IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Gypsum City OHV Park | Date: 8/20/2026 | Project No. |
| ATV Bridge - REBID | County: | WEBSTER | Time: 11:00 AM | 23-02-94-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $350,000.00 | Contractor: | Dixon Construction | Peterson Contractors, Inc | ||||||||||
| Funding Source: 100% ATV Fund, | 1319 Hackberry St | 104 Blackhawk St PO Box A | |||||||||||
| Correctionville IA 51016 | Reinbeck IA 50669 | ||||||||||||
| Plan Sets Requested: 3 | Quantities | 712-372-4224 | 319-575-0796 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $40,000.00 | $40,000.00 | $30,500.00 | $30,500.00 | $0.00 | |||||
| 2 | Class 10 Excavation | 104 | C.Y. | $21.00 | $2,184.00 | $38.00 | $3,952.00 | $0.00 | |||||
| 3 | 100' x 8' Pratt-Truss Bridge | 1 | Each | $170,000.00 | $170,000.00 | $195,000.00 | $195,000.00 | $0.00 | |||||
| 4 | Bridge Headwall and Foundation | 2 | Each | $62,500.00 | $125,000.00 | $77,000.00 | $154,000.00 | $0.00 | |||||
| 5 | Construction Staking | 1 | L.S. | $3,000.00 | $3,000.00 | $5,000.00 | $5,000.00 | $0.00 | |||||
| 6 | Site Restoration | 1 | L.S. | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | $0.00 | |||||
| $345,184.00 | $398,452.00 | $0.00 | |||||||||||