing Sidewalk     219 S.Y.
    Remove Existing Gravel Parking     210.9 S.Y.
    Remove Existing Paved Parking     11,159.2 S.Y.
    Remove Camp Pads     6,069 S.Y.
    Remove Existing Hydrants and Posts     10 Each
    Abandon Existing Sanitary Sewer Pipe     264 L.F.
    Remove Existing Sanitary Sewer Manholes     1 Each
    Remove Existing Sanitary Sewer Pipe, 6"      210 L.F.
    Remove Existing Water Line     729 L.F.
    Remove Existing Electrical Line     200 L.F.
    Remove Existing Dump Station     1 L.S.
    Demolition     1 L.S.
    Sanitary Sewer Main, 6" Schedule 40 PVC     225 L.F.
    Water Main, 2" HDPE     2,067 L.F.
    Hydrants     2 Each
    Design Guide Shelter, Slab and Electric       1 L.S.
    Design Guide Restroom, Slab and MEP         1 L.S.
    Precast Concrete Double Vault     1 Each
    Pilot Rock Grill Q3-2460 B8 Surface Mount Grill with Model S7      2 Each
    Contour 6’ Redwood Bench with Powder Coated (Black) Surface Mount Frame     5 Each
    Furnish and Install Light Fixture     2 Each
    Light Pole and Base, Complete     2 Each
    Electrical Line     610 L.F.
    Urban Seeding, Fertilizing and Mulching     2.6 Acres
    Native Grass Seeding, Fertilizing and Mulching     4.6 Acres
    Class "A" Crushed Stone     37 Tons
    Special Backfill     5,374.6 S.Y.
    Roadway Pavement, PCC, 7"     428.4 S.Y.
    Shoulder Construction, Earth     4 STA.
    Sidewalk, PCC, 5"     1,127 S.Y.
    Parking Lot, PCC, 7"     4,658 S.Y.
    Detectable Warning Panel     96 S.F.
    Signing     4 Each
    Painted Pavement Markings, Waterborne/Solvent - White     26 STA.
    Excavation, Class 10, Roadway and Borrow     1 C.Y.
    Embankment-In-Place     15,926 C.Y.
    Erosion Control     2,076 L.F.
    Vegetative Noise Barrier     600 L.F.
    Drain-Down Pit     1 L.S.
    Full Depth HMA Finish Pacthes by Sy. Yd.     52 STA.-CY
    Full Depth HMA Finish Joint Pacthes by Count     2 Each
    Subbase Repair     52 STA.-CY
    Heavy Jet Cleaning, Sanitary Sewer     265 L.F.
    Furnish and Install Electric Meter     1 Each
    Construction Staking     1 L.S.
    Mobilization     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




WARREN -- PROJECT # 17-05-91-02                1/26/2017                Small Project Letting
LAKE AHQUABI STATE PARK
CAMPGROUND PIT VAULT RESTROOM
Proposal Guarantee: $0
Completion Date: 5/26/2017

   Install precast concrete pit vault restroom in campground at Lake Ahquabi State Park. Supply electrical power to new restroom from nearby pump building. Road crossing shall be bored. Demolish existing restroom. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




CASS -- PROJECT # 17-04-15-02                2/2/2017                Small Project Letting
LAKE ANITA
SINGLE PIT VAULT, DEMO OF OLD
Proposal Guarantee: $0
Completion Date: 4/20/2017

   Provide and install a precast concrete pit latrine at the east boat ramp at Lake Anita State Park. Removal of old building along with seeding of all disturbed areas is also required. Proposal & plan may be obtained by e-mailing name, address, and phone number.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov




HARDIN -- PROJECT # 17-02-42-02                2/9/2017                Small Project Letting
PINE LAKE STATE PARK
EMERGENCY ROAD REPAIR PHASE 1 OF 2
Proposal Guarantee: $0
Completion Date: 4/1/2017

   The Pine Lake State Park Emergency Road Repair, Phase 1 of 2, project near Eldora, IA consists of removing (15" VCP) and replacing (18" CMP) approximately 75' of roadway pipe, including aprons with metal toes, and repairing the associated roadway surface ~ 58 SY.

Contact:
Bruce Flippin
515-250-3719
bruce.flippin@dnr.iowa.gov




ALLAMAKEE -- PROJECT # 17-03-03-02                2/16/2017                Small Project Letting
YELLOW RIVER STATE FOREST
ROCK ON FIRE TOWER ROAD AND OTH
Proposal Guarantee: $0
Completion Date: 6/30/2017

   The Fire Tower Road Rock project consists of placing approximately 3700 ton road surfacing and 198 ton Class D Riprap on 5 miles of roadway at various locations in Yellow River State Forest near Harpers Ferry, Allamakee Co., Iowa. Proposal and Plan may be obtained by emailing name, address, and phone number.

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




JONES -- PROJECT # 17-06-53-01                2/16/2017                Small Project Letting
WAPSIPINICON STATE PARK
2017 STREAM BANK REPAIRS
Proposal Guarantee:
Completion Date: 4/28/2017

   Project includes placement of approximately 450 tons of Class E Revetment to repair a washout along Dutch Creek within Wapsipinicon State Park.

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov




LUCAS -- PROJECT # 17-05-59-04                2/16/2017                Small Project Letting
BROWN'S SLOUGH
REPLACE BRIDGE DECK
Proposal Guarantee: $0
Completion Date: 5/31/2017

   Replacing a bridge deck with steel bar grating. DNR will remove and salvage any usable wood planks. Contractor will remove and dispose of any remaining wood. Add W4x13 beams at 36" O.C. Then add bar grating for new bridge deck. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




MUSCATINE -- PROJECT # 16-06-70-03                2/17/2017                Small Project Letting
FAIRPORT FISHERIES MANAGEMENT UNIT
REPLACE 12 INCH RESERVOIR VAVLE
Proposal Guarantee: $0
Completion Date: 3/24/2017

   Project includes replacing a deteriorated existing valve with a 12" Eco Valve including all necessary excavation, concrete encasement, compaction and restoration.

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov




DICKINSON -- PROJECT # 17-01-30-06                2/23/2017                Small Project Letting
GULL POINT STATE PARK
COLD STORAGE BUILDING EXTERIOR STEEL REPLACEMENT
Proposal Guarantee: $0
Completion Date: 5/12/2017

   The intent of this project is to remove and replace the exterior steel skin of an existing 50'x87' Steel cold storage facility located at Gull Point State Park complex in Dickinson County, IA. Work will involve the removal of all the existing steel skin and trim along with the existing roof insulation followed by installation of new steel skin, associated trim, and a new steel walk door.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




LINN -- PROJECT # 17-06-57-05                2/23/2017                Small Project Letting
PALISADES-KEPLER STATE PARK
WASHOUT REPAIR
Proposal Guarantee: $0
Completion Date: 4/28/2017

   Project includes repairing a washout at a culvert outletting into the Cedar River by placing approximately 96 tons of Class A Revetment on 70 SY of engineering fabric within Palisades-Kepler State Park.

Contact:
Michael Dufoe
515-985-9196
Michael.dufoe@dnr.iowa.gov