 Bids For:  Location:   Black Hawk Lake State Marina  Date: 8/27/2015  Project No.  
  Black Hawk Lake Marina Sediment Removal  County:   SAC  Time: 3:00 p.m.  15-01-81-01

 

 
1
2
3
Estimated Cost: $64,900.00
Contractor: 
Healy ExcavatingSpring Lake ConstructionVeit & Company, Inc.
Funding Source: 50% Marine Fuel Tax, 50% Federal-Boat Safety (Coast Guard), 3483 Perkins Ave
4123 NW 95th PL
14000 Veit PL
Lake View IA  51450Polk City IA  50226Rogers MN  55374
Plan Sets Requested: 0
Quantities
712-665-4500712-830-4515763-428-2242
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$3,000.00$3,000.00 $3,000.00$3,000.00 $65,000.00$65,000.00 
2Shoreline Vegetation Clearing1L.S.$3,500.00$3,500.00 $3,500.00$3,500.00 $11,000.00$11,000.00 
3Excavation & Spoil6200C.Y.$12.45$77,190.00 $17.00$105,400.00 $31.00$192,200.00 
4Floating Silt Curtain80L.F.$27.50$2,200.00 $50.00$4,000.00 $65.00$5,200.00 
5Site Restoration & Seeding1L.S.$7,500.00$7,500.00 $1,000.00$1,000.00 $11,000.00$11,000.00 
      $93,390.00  $116,900.00  $284,400.00 
 



 