PROJECTS LETTING -  January , 2020

 
 
bid envelopes

 
 

The following projects are currently advertised for bids. Interested bidders may find general information about each project, as well as printable actual Contract Documents in PDF format. The general information is the same project description provided to Newspapers and by direct mail solicitations. The Contract Documents include the Drawings and the entire Project Manual.  Drawings can be printed on any regular or large format printers. The Project Manual includes Proposal Forms,  Front End Documents, General and Supplementary Covenants, and Technical specifications. All these are also completely printable.

Effective October 2009, the Department will no longer be responsible for providing hard copy notice to bidders or addenda to either contractors or plan rooms. An email listserv has been created to communicate electronically with vendors currently on file with the DNR. As a member of this listserv, you will receive electronic notice to bidder information on a regular basis. To subscribe to this list, click here.

The Department will be utilizing the vendor Beeline and Blue to provide printed copies of Plans and Specifications and Addenda upon request. The department will no longer provide complimentary copies of Plans and Specifications to contractors or sub-contractors after award of the contract. Please visit dfs.beelineandblue.com/iowa or contact (515) 244-1611 for more information.

To access any of these, unless you have already done so, you will need to download and install Acrobat Reader from the Adobe Website. 
You may obtain a free download from
 

Click on the project names below to view the one(s) which interest you.

FRANKLIN 19-02-35-02 Beed's Lake - Flood Repairs-2020-01-09   Bid Completion detail
HARDIN 20-02-42-01 Pine Lake - Tunnel Drainage Repair-2020-01-09   Bid Completion detail
POLK 17-02-77-09 Big Creek WMA - Road Maintenance-2020-01-09   Bid Completion detail
POLK 17-02-77-09 Big Creek WMA - Road Maintenance - Contract-2020-01-09   Bid Completion detail
TAYLOR 19-04-87-01 Lake of Three Fires - Effluent Chlorination System-2020-01-09   Bid Completion detail
LUCAS 20-05-59-07 Rathbun WMA - North Colyn - Bridge Deck (rebid)-2020-01-16   Bid Completion detail
POLK 20-05-77-04 Big Creek State Park - Entry Portals-2020-01-23   Bid Completion detail
SAC 20-01-81-01 Black Hawk Lake - Ice House Point Shoreline Armoring Phase II-2020-01-23   Bid Completion detail
FAYETTE 18-03-33-01 Volga River State Recreation Area - Tree Clearing-2020-01-30   Bid Completion detail
SAC 20-02-81-03 Black Hawk State Park - Culvert Repair-2020-01-30   Bid Completion detail
MADISON 18-04-61-02 Badger Creek Recreation Area - Clear brush and trees -ditch (REBID)-2020-02-06   Bid Completion detail




POLK -- PROJECT # 20-05-77-04                1/23/2020                Large Project Letting
BIG CREEK STATE PARK
ENTRY PORTALS
Proposal Guarantee: $6,250
Completion Date: 5/1/2020

   Big Creek State Park will be receiving an Iowa DNR design guide entrance portal and a new sign guide portal (A3). The design guide portals will have real stone bricking, steel bracketing, and glulam timber supports as well as limestone capstones. The new portals will be placed near the entrances of the state parks, as shown.

ESTIMATED QUANTITIES:
    CLEARING AND GRUBBING     1 L.S.
    SEEDING, FERTILIZING, AND MULCHING     1 L.S.
    DESIGN GUIDE PORTAL     1 L.S.
    A3 PORTAL     1 L.S.
    CONSTRUCTION STAKING     1 L.S.
    MOBILIZATION     1 L.S.

notice to bidders

download plans and specs

Plans can be ordered by following this link: http://bit.ly/IADNRPlans

planholders list




FRANKLIN -- PROJECT # 19-02-35-02                1/9/2020                Small Project Letting
BEED'S LAKE
FLOOD REPAIRS
Proposal Guarantee: $0
Completion Date: 5/1/2020

   This project is to repair flood damage to the spillway trail at Beeds Lake State Park including riprap placement, bank repair, gabion baskets and erosion stone and 1" road stone and other work as directed by the DNR Engineer.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov




HARDIN -- PROJECT # 20-02-42-01                1/9/2020                Small Project Letting
PINE LAKE
TUNNEL DRAINAGE REPAIR
Proposal Guarantee: $0
Completion Date: 5/15/2020

   This project involves the repair of the drainage at a pedestrian tunnel at Pine Lake State Park under a county highway as shown in the plans and as required by the DNR construction inspector.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov




POLK -- PROJECT # 17-02-77-09                1/9/2020                Small Project Letting
BIG CREEK WMA
ROAD MAINTENANCE
Proposal Guarantee: $0
Completion Date: 6/30/2020

   The proposed project includes a bituminous fog seal, painted symbols, patching, transverse joint repair and crack and joint cleaning and sealing (HMA surfaces) at Big Creek Wildlife Management Area as shown in the plans and as required by the DNR construction inspector.

