IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Hawkeye Wildlife Management Area | Date: 11/20/2025 | Project No. |
| Swan Lake Road & James Avenue Road Maintenance Phase 3 | County: | JOHNSON | Time: 3:00 p.m. | 25-06-52-04 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | Boomerang Corp | Adam Laubenthal DBA Laubenthal Excavation | Triple B Construction | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 13225 Circle Drive Suite A | 1245 180th St | 710 Ayres Progress Drive | ||||||||||
| Anamosa IA 52205 | Bradgate IA 50520 | Wilton IA 52778 | |||||||||||
| Plan Sets Requested: 7 | Quantities | 319-462-4435 | 515-368-1112 | 563-732-3478 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $4,000.00 | $4,000.00 | $6,500.00 | $6,500.00 | $5,000.00 | $5,000.00 | ||||
| 2 | Traffic Control | 1 | L.S. | $2,200.00 | $2,200.00 | $2,000.00 | $2,000.00 | $1,000.00 | $1,000.00 | ||||
| 3 | Construction Staking | 1 | L.S. | $1,200.00 | $1,200.00 | $2,000.00 | $2,000.00 | $1,500.00 | $1,500.00 | ||||
| 4 | Reshaping Ditches | 175 | C.Y. | $6.00 | $1,050.00 | $11.43 | $2,000.25 | $23.00 | $4,025.00 | ||||
| 5 | Tree Removal | 2 | Each | $1,600.00 | $3,200.00 | $1,000.00 | $2,000.00 | $700.00 | $1,400.00 | ||||
| 6 | Remove Storm Sewer Pipe (36" Dia. or Less) | 130 | L.F. | $10.00 | $1,300.00 | $5.76 | $748.80 | $10.00 | $1,300.00 | ||||
| 7 | Remove Storm Sewer Pipe (greater Than 36") | 35 | L.F. | $10.00 | $350.00 | $5.71 | $199.85 | $12.00 | $420.00 | ||||
| 8 | Culvert, RCP Roadway, 18" | 32 | L.F. | $70.00 | $2,240.00 | $44.14 | $1,412.48 | $95.00 | $3,040.00 | ||||
| 9 | Apron, RCP, 18" | 2 | Each | $2,300.00 | $4,600.00 | $1,078.80 | $2,157.60 | $2,195.00 | $4,390.00 | ||||
| 10 | Culvert, RCP Roadway, 24" | 40 | L.F. | $80.00 | $3,200.00 | $69.06 | $2,762.40 | $115.00 | $4,600.00 | ||||
| 11 | Apron, RCP, 24" | 2 | Each | $2,500.00 | $5,000.00 | $1,401.20 | $2,802.40 | $2,675.00 | $5,350.00 | ||||
| 12 | Culvert, RCP Roadway, 30" | 60 | L.F. | $100.00 | $6,000.00 | $106.60 | $6,396.00 | $135.00 | $8,100.00 | ||||
| 13 | Apron, RCP, 30" | 4 | Each | $2,700.00 | $10,800.00 | $2,836.30 | $11,345.20 | $3,050.00 | $12,200.00 | ||||
| 14 | Culvert, RCP Roadway, 48" | 36 | L.F. | $120.00 | $4,320.00 | $263.97 | $9,502.92 | $220.00 | $7,920.00 | ||||
| 15 | Apron, RCP, 48" | 2 | Each | $4,200.00 | $8,400.00 | $4,759.50 | $9,519.00 | $4,900.00 | $9,800.00 | ||||
| 16 | Special Backfill | 103 | Tons | $26.00 | $2,678.00 | $25.00 | $2,575.00 | $35.00 | $3,605.00 | ||||
| 17 | Excavation, Class 10, Borrow Off-site | 260 | C.Y. | $20.00 | $5,200.00 | $40.00 | $10,400.00 | $12.00 | $3,120.00 | ||||
| 18 | Revetment, Class E | 308 | Tons | $50.00 | $15,400.00 | $50.00 | $15,400.00 | $65.00 | $20,020.00 | ||||
| 19 | Macadam Stone Base | 218 | Tons | $32.00 | $6,976.00 | $35.00 | $7,630.00 | $35.00 | $7,630.00 | ||||
| 20 | Granular Surfacing on Road, 1-1/2" Roadstone | 119 | Tons | $36.00 | $4,284.00 | $32.00 | $3,808.00 | $35.00 | $4,165.00 | ||||
| 21 | Road Signs | 8 | Each | $275.00 | $2,200.00 | $150.00 | $1,200.00 | $515.00 | $4,120.00 | ||||
