WARREN -- PROJECT # 17-05-91-02                1/26/2017                Small Project Letting
LAKE AHQUABI STATE PARK
CAMPGROUND PIT VAULT RESTROOM
 
BIDS RECEIVED:
    Haworth Land Construction 
$35,880.00 
    Iowa Technology Solutions LLC dba ITS Land Improv. 
$44,509.50 
    Savage Dirt Works, LLC 
$45,492.65 
    Joiner Construction Co. Inc. 
$46,750.00 
    Hymbaugh Construction 
$48,500.00 
    Caliber Concrete LLC 
$53,912.00 