IOWA DEPARTMENT OF NATURAL RESOURCES |
|
| Bids For: | Location: | Union Grove | Date: 2/12/2026 | Project No. |
| House Foundation Removal | County: | TAMA | Time: 3:00 p.m. | 26-05-86-01 |
1 | 2 | 3 | |||||||||||
| Estimated Cost: $20,000.00 | Contractor: | Bears Bulldozing/Excavating | Matt Construction Inc | Rohach Excavating LLC | |||||||||
| Funding Source: 100% Other, | 1887 J Ave | 203 Y Ave | 2438 Highway E64 | ||||||||||
| Traer IA 50675 | Sumner IA 50674 | Tama IA 52339 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-485-5872 | 563-578-8418 | 641-691-5664 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Complete Scope of Work | 1 | L.S. | $3,525.00 | $3,525.00 | $14,365.00 | $14,365.00 | $14,500.00 | $14,500.00 | ||||
| $3,525.00 | $14,365.00 | $14,500.00 | |||||||||||
4 | 5 | 6 | |||||||||||
| Estimated Cost: $20,000.00 | Contractor: | Kupka Excavating & Trucking LLC | Hudson Hardware Plumbing & Heating | Dig It Land Improvements LLC | |||||||||
| Funding Source: 100% Other, | 3108 S Ave | 585 Dale Drive | 24485 242nd St | ||||||||||
| Chelsea IA 52215 | Hudson IA 50643 | Eldora IA 50627 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 641-485-4231 | 319-988-3231 | 641-373-1573 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Complete Scope of Work | 1 | L.S. | $15,495.00 | $15,495.00 | $16,012.50 | $16,012.50 | $17,677.00 | $17,677.00 | ||||
| $15,495.00 | $16,012.50 | $17,677.00 | |||||||||||
7 | 8 | 9 | |||||||||||
| Estimated Cost: $20,000.00 | Contractor: | Hatch Grading & Contracting Inc | Heritage Land Solutions | Schares Landscaping LLC | |||||||||
| Funding Source: 100% Other, | 801 Hwy 21 Box 157 | 302 Broad St | 7501 Poyner Rd | ||||||||||
| Dysart IA 52224 | Story City IA 50248 | Jesup IA 50648 | |||||||||||
| Plan Sets Requested: 0 | Quantities | 319-476-2626 | 515-520-8146 | 319-830-7052 | |||||||||
| No. | Description: | No. | Unit | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | ||||
| 1 | Complete Scope of Work | 1 | L.S. | $21,095.40 | $21,095.40 | $22,050.00 | $22,050.00 | $23,272.00 | $23,272.00 | ||||
| $21,095.40 | $22,050.00 | $23,272.00 | |||||||||||
2/18/2026