IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Lost Grove Lake Access | Date: 5/19/2011 | Project No. |
| Shoreline Armoring / Fish Habitat | County: | SCOTT | Time: 11:00 a.m. | 08-06-82-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $1,155,000.00 | Contractor: | Langman Construction Inc. | Valley Construction Company | PETERSON CONTRACTORS INC (PCI-REINBECK) | |||||||||
| Funding Source: 40% Marine Fuel Tax, 30% F&W Trust-Fisheries Non-Habitat Stamp, 30% Federal-Boat Safety (Coast Guard), | 220 - 34th Avenue | 3610 78th Ave W | 104 Blackhawk St Box A | ||||||||||
| Rock Island IL 61201 | Rock Island IL 61201 | Reinbeck IA 50669 | |||||||||||
| Plan Sets Requested: 14 | Quantities | 309-786-8944 | 309-787-0292 | 319-345-2713 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Class "D" Revetment | 27279 | Tons | $25.50 | $695,614.50 | $25.50 | $695,614.50 | $29.50 | $804,730.50 | ||||
| 2 | Class "10" Excavation | 34450 | C.Y. | $2.00 | $68,900.00 | $3.30 | $113,685.00 | $1.10 | $37,895.00 | ||||
| 3 | Engineering Fabric | 33432 | S.Y. | $0.85 | $28,417.20 | $1.75 | $58,506.00 | $1.90 | $63,520.80 | ||||
| 4 | Class "A" Road Stone | 395 | Tons | $19.00 | $7,505.00 | $24.00 | $9,480.00 | $22.00 | $8,690.00 | ||||
| 5 | 3/8" Granular Surfacing | 584 | Tons | $20.00 | $11,680.00 | $25.00 | $14,600.00 | $18.00 | $10,512.00 | ||||
| 6 | Sheet Piling | 3255 | S.F. | $25.00 | $81,375.00 | $34.00 | $110,670.00 | $30.15 | $98,138.25 | ||||
| 7 | 3"x12" Bridge Planking | 388 | L.F. | $80.00 | $31,040.00 | $24.00 | $9,312.00 | $31.75 | $12,319.00 | ||||
| 8 | 2" Stone | 20 | Tons | $25.00 | $500.00 | $25.00 | $500.00 | $24.00 | $480.00 | ||||
| 9 | 6" Erosion Stone | 245 | Tons | $20.00 | $4,900.00 | $25.00 | $6,125.00 | $24.00 | $5,880.00 | ||||
| 10 | 3" Rock | 95 | Tons | $20.00 | $1,900.00 | $25.00 | $2,375.00 | $24.00 | $2,280.00 | ||||
| 11 | Sand | 110 | Tons | $20.00 | $2,200.00 | $23.00 | $2,530.00 | $22.00 | $2,420.00 | ||||
| 12 | Earthfill | 32395 | C.Y. | $2.50 | $80,987.50 | $1.50 | $48,592.50 | $1.50 | $48,592.50 | ||||
| 13 | Tree Structures | 3 | Each | $500.00 | $1,500.00 | $2,000.00 | $6,000.00 | $3,300.00 | $9,900.00 | ||||
| 14 | Debris Cleanup | 1 | L.S. | $1,000.00 | $1,000.00 | $800.00 | $800.00 | $8,500.00 | $8,500.00 | ||||
| 15 | Mobilization | 1 | L.S. | $125,000.00 | $125,000.00 | $66,000.00 | $66,000.00 | $34,000.00 | $34,000.00 | ||||
| $1,142,519.20 | $1,144,790.00 | $1,147,858.05 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $1,155,000.00 | Contractor: | JB Holland Construction | Foley Construction Company | Merryman Excavation Inc. | |||||||||
| Funding Source: 40% Marine Fuel Tax, 30% F&W Trust-Fisheries Non-Habitat Stamp, 30% Federal-Boat Safety (Coast Guard), | 2092 HWY 9 West | 5401 Victoria Ave | 1501 Lamb Rd | ||||||||||
| Decorah IA 52101 | Davenport IA 52807 | Woodstock IL 60098 | |||||||||||
| Plan Sets Requested: 14 | Quantities | 563-382-2901 | 563-344-9333 | 815-337-1700 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Class "D" Revetment | 27279 | Tons | $31.00 | $845,649.00 | $30.25 | $825,189.75 | $31.09 | $848,104.11 | ||||
| 2 | Class "10" Excavation | 34450 | C.Y. | $0.75 | $25,837.50 | $1.80 | $62,010.00 | $2.95 | $101,627.50 | ||||
| 3 | Engineering Fabric | 33432 | S.Y. | $1.50 | $50,148.00 | $1.25 | $41,790.00 | $1.14 | $38,112.48 | ||||
| 4 | Class "A" Road Stone | 395 | Tons | $19.00 | $7,505.00 | $19.00 | $7,505.00 | $28.71 | $11,340.45 | ||||