Contact:
Don Labate
515-250-3714
Don.Labate@dnr.iowa.gov




TAYLOR -- PROJECT # 19-04-87-01                1/9/2020                Small Project Letting
LAKE OF THREE FIRES
EFFLUENT CHLORINATION SYSTEM
Proposal Guarantee: $0
Completion Date: 4/30/2020

   This project consists of installing tablet feeders for chlorination and de-chlorination,a chlorine contact tank and a sampling manhole for the treated wastewater after an existing lagoon system.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov




LUCAS -- PROJECT # 20-05-59-07                1/16/2020                Small Project Letting
RATHBUN WMA
NORTH COLYN - BRIDGE DECK (REBID)
Proposal Guarantee: $0
Completion Date: 6/30/2020

   This project involves replacing a wooden bridge deck with a steel bar grating deck. The bridge is 12'x16'. Send an email to request plans.

Contact:
Jason Kruse
(515) 250-3707
jason.kruse@dnr.iowa.gov




SAC -- PROJECT # 20-01-81-01                1/23/2020                Small Project Letting
BLACK HAWK LAKE
ICE HOUSE POINT SHORELINE ARMORING PHASE II
Proposal Guarantee: $0
Completion Date: 4/17/2020

   This project is designed to add erosion protection via fieldstone revetment to the shoreline of Black Hawk Lake in the public area known as Ice House Point in Sac County, IA. Work under this contract involves supply and installation of 575 TN of fieldstone revetment along approximately 475 lineal feet of shoreline.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




FAYETTE -- PROJECT # 18-03-33-01                1/30/2020                Small Project Letting
VOLGA RIVER STATE RECREATION AREA
TREE CLEARING
Proposal Guarantee: $0
Completion Date: 3/31/2020

   This project consists of removing trees from the gullies within the Frog Hollow Lake Watershed in Volga River SRA near Fayette, Iowa. Proposal may be obtained by emailing name, address, and phone number to melvin.pacovsky@dnr.iowa.gov

Contact:
Mel Pacovsky
319-240-3553
melvin.pacovsky@dnr.iowa.gov




SAC -- PROJECT # 20-02-81-03                1/30/2020                Small Project Letting
BLACK HAWK STATE PARK
CULVERT REPAIR
Proposal Guarantee: $0
Completion Date: 6/5/2020

   This project is designed to repair separated pipe joints on an existing dual 24" concrete pipe road crossing in Black Hawk State Park, Sac County, IA. Work under this contract involves removal and replacement of 4 sections of 24" RCP pipe, concrete roadway patching, and stone erosion protection for the inlet of the culverts.

Contact:
Jeff Felts
515-250-3712
Jeff.Felts@dnr.iowa.gov




MADISON -- PROJECT # 18-04-61-02                2/6/2020                Small Project Letting
BADGER CREEK RECREATION AREA
CLEAR BRUSH AND TREES -DITCH (REBID)
Proposal Guarantee:
Completion Date: 3/31/2020

   Clear Brush & Trees - Ditch (REBID), Badger Creek Recreation Area (120th LN) Cut down all trees and shrubs along roadway that are 4" in diameter or larger along both sides of paved roadway. All trees and shrubs shall be cut at ground level and treated to prevent regrowth. All cut trees and shrubs shall be placed in road ditch and not in crop fields, no branches shall be left within 5' of pavement edge. There is approximately 45 trees on the north side of the roadway, 15 trees on the east side of the roadway by the boat ramp and 130 trees on the south side of the roadway. The trees removed along the road in the boat ramp area shall be placed in a pile off the northwest side of the parking area. Other piles could be made along the roadway if the trees will not fit in the roadway ditch in areas that are not crop field. Brush is expected to be removed flush with the ground. Tearing up or digging in the ground is not expected on this project. Disturbed areas to be repaired and seeded by contractor at no additional cost to the Iowa DNR. Contractor shall take extra care to protect trees and property outside the construction area. Contractor will be responsible for materials and equipment stored on site.

Contact:
Mark Johnson
515-250-3713
mark.johnson@dnr.iowa.gov