BID LETTING RESULTS - September, 2013

 
 

The following are the results of bids received September, 2013 for projects which the Iowa Department of Natural Resources required to be constructed.  Should there be any discrepancies between the bids below and those provided and recorded in official bid tabs, the official bid tabs govern.
 

To see the Project Details for this Bid Letting Click Here .




GUTHRIE -- PROJECT # 14-04-39-03                9/3/2013                Large Project Letting
SPRINGBROOK
SHOWER BLDG
 
BIDS RECEIVED:
    Burkett Construction LLC 
$205,257.35 
    Caliber Concrete LLC 
$317,249.00 
    Lansink Construction Inc. 
$437,704.00 

full bid tab