| 22 | Site Restoration | 1 | L.S. | $1,402.00 | $1,402.00 | $6,000.00 | $6,000.00 | $4,500.00 | $4,500.00 | ||||
| $96,000.00 | $108,359.90 | $117,205.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | Connolly Construction Inc | Dave Schmitt Construction | Ground Line Company LLC | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 18409 N Cascade Rd | 4601 J St SW | 4782 County Rd E17 | ||||||||||
| Peosta IA 52068 | Cedar Rapids IA 52404 | Onslow IA 52321 | |||||||||||
| Plan Sets Requested: 7 | Quantities | 563-876-3225 | 319-365-8669 | 319-251-0425 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $8,500.00 | $8,500.00 | $6,500.00 | $6,500.00 | $12,000.00 | $12,000.00 | ||||
| 2 | Traffic Control | 1 | L.S. | $3,200.00 | $3,200.00 | $2,200.00 | $2,200.00 | $2,000.00 | $2,000.00 | ||||
| 3 | Construction Staking | 1 | L.S. | $1,000.00 | $1,000.00 | $3,900.00 | $3,900.00 | $500.00 | $500.00 | ||||
| 4 | Reshaping Ditches | 175 | C.Y. | $10.00 | $1,750.00 | $22.00 | $3,850.00 | $28.00 | $4,900.00 | ||||
| 5 | Tree Removal | 2 | Each | $600.00 | $1,200.00 | $540.00 | $1,080.00 | $600.00 | $1,200.00 | ||||
| 6 | Remove Storm Sewer Pipe (36" Dia. or Less) | 130 | L.F. | $16.00 | $2,080.00 | $17.25 | $2,242.50 | $35.00 | $4,550.00 | ||||
| 7 | Remove Storm Sewer Pipe (greater Than 36") | 35 | L.F. | $24.00 | $840.00 | $33.00 | $1,155.00 | $50.00 | $1,750.00 | ||||
| 8 | Culvert, RCP Roadway, 18" | 32 | L.F. | $94.00 | $3,008.00 | $100.00 | $3,200.00 | $130.00 | $4,160.00 | ||||
| 9 | Apron, RCP, 18" | 2 | Each | $2,075.00 | $4,150.00 | $1,340.00 | $2,680.00 | $1,200.00 | $2,400.00 | ||||
| 10 | Culvert, RCP Roadway, 24" | 40 | L.F. | $112.85 | $4,514.00 | $119.00 | $4,760.00 | $160.00 | $6,400.00 | ||||
| 11 | Apron, RCP, 24" | 2 | Each | $2,500.00 | $5,000.00 | $2,025.00 | $4,050.00 | $2,700.00 | $5,400.00 | ||||
| 12 | Culvert, RCP Roadway, 30" | 60 | L.F. | $126.00 | $7,560.00 | $154.00 | $9,240.00 | $180.00 | $10,800.00 | ||||
| 13 | Apron, RCP, 30" | 4 | Each | $3,000.00 | $12,000.00 | $2,300.00 | $9,200.00 | $3,300.00 | $13,200.00 | ||||
| 14 | Culvert, RCP Roadway, 48" | 36 | L.F. | $225.00 | $8,100.00 | $261.00 | $9,396.00 | $330.00 | $11,880.00 | ||||
| 15 | Apron, RCP, 48" | 2 | Each | $4,865.00 | $9,730.00 | $5,070.00 | $10,140.00 | $4,800.00 | $9,600.00 | ||||
| 16 | Special Backfill | 103 | Tons | $37.25 | $3,836.75 | $25.00 | $2,575.00 | $50.00 | $5,150.00 | ||||
| 17 | Excavation, Class 10, Borrow Off-site | 260 | C.Y. | $20.75 | $5,395.00 | $38.75 | $10,075.00 | $28.00 | $7,280.00 | ||||
| 18 | Revetment, Class E | 308 | Tons | $58.25 | $17,941.00 | $72.56 | $22,348.48 | $60.00 | $18,480.00 | ||||
| 19 | Macadam Stone Base | 218 | Tons | $44.25 | $9,646.50 | $43.15 | $9,406.70 | $48.00 | $10,464.00 | ||||
| 20 | Granular Surfacing on Road, 1-1/2" Roadstone | 119 | Tons | $35.35 | $4,206.65 | $42.50 | $5,057.50 | $36.00 | $4,284.00 | ||||
| 21 | Road Signs | 8 | Each | $325.00 | $2,600.00 | $185.00 | $1,480.00 | $300.00 | $2,400.00 | ||||
| 22 | Site Restoration | 1 | L.S. | $7,750.00 | $7,750.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | ||||
