LINN -- PROJECT # 13-06-57-05                8/27/2015                Small Project Letting
PLEASANT CREEK STATE RECREATION AREA
DRAW DOWN VALVE REPLACEMENT
 
BIDS RECEIVED:
    Engineering Consultants, Inc 
$42,859.00 
    B.G. Brecke, Inc. 
$57,275.00 

full bid tab




SAC -- PROJECT # 15-01-81-01                8/27/2015                Small Project Letting
BLACK HAWK LAKE STATE MARINA
BLACK HAWK LAKE MARINA SEDIMENT REMOVAL
 
BIDS RECEIVED:
    Healy Excavating 
$93,390.00 
    Spring Lake Construction 
$116,900.00 
    Veit & Company, Inc. 
$284,400.00 

full bid tab