IOWA DEPARTMENT OF NATURAL RESOURCES |
|
Bids For: | Location: | Lake Miami | Date: 8/18/2016 | Project No. |
Sediment Ponds | County: | MONROE | Time: 11:00 AM | 15-05-68-01 |
1 | 2 | 3 | |||||||||||
Estimated Cost: $340,000.00 | Contractor: | Kinman Company Inc | Seaton Construction | Adam Benner dba Benner Trucking & Dozing | |||||||||
Funding Source: 100% Lake Restoration, | 3101 Kent Ave | 602 Locust St PO Box 213 | 248th Trail 3215 | ||||||||||
Oskaloosa IA 52577 | Deep River IA 522220213 | Panora IA 50216 | |||||||||||
Plan Sets Requested: 7 | Quantities | 641-660-0897 | 641-595-2261 | 641-757-1719 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | MOBILIZATION | 1 | L.S. | $6,715.21 | $6,715.21 | $6,700.00 | $6,700.00 | $15,000.00 | $15,000.00 | ||||
2 | 6" DIA SMP | 469 | L.F. | $15.00 | $7,035.00 | $16.00 | $7,504.00 | $18.00 | $8,442.00 | ||||
3 | 12" DIA SMP | 142 | L.F. | $20.75 | $2,946.50 | $20.00 | $2,840.00 | $30.00 | $4,260.00 | ||||
4 | TRASH RACK, 6" | 2 | Each | $295.00 | $590.00 | $350.00 | $700.00 | $240.00 | $480.00 | ||||
5 | TRASH RACK, 12" | 1 | Each | $325.00 | $325.00 | $350.00 | $350.00 | $360.00 | $360.00 | ||||
6 | 5' X 5' X 1/4" ANTI SEEP COLLAR | 21 | Each | $292.00 | $6,132.00 | $450.00 | $9,450.00 | $200.00 | $4,200.00 | ||||
7 | EARTHFILL, EMBANKMENT | 60715 | C.Y. | $1.25 | $75,893.75 | $1.40 | $85,001.00 | $1.50 | $91,072.50 | ||||
8 | EARTHFILL, CORE TRENCH | 2854 | C.Y. | $1.00 | $2,854.00 | $1.30 | $3,710.20 | $1.80 | $5,137.20 | ||||
9 | SEED & MULCH | 3.8 | Acres | $1,480.00 | $5,624.00 | $1,500.00 | $5,700.00 | $900.00 | $3,420.00 | ||||
10 | CLEARING & GRUBBING | 4.4 | Acres | $1,100.00 | $4,840.00 | $1,200.00 | $5,280.00 | $1,800.00 | $7,920.00 | ||||
11 | 6" STRIPPING | 8737 | C.Y. | $1.00 | $8,737.00 | $3.00 | $26,211.00 | $2.25 | $19,658.25 | ||||
12 | 6" Perforated Tile | 70 | L.F. | $4.00 | $280.00 | $4.00 | $280.00 | $2.50 | $175.00 | ||||
13 | 12" Hickenbottom Style Intake | 1 | Each | $650.00 | $650.00 | $400.00 | $400.00 | $500.00 | $500.00 | ||||
$122,622.46 | $154,126.20 | $160,624.95 | |||||||||||
Alternate | |||||||||||||
14 | 6" Dia Smooth Steel Pipe | 177 | L.F. | $15.00 | $2,655.00 | $16.00 | $2,832.00 | $18.00 | $3,186.00 | ||||
Alternate | |||||||||||||
15 | Trash Rack | 1 | Each | $295.00 | $295.00 | $300.00 | $300.00 | $240.00 | $240.00 | ||||
16 | 5' x 5' x 1/4" Anti-Seep Collar | 5 | Each | $310.00 | $1,550.00 | $250.00 | $1,250.00 | $200.00 | $1,000.00 | ||||
17 | Earthfill, Embankment | 34071 | C.Y. | $1.25 | $42,588.75 | $1.35 | $45,995.85 | $1.50 | $51,106.50 | ||||
Alternate | |||||||||||||
18 | Eartfill, Core Trench | 1346 | C.Y. | $1.00 | $1,346.00 | $1.50 | $2,019.00 | $1.80 | $2,422.80 | ||||
Alternate | |||||||||||||
19 | Seed & Mulch | 1.5 | Acres | $1,480.00 | $2,220.00 | $1,500.00 | $2,250.00 | $900.00 | $1,350.00 | ||||
Alternate | |||||||||||||
20 | Clear & Grubb | 7 | Acres | $1,100.00 | $7,700.00 | $1,200.00 | $8,400.00 | $1,800.00 | $12,600.00 | ||||
Alternate | |||||||||||||
21 | 6" Stripping | 3630 | C.Y. | $1.00 | $3,630.00 | $3.00 | $10,890.00 | $2.25 | $8,167.50 | ||||
Alternate | |||||||||||||
22 | Riprap | 3266 | Tons | $42.25 | $137,988.50 | $41.00 | $133,906.00 | $44.00 | $143,704.00 | ||||
Alternate | |||||||||||||
23 | Engineering Fabric | 546 | S.Y. | $2.25 | $1,228.50 | $2.50 | $1,365.00 | $5.00 | $2,730.00 | ||||
Alternate | |||||||||||||
