The following are the results of bids received August, 2016 for public improvement projects which the Iowa Department of Natural Resources requires to be constructed. The results included below are the bids that were received timely. Consistent with the Specifications Manual, in the event of a discrepancy between a unit price, extensions or total amounts of bid, the unit price proposed by the bidder has been used to accurately calculate the total price based on the quantities identified in the project specifications.
NO DETERMINATION HAS BEEN MADE BY THIS PUBLICATION AS TO WHICH BID, IF ANY, IS THE LOWEST RESPONSIBLE, RESPONSIVE BID. THE DNR RESERVES THE RIGHT, AFTER REVIEW OF THE BIDS SUBMITTED, TO AWARD A CONTRACT FOR THE PROJECTS LISTED BELOW TO THE ENTITY SUBMITTING THE LOWEST RESPONSIBLE, RESPONSIVE BID OR TO REJECT ALL BIDS.
View Project Details for this Bid Letting
| DICKINSON -- PROJECT # 15-01-30-05 8/18/2016 Large Project Letting
| CENTER LAKE
| FISH BARRIER SYSTEM & SHORELINE RESTORATION | | BIDS RECEIVED: |
Valley Contracting Inc
|
$563,511.00 |
Beck Excavating Inc.
|
$617,893.50 |
Christensen Construction & Design Company
|
$793,172.23 |

|
| MONROE -- PROJECT # 15-05-68-01 8/18/2016 Large Project Letting
| LAKE MIAMI
| SEDIMENT PONDS | | BIDS RECEIVED: |
Kinman Company Inc
|
$326,024.21 |
Seaton Construction
|
$366,334.05 |
Adam Benner dba Benner Trucking & Dozing
|
$391,481.75 |
Sterk Excavating Inc
|
$412,978.33 |
LANGMAN CONSTRUCTION INC
|
$419,073.10 |
Hendrickson Transportation, LLC
|
$840,409.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. RW Excavating & Dozing
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
| ALLAMAKEE -- PROJECT # 15-03-03-9 8/4/2016 Small Project Letting
| YELLOW RIVER STATE FOREST
| PAINT CREEK BANK STABILIZATION | | BIDS RECEIVED: |
Riehm Construction
|
$40,442.90 |
Nick Jones Earthmoving
|
$43,765.00 |
Donlon Brothers Construction LLC
|
$45,956.00 |
David Ryan Construction
|
$46,954.00 |
Mehmert Tiling, Inc.
|
$50,744.70 |
Connolly Construction Inc.
|
$55,344.00 |
Landau Golf Corp dba Greenrain Services
|
$74,940.00 |
The following apparent low bidders were found to be Non-Responsive and/or Not Responsible. No determinations have been made regarding the Responsiveness and Responsibility of the bidders that are not the apparent low. Dubuque Barge & Fleeting Service Co. dba
DNR reserves the right to modify this list as it reviews and inspects the bids received. DNR will update the bid tab accordingly.

|
| UNION -- PROJECT # 20-04-88-01 8/4/2016 Small Project Letting
| GRAND RIVER WILDLIFE UNIT
| OUTLET PIPE REPAIR / 12 MILE | | BIDS RECEIVED: |
JNC Construction, LLC
|
$11,438.42 |
Jeff Sickels Dozing LLC
|
$14,200.00 |
Dingman Const.
|
$16,877.16 |
Hymbaugh Construction
|
$22,000.00 |

|
| WINNESHIEK -- PROJECT # 17-03-96-02 8/4/2016 Small Project Letting
| DECORAH FISH HATCHERY
| REPLACE OFFICE & HOUSE ROOFS REBID | | BIDS RECEIVED: |
Lifetime Gutters & More
|
$20,495.00 |
All Season Const. Co., Inc.
|
$20,773.00 |
Hymbaugh Construction
|
$24,680.00 |

|
| TAMA -- PROJECT # 14-05-86-06 8/11/2016 Small Project Letting
| UNION GROVE
| TRAIL ARMORING | | BIDS RECEIVED: |
MD Construction INC
|
$47,442.09 |
Nagle Land Tiling Inc
|
$50,874.00 |
Landau Golf Corp dba Greenrain Services
|
$56,974.00 |
Hatch Grading & Contracting Inc.
|
$58,770.00 |
LaGrange, Inc.
|
$58,863.00 |
Peterson Contractors, Inc.
|
$69,843.05 |
Gehrke Inc
|
$70,560.60 |
Con-Struct Inc.
|
$72,412.00 |
Lanphier Excavating LLC
|
$75,991.49 |
Jasper Construction Services, Inc.
|
$89,205.00 |
Strand Excavating Inc
|
$107,412.00 |

|
| DELAWARE -- PROJECT # 17-03-28-01 8/25/2016 Small Project Letting
| BACKBONE STATE PARK
| REMOVAL OF BRIDGE EMBUTMENTS & BRIDGE | | BIDS RECEIVED: |
Lansing Brothers Construction Co. Inc.
|
$7,750.00 |
Brown's Well Srv and Excavating LLC
|
$12,700.00 |
David Ryan Construction
|
$15,050.00 |
Matt Construction, Inc.
|
$19,095.00 |
Taylor Construction Inc.
|
$19,950.00 |
Connolly Construction Inc
|
$30,020.00 |

|
| WRIGHT -- PROJECT # 15-02-99-01 8/25/2016 Small Project Letting
| CLEAR LAKE WILDLIFE UNIT
| MORSE LAKE BOAT RAMP | | BIDS RECEIVED: |
Larson Contracting Central, LLC
|
$5,299.00 |
Richards Construction Co., Inc.
|
$15,995.00 |
|
|