 Bids For:  Location:   Spirit Lake (Templar Lagoon)  Date: 5/12/2011  Project No.  
  Fishing "Boardwalk" / Dredging  County:   DICKINSON  Time: 3:00 p.m.  09-01-30-01

 

 
1
2
3
Estimated Cost: $76,000.00
Contractor: 
Christensen Construction & Design Company
Funding Source: 100% F&W Trust-Fisheries Non-Habitat Stamp, 821 S 28th St


Estherville IA  51334    
Plan Sets Requested: 0
Quantities
712-362-7755
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Mobilization1L.S.$1,350.00$1,350.00 $0.00 $0.00 
2Earthwork54C.Y.$25.00$1,350.00 $0.00 $0.00 
3Class "A" Crushed Stone35Tons$9.66$338.10 $0.00 $0.00 
46" PCC Parking65S.Y.$47.15$3,064.75 $0.00 $0.00 
5Curb Removal45L.F.$18.00$810.00 $0.00 $0.00 
6Curb & Cutter75L.F.$27.00$2,025.00 $0.00 $0.00 
74" PCC Sidewalk27S.Y.$37.52$1,013.04 $0.00 $0.00 
8Reinforced PCC Abutment1L.S.$3,024.00$3,024.00 $0.00 $0.00 
9Fieldstone Riprap3Tons$135.00$405.00 $0.00 $0.00 
108"x 8" Treated Wood Piles - In-Place40Each$725.63$29,025.20 $0.00 $0.00 
11Fishing Boardwalk - Complete Sta 0+39.93 to Sta 2+46.751L.S.$59,500.00$59,500.00 $0.00 $0.00 
12Seeding - Class "B"1L.S.$405.00$405.00 $0.00 $0.00 
13Silt Fence25L.F.$8.12$203.00 $0.00 $0.00 
      $102,513.09  $0.00  $0.00 
Alternate        
14Fishing Boardwalk Extension - Complete Sta 2+46.75 to Sta 3+17.661L.S.$20,400.00$20,400.00 $0.00 $0.00 
Alternate        
158"x8" Treated Wood Piles14Each$725.63$10,158.82 $0.00 $0.00 
      $133,071.91  $0.00  $0.00 
 



 