 Bids For:  Location:   Banner Lakes At Summerset State Park  Date: 11/20/2025  Project No.  
  Banner Shooting Range Septic System  County:   WARREN  Time: 3:00 p.m.  26-05-91-01

 

 
1
2
3
Estimated Cost: $25,000.00
Contractor: 
VANS ExcavatingVanderpool Construction, IncVicker Drilling LLC
Funding Source: 100% REAP OS Acquisition & Development, 1521 Taylor Ave
1100 N 14th St
2151 Cherry Street Rd
Belmond IA  50421Indianola IA  50125Creston IA  50801
Plan Sets Requested: 0
Quantities
641-420-5052515-961-4682641-202-2728
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Septic System, Complete1L.S.$18,900.00$18,900.00 $19,500.00$19,500.00 $20,500.00$20,500.00 
      $18,900.00  $19,500.00  $20,500.00 
 
 
4
5
6
Estimated Cost: $25,000.00
Contractor: 
R Rogers LLCHaworth Land ConstructionBurt Dirt LLC
Funding Source: 100% REAP OS Acquisition & Development, 6288 NE 14th St
12981 Quaker St
64923 Lincoln Hwy
Des Moines IA  50313Indianola IA  50125Nevada IA  50201
Plan Sets Requested: 0
Quantities
515-282-0777515-249-4747515-822-8792
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Septic System, Complete1L.S.$20,577.00$20,577.00 $21,862.00$21,862.00 $22,000.00$22,000.00 
      $20,577.00  $21,862.00  $22,000.00 
 
7
8
9
Estimated Cost: $25,000.00
Contractor: 
Sterk Excavating IncSmith LandworxDenney Construction
Funding Source: 100% REAP OS Acquisition & Development, 1087 200th St

PO Box 28
1371 180th Ave
Pella IA  50219St Charles IA  50240Osceola IA  50213
Plan Sets Requested: 0
Quantities
641-416-0110515-240-4006641-414-1968
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Septic System, Complete1L.S.$23,000.00$23,000.00 $25,000.00$25,000.00 $25,416.00$25,416.00 
      $23,000.00  $25,000.00  $25,416.00 
 
 
10
11
12
Estimated Cost: $25,000.00
Contractor: 
JC Midwest Services
Funding Source: 100% REAP OS Acquisition & Development, 2233 Upland Ave


St Charles IA  50240    
Plan Sets Requested: 0
Quantities
515-478-4272
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Septic System, Complete1L.S.$30,892.12$30,892.12 $0.00 $0.00 
      $30,892.12  $0.00  $0.00 
 



 

12/5/2025