IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Backbone State Park | Date: 6/16/2011 | Project No. |
| CCC Museum Fdn Repairs | County: | DELAWARE | Time: 11:00 a.m. | 07-03-28-02 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $17,171.00 | Contractor: | Lansing Brothers Construction | Matt Construction Inc | Raber Construction | |||||||||
| Funding Source: 100% REAP Land Management, | 101 E. 1st St | 203 Y Ave | 1296 145th St | ||||||||||
| Luxemburg IA 52056 | Sumner IA 50674 | Fairbank IA 50629 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 563-543-7360 | 563-578-8418 | 319-464-4324 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Retaining Wall waterproofing and site work | 1 | L.S. | $3,260.00 | $3,260.00 | $3,300.00 | $3,300.00 | $8,600.00 | $8,600.00 | ||||
| 2 | Building concrete foundation wall repair & epoxy injection | 1 | L.S. | $2,000.00 | $2,000.00 | $3,800.00 | $3,800.00 | $4,300.00 | $4,300.00 | ||||
| 3 | Interior wood floor joist repairs | 1 | L.S. | $500.00 | $500.00 | $500.00 | $500.00 | $1,200.00 | $1,200.00 | ||||
| $5,760.00 | $7,600.00 | $14,100.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $17,171.00 | Contractor: | Tricon Construction | |||||||||||
| Funding Source: 100% REAP Land Management, | 2245 Kerper Blvd Ste 2 | ||||||||||||
| Dubuque IA 52001 | |||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-588-9516 | |||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Retaining Wall waterproofing and site work | 1 | L.S. | $25,200.00 | $25,200.00 | $0.00 | $0.00 | ||||||
| 2 | Building concrete foundation wall repair & epoxy injection | 1 | L.S. | $15,000.00 | $15,000.00 | $0.00 | $0.00 | ||||||
| 3 | Interior wood floor joist repairs | 1 | L.S. | $3,000.00 | $3,000.00 | $0.00 | $0.00 | ||||||
| $43,200.00 | $0.00 | $0.00 | |||||||||||
10/13/2026