| 5 | 3/8" Granular Surfacing | 584 | Tons | $15.00 | $8,760.00 | $21.00 | $12,264.00 | $28.87 | $16,860.08 | ||||
| 6 | Sheet Piling | 3255 | S.F. | $32.25 | $104,973.75 | $26.00 | $84,630.00 | $29.30 | $95,371.50 | ||||
| 7 | 3"x12" Bridge Planking | 388 | L.F. | $18.20 | $7,061.60 | $50.00 | $19,400.00 | $22.94 | $8,900.72 | ||||
| 8 | 2" Stone | 20 | Tons | $26.00 | $520.00 | $23.00 | $460.00 | $33.00 | $660.00 | ||||
| 9 | 6" Erosion Stone | 245 | Tons | $27.75 | $6,798.75 | $26.00 | $6,370.00 | $31.02 | $7,599.90 | ||||
| 10 | 3" Rock | 95 | Tons | $27.75 | $2,636.25 | $24.00 | $2,280.00 | $31.37 | $2,980.15 | ||||
| 11 | Sand | 110 | Tons | $22.50 | $2,475.00 | $24.00 | $2,640.00 | $25.14 | $2,765.40 | ||||
| 12 | Earthfill | 32395 | C.Y. | $2.24 | $72,564.80 | $2.00 | $64,790.00 | $2.85 | $92,325.75 | ||||
| 13 | Tree Structures | 3 | Each | $810.00 | $2,430.00 | $2,700.00 | $8,100.00 | $3,967.40 | $11,902.20 | ||||
| 14 | Debris Cleanup | 1 | L.S. | $250.00 | $250.00 | $2,000.00 | $2,000.00 | $3,777.71 | $3,777.71 | ||||
| 15 | Mobilization | 1 | L.S. | $15,000.00 | $15,000.00 | $40,000.00 | $40,000.00 | $17,012.05 | $17,012.05 | ||||
| $1,152,609.65 | $1,179,428.75 | $1,259,340.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $1,155,000.00 | Contractor: | Connolly Construction Inc | Brandt Construction Co. | Lester Construction Inc. | |||||||||
| Funding Source: 40% Marine Fuel Tax, 30% F&W Trust-Fisheries Non-Habitat Stamp, 30% Federal-Boat Safety (Coast Guard), | 18409 N Cascade Rd PO Box 68 | 700 4th St West | 127 1/2 - 31st Avenue | ||||||||||
| Peosta IA 52068 | Milan IL 61264 | Rock Island IL 61201 | |||||||||||
| Plan Sets Requested: 14 | Quantities | 563-876-3225 | 309-787-4644 | 309-314-6002 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Class "D" Revetment | 27279 | Tons | $31.01 | $845,921.79 | $27.15 | $740,624.85 | $34.00 | $927,486.00 | ||||
| 2 | Class "10" Excavation | 34450 | C.Y. | $2.50 | $86,125.00 | $4.60 | $158,470.00 | $4.65 | $160,192.50 | ||||
| 3 | Engineering Fabric | 33432 | S.Y. | $1.45 | $48,476.40 | $1.65 | $55,162.80 | $2.00 | $66,864.00 | ||||
| 4 | Class "A" Road Stone | 395 | Tons | $22.50 | $8,887.50 | $23.00 | $9,085.00 | $30.00 | $11,850.00 | ||||
| 5 | 3/8" Granular Surfacing | 584 | Tons | $20.00 | $11,680.00 | $27.00 | $15,768.00 | $30.00 | $17,520.00 | ||||
| 6 | Sheet Piling | 3255 | S.F. | $31.65 | $103,020.75 | $45.25 | $147,288.75 | $38.00 | $123,690.00 | ||||
| 7 | 3"x12" Bridge Planking | 388 | L.F. | $8.60 | $3,336.80 | $42.00 | $16,296.00 | $25.00 | $9,700.00 | ||||
| 8 | 2" Stone | 20 | Tons | $26.00 | $520.00 | $22.00 | $440.00 | $35.00 | $700.00 | ||||
| 9 | 6" Erosion Stone | 245 | Tons | $26.87 | $6,583.15 | $38.50 | $9,432.50 | $30.00 | $7,350.00 | ||||
| 10 | 3" Rock | 95 | Tons | $24.45 | $2,322.75 | $37.50 | $3,562.50 | $30.00 | $2,850.00 | ||||
| 11 | Sand | 110 | Tons | $24.30 | $2,673.00 | $37.35 | $4,108.50 | $28.00 | $3,080.00 | ||||
| 12 | Earthfill | 32395 | C.Y. | $3.00 | $97,185.00 | $3.00 | $97,185.00 | $4.80 | $155,496.00 | ||||
| 13 | Tree Structures | 3 | Each | $3,300.00 | $9,900.00 | $3,500.00 | $10,500.00 | $1,500.00 | $4,500.00 | ||||
| 14 | Debris Cleanup | 1 | L.S. | $8,800.00 | $8,800.00 | $8,100.00 | $8,100.00 | $20,000.00 | $20,000.00 | ||||
| 15 | Mobilization | 1 | L.S. | $40,500.00 | $40,500.00 | $70,500.00 | $70,500.00 | $30,000.00 | $30,000.00 | ||||
| $1,275,932.14 | $1,346,523.90 | $1,541,278.50 | |||||||||||