24 | Clearing & Grubbing | 1 | Acres | $1,100.00 | $1,100.00 | $1,200.00 | $1,200.00 | $3,000.00 | $3,000.00 | ||||
Alternate | |||||||||||||
25 | Temporary Seeding | 1 | Acres | $100.00 | $100.00 | $1,500.00 | $1,500.00 | $350.00 | $350.00 | ||||
26 | Temporary Ditch Crossing | 1 | L.S. | $1,000.00 | $1,000.00 | $300.00 | $300.00 | $1,000.00 | $1,000.00 | ||||
$326,024.21 | $366,334.05 | $391,481.75 | |||||||||||
4 | 5 | 6 | |||||||||||
Estimated Cost: $340,000.00 | Contractor: | Sterk Excavating Inc | LANGMAN CONSTRUCTION INC | RW Excavating & Dozing | |||||||||
Funding Source: 100% Lake Restoration, | 117 - 180th Ave | 220 - 34TH AVENUE | 88th Ave W 13293 South | ||||||||||
Otley IA 50214 | ROCK ISLAND IL 61201 | Prairie City IA 50228 | |||||||||||
Plan Sets Requested: 7 | Quantities | 641-416-0110 | (309)786-8885 | 515-994-2648 | |||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | MOBILIZATION | 1 | L.S. | $9,300.00 | $9,300.00 | $22,000.00 | $22,000.00 | $20,000.00 | $20,000.00 | ||||
2 | 6" DIA SMP | 469 | L.F. | $12.56 | $5,890.64 | $22.00 | $10,318.00 | $20.00 | $9,380.00 | ||||
3 | 12" DIA SMP | 142 | L.F. | $25.82 | $3,666.44 | $35.00 | $4,970.00 | $40.00 | $5,680.00 | ||||
4 | TRASH RACK, 6" | 2 | Each | $522.73 | $1,045.46 | $500.00 | $1,000.00 | $1,200.00 | $2,400.00 | ||||
5 | TRASH RACK, 12" | 1 | Each | $798.25 | $798.25 | $1,000.00 | $1,000.00 | $3,000.00 | $3,000.00 | ||||
6 | 5' X 5' X 1/4" ANTI SEEP COLLAR | 21 | Each | $253.83 | $5,330.43 | $350.00 | $7,350.00 | $100.00 | $2,100.00 | ||||
7 | EARTHFILL, EMBANKMENT | 60715 | C.Y. | $2.06 | $125,072.90 | $1.65 | $100,179.75 | $2.98 | $180,930.70 | ||||
8 | EARTHFILL, CORE TRENCH | 2854 | C.Y. | $2.32 | $6,621.28 | $1.00 | $2,854.00 | $4.77 | $13,613.58 | ||||
9 | SEED & MULCH | 3.8 | Acres | $1,339.00 | $5,088.20 | $1,500.00 | $5,700.00 | $2,000.00 | $7,600.00 | ||||
10 | CLEARING & GRUBBING | 4.4 | Acres | $2,575.00 | $11,330.00 | $3,220.00 | $14,168.00 | $2,700.00 | $11,880.00 | ||||
11 | 6" STRIPPING | 8737 | C.Y. | $2.06 | $17,998.22 | $2.00 | $17,474.00 | $4.00 | $34,948.00 | ||||
12 | 6" Perforated Tile | 70 | L.F. | $3.09 | $216.30 | $5.00 | $350.00 | $2.00 | $140.00 | ||||
13 | 12" Hickenbottom Style Intake | 1 | Each | $515.00 | $515.00 | $250.00 | $250.00 | $250.00 | $250.00 | ||||
Alternate | |||||||||||||
14 | 6" Dia Smooth Steel Pipe | 177 | L.F. | $15.09 | $2,670.93 | $22.00 | $3,894.00 | $20.00 | $3,540.00 | ||||
Alternate | |||||||||||||
15 | Trash Rack | 1 | Each | $625.21 | $625.21 | $500.00 | $500.00 | $1,200.00 | $1,200.00 | ||||
16 | 5' x 5' x 1/4" Anti-Seep Collar | 5 | Each | $249.88 | $1,249.40 | $350.00 | $1,750.00 | $100.00 | $500.00 | ||||
17 | Earthfill, Embankment | 34071 | C.Y. | $2.11 | $71,889.81 | $1.85 | $63,031.35 | $2.98 | $101,531.58 | ||||
Alternate | |||||||||||||
18 | Eartfill, Core Trench | 1346 | C.Y. | $2.32 | $3,122.72 | $1.00 | $1,346.00 | $4.77 | $6,420.42 | ||||
Alternate | |||||||||||||
19 | Seed & Mulch | 1.5 | Acres | $1,339.00 | $2,008.50 | $1,500.00 | $2,250.00 | $2,000.00 | $3,000.00 | ||||
Alternate | |||||||||||||
20 | Clear & Grubb | 7 | Acres | $2,060.00 | $14,420.00 | $3,220.00 | $22,540.00 | $2,700.00 | $18,900.00 | ||||
Alternate | |||||||||||||
21 | 6" Stripping | 3630 | C.Y. | $2.06 | $7,477.80 | $2.00 | $7,260.00 | $4.00 | $14,520.00 | ||||
Alternate | |||||||||||||
22 | Riprap | 3266 | Tons | $34.65 | $113,166.90 | $37.00 | $120,842.00 | $55.00 | $179,630.00 | ||||
