IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Manchester Fisheries Management Unit | Date: 1/8/2026 | Project No. |
| Hatchery storm damage repairs | County: | DELAWARE | Time: 3:00 PM | 26-03-28-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $73,000.00 | Contractor: | Matt Construction Inc | MZ Construction, Inc | ||||||||||
| Funding Source: 100% Executive Council, | 203 Y Ave | 285 N Center Street | |||||||||||
| Sumner IA 50674 | Livingston WI 53554 | ||||||||||||
| Plan Sets Requested: 0 | Quantities | 563-578-8418 | 608-341-0578 | ||||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $3,045.00 | $3,045.00 | $24,000.00 | $24,000.00 | $0.00 | |||||
| 2 | Demo Existing Building | 1 | L.S. | $1,015.00 | $1,015.00 | $4,000.00 | $4,000.00 | $0.00 | |||||
| 3 | New Pole Building | 1 | L.S. | $22,106.70 | $22,106.70 | $26,000.00 | $26,000.00 | $0.00 | |||||
| 4 | Remove and Replace Standing Seam Roof | 1500 | S.F. | $7.61 | $11,415.00 | $20.00 | $30,000.00 | $0.00 | |||||
| 5 | Remove and Replace Steel Facia | 50 | L.F. | $7.11 | $355.50 | $10.00 | $500.00 | $0.00 | |||||
| 6 | Remove and Replace Steel Roof Edging | 35 | L.F. | $10.15 | $355.25 | $10.00 | $350.00 | $0.00 | |||||
| $38,292.45 | $84,850.00 | $0.00 | |||||||||||
1/12/2026