| $124,007.90 | $127,536.18 | $141,798.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $140,000.00 | Contractor: | Eastern Iowa Excavating & Concrete, LLC | DeLong Construction, Inc | H Johnson Services LLC | |||||||||
| Funding Source: 100% Park & Institutional Road Fund, | 121 Nixon St SE | PO Box 488 | 1943 180th St | ||||||||||
| Cascade IA 52033 | Washington IA 52353 | Creston IA 50801 | |||||||||||
| Plan Sets Requested: 7 | Quantities | 563-852-5120 | 319-653-3334 | 515-681-2224 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Mobilization | 1 | L.S. | $11,500.00 | $11,500.00 | $6,500.00 | $6,500.00 | $26,000.00 | $26,000.00 | ||||
| 2 | Traffic Control | 1 | L.S. | $2,500.00 | $2,500.00 | $3,500.00 | $3,500.00 | $10,000.00 | $10,000.00 | ||||
| 3 | Construction Staking | 1 | L.S. | $1,850.00 | $1,850.00 | $5,000.00 | $5,000.00 | $10,000.00 | $10,000.00 | ||||
| 4 | Reshaping Ditches | 175 | C.Y. | $25.50 | $4,462.50 | $70.00 | $12,250.00 | $50.00 | $8,750.00 | ||||
| 5 | Tree Removal | 2 | Each | $2,000.00 | $4,000.00 | $1,300.00 | $2,600.00 | $5,000.00 | $10,000.00 | ||||
| 6 | Remove Storm Sewer Pipe (36" Dia. or Less) | 130 | L.F. | $25.00 | $3,250.00 | $20.00 | $2,600.00 | $25.00 | $3,250.00 | ||||
| 7 | Remove Storm Sewer Pipe (greater Than 36") | 35 | L.F. | $29.00 | $1,015.00 | $30.00 | $1,050.00 | $100.00 | $3,500.00 | ||||
| 8 | Culvert, RCP Roadway, 18" | 32 | L.F. | $95.50 | $3,056.00 | $95.00 | $3,040.00 | $150.00 | $4,800.00 | ||||
| 9 | Apron, RCP, 18" | 2 | Each | $1,055.00 | $2,110.00 | $1,200.00 | $2,400.00 | $1,500.00 | $3,000.00 | ||||
| 10 | Culvert, RCP Roadway, 24" | 40 | L.F. | $131.50 | $5,260.00 | $110.00 | $4,400.00 | $200.00 | $8,000.00 | ||||
| 11 | Apron, RCP, 24" | 2 | Each | $2,525.00 | $5,050.00 | $2,600.00 | $5,200.00 | $3,000.00 | $6,000.00 | ||||
| 12 | Culvert, RCP Roadway, 30" | 60 | L.F. | $189.25 | $11,355.00 | $150.00 | $9,000.00 | $250.00 | $15,000.00 | ||||
| 13 | Apron, RCP, 30" | 4 | Each | $2,800.00 | $11,200.00 | $2,700.00 | $10,800.00 | $2,000.00 | $8,000.00 | ||||
| 14 | Culvert, RCP Roadway, 48" | 36 | L.F. | $360.00 | $12,960.00 | $290.00 | $10,440.00 | $400.00 | $14,400.00 | ||||
| 15 | Apron, RCP, 48" | 2 | Each | $4,450.00 | $8,900.00 | $5,000.00 | $10,000.00 | $4,000.00 | $8,000.00 | ||||
| 16 | Special Backfill | 103 | Tons | $36.00 | $3,708.00 | $50.00 | $5,150.00 | $55.00 | $5,665.00 | ||||
| 17 | Excavation, Class 10, Borrow Off-site | 260 | C.Y. | $38.85 | $10,101.00 | $28.00 | $7,280.00 | $50.00 | $13,000.00 | ||||
| 18 | Revetment, Class E | 308 | Tons | $68.85 | $21,205.80 | $70.00 | $21,560.00 | $85.00 | $26,180.00 | ||||
| 19 | Macadam Stone Base | 218 | Tons | $39.50 | $8,611.00 | $46.00 | $10,028.00 | $70.00 | $15,260.00 | ||||
| 20 | Granular Surfacing on Road, 1-1/2" Roadstone | 119 | Tons | $48.50 | $5,771.50 | $45.00 | $5,355.00 | $70.00 | $8,330.00 | ||||
| 21 | Road Signs | 8 | Each | $310.00 | $2,480.00 | $600.00 | $4,800.00 | $1,000.00 | $8,000.00 | ||||
| 22 | Site Restoration | 1 | L.S. | $5,500.00 | $5,500.00 | $10,000.00 | $10,000.00 | $5,000.00 | $5,000.00 | ||||
| $145,845.80 | $152,953.00 | $220,135.00 | |||||||||||
12/5/2025