Animal Feeding Operation - Construction Review Details

Hickory Hill Farms Inc. - #61067
4045 400th Street Hospers, Iowa 51238

Field Office 3
NW 1/4 of the NE 1/4 of Section 12, T095N, R44W
Holland Township, Sioux County


Construction Review


Construction Fee
Fee Action Type Amount Date Received
Construction Permit Fee Received $250.00 04/04/2024
MMP Filing Fee Received $250.00 04/04/2024
Indemnity Fee Received $563.00 04/04/2024
Total: $1063.00

Construction Review Actions
Actions Date Document User
Permit Approved 05/22/2024 61067_Final Permit_052224.pdf
cgarza
Notice of Intent Sent (Draft Permit) 05/07/2024 61067 NOI 050724.pdf
cgarza
County Received Notice of Intent (Start of 14 day appeal period) 05/07/2024 61067 County Receipt 050724.pdf
cgarza
County Proof of Publication/Recommendation Received 04/29/2024 61067_Co Recomm_04232024.pdf
61067_proof of pub_04292024.pdf
ppetitti
FO Site Survey Received 04/26/2024 61067_site survey_04262024.pdf
ppetitti
Application Received 04/04/2024 61067_revised site plan_03282024.pdf
61067_Appl plans_03282024.pdf
61067_Appl_03282024.pdf
61067_County Receipt_04012024.pdf
ppetitti
Master Matrix Submitted 04/04/2024 61067_Matrix_03282024.pdf
ppetitti
Enforcement Review 04/04/2024 61067_int parties_04042024.pdf
ppetitti
County Notice Letter Sent 04/04/2024 61067_County Notice_04042024.pdf
ppetitti
Correspondence 04/04/2024 61067_Co receipt of notice_04042024.pdf
ppetitti
FO Site Survey Requested 04/04/2024 61067_W.R.#5634_04042024.pdf
ppetitti
Animal Summary
Animal Unit Information Confinements Open Feedlot
Current Authorized AU 5680.00 1000.00
Proposed AU Change 2815.00 0
Total AU If Approved 8495.00 1000.00
Total Animal Weight Capacity if Approved


Features
Feature Type Feature Name Feature Description Operation Type
Production Area Confinement Building - Concrete Floor free stall bqrn addition 2024 Confinement
Production Area Confinement Building - Concrete Floor 1100 hd mature free stall barn Confinement
Treatment Digester Anaerobic digester Confinement
Production Area Confinement Building 850 hd freestall barn Confinement
Storage Structure Earthen Basin 33MG basin Confinement
Storage Structure Settled Open Feedlot Effluent Basin 4.9MG runoff basin Open Feedlot
Production Area Confinement Building 100 head bed pack Confinement
Storage Structure Sand Settling Lane sand lane Confinement
Production Area Confinement Building 200 head holding barn Confinement
Storage Structure Earthen Basin 10.5MG cell #2 Confinement
Production Area Feedlot 3.88 acres for 500 heifers Open Feedlot
Production Area Feedlot 9.54 acres of feed storage Open Feedlot
Production Area Confinement Building 2-700 head freestall barns Confinement
Storage Structure Earthen Basin 8.6MG cell #1 Confinement