Alternate | |||||||||||||
23 | Engineering Fabric | 546 | S.Y. | $1.89 | $1,031.94 | $1.00 | $546.00 | $3.00 | $1,638.00 | ||||
Alternate | |||||||||||||
24 | Clearing & Grubbing | 1 | Acres | $1,030.00 | $1,030.00 | $5,000.00 | $5,000.00 | $3,000.00 | $3,000.00 | ||||
Alternate | |||||||||||||
25 | Temporary Seeding | 1 | Acres | $412.00 | $412.00 | $1,500.00 | $1,500.00 | $2,000.00 | $2,000.00 | ||||
26 | Temporary Ditch Crossing | 1 | L.S. | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $5,000.00 | $5,000.00 | ||||
$412,978.33 | $419,073.10 | $632,802.28 | |||||||||||
7 | 8 | 9 | |||||||||||
Estimated Cost: $340,000.00 | Contractor: | Hendrickson Transportation, LLC | |||||||||||
Funding Source: 100% Lake Restoration, | 2762 310th St | ||||||||||||
Hamburg IA 51640 | |||||||||||||
Plan Sets Requested: 7 | Quantities | 712-382-1505 | |||||||||||
No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
1 | MOBILIZATION | 1 | L.S. | $98,000.00 | $98,000.00 | $0.00 | $0.00 | ||||||
2 | 6" DIA SMP | 469 | L.F. | $25.00 | $11,725.00 | $0.00 | $0.00 | ||||||
3 | 12" DIA SMP | 142 | L.F. | $40.00 | $5,680.00 | $0.00 | $0.00 | ||||||
4 | TRASH RACK, 6" | 2 | Each | $200.00 | $400.00 | $0.00 | $0.00 | ||||||
5 | TRASH RACK, 12" | 1 | Each | $250.00 | $250.00 | $0.00 | $0.00 | ||||||
6 | 5' X 5' X 1/4" ANTI SEEP COLLAR | 21 | Each | $500.00 | $10,500.00 | $0.00 | $0.00 | ||||||
7 | EARTHFILL, EMBANKMENT | 60715 | C.Y. | $4.00 | $242,860.00 | $0.00 | $0.00 | ||||||
8 | EARTHFILL, CORE TRENCH | 2854 | C.Y. | $5.00 | $14,270.00 | $0.00 | $0.00 | ||||||
9 | SEED & MULCH | 3.8 | Acres | $1,800.00 | $6,840.00 | $0.00 | $0.00 | ||||||
10 | CLEARING & GRUBBING | 4.4 | Acres | $4,500.00 | $19,800.00 | $0.00 | $0.00 | ||||||
11 | 6" STRIPPING | 8737 | C.Y. | $3.00 | $26,211.00 | $0.00 | $0.00 | ||||||
12 | 6" Perforated Tile | 70 | L.F. | $10.00 | $700.00 | $0.00 | $0.00 | ||||||
13 | 12" Hickenbottom Style Intake | 1 | Each | $500.00 | $500.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
14 | 6" Dia Smooth Steel Pipe | 177 | L.F. | $25.00 | $4,425.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
15 | Trash Rack | 1 | Each | $200.00 | $200.00 | $0.00 | $0.00 | ||||||
16 | 5' x 5' x 1/4" Anti-Seep Collar | 5 | Each | $500.00 | $2,500.00 | $0.00 | $0.00 | ||||||
17 | Earthfill, Embankment | 34071 | C.Y. | $4.00 | $136,284.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
18 | Eartfill, Core Trench | 1346 | C.Y. | $5.00 | $6,730.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
19 | Seed & Mulch | 1.5 | Acres | $1,800.00 | $2,700.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
20 | Clear & Grubb | 7 | Acres | $4,500.00 | $31,500.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
21 | 6" Stripping | 3630 | C.Y. | $3.00 | $10,890.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
22 | Riprap | 3266 | Tons | $60.00 | $195,960.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
23 | Engineering Fabric | 546 | S.Y. | $4.00 | $2,184.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
24 | Clearing & Grubbing | 1 | Acres | $4,500.00 | $4,500.00 | $0.00 | $0.00 | ||||||
Alternate | |||||||||||||
25 | Temporary Seeding | 1 | Acres | $1,800.00 | $1,800.00 | $0.00 | $0.00 | ||||||
26 | Temporary Ditch Crossing | 1 | L.S. | $3,000.00 | $3,000.00 | $0.00 | $0.00 | ||||||
$840,409.00 | $0.00 | $0.00 | |||||||||||