 Bids For:  Location:   Big Creek Beach  Date: 9/17/2026  Project No.  
  Watershed BMPs  County:   POLK  Time: 11:00 a.m.  26-02-77-02

 

 
1
2
3
Estimated Cost: $672,000.00
Contractor: 
Southeast Constructors IncPirc-Tobin Construction IncRW Excavating Solutions LC
Funding Source: 100% Lake Restoration, 3018 Fox Run
2650 Old Quaas Rd
13293 S 88th Ave W
Des Moines IA  50321Alburnett IA  52202Prairie City IA  50228
Plan Sets Requested: 3
Quantities
754-234-9944319-842-2130515-994-2648
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clearing and Grubbing1L.S.$2,500.00$2,500.00 $7,300.00$7,300.00 $4,000.00$4,000.00 
2Topsoil, On-Site810C.Y.$7.50$6,075.00 $11.50$9,315.00 $8.00$6,480.00 
3Excavation, Class 10, Rough Grading820C.Y.$16.00$13,120.00 $30.00$24,600.00 $7.00$5,740.00 
4Subgrade Preparation1203S.Y.$5.00$6,015.00 $5.00$6,015.00 $5.00$6,015.00 
5Subbase, Modified, 6"868S.Y.$15.00$13,020.00 $17.50$15,190.00 $15.00$13,020.00 
6Removal of Known Trench Drain1L.S.$250.00$250.00 $1,200.00$1,200.00 $1,000.00$1,000.00 
7Storm Sewer, Trenched, PVC, 6"113L.F.$18.00$2,034.00 $45.00$5,085.00 $35.00$3,955.00 
8Storm Sewer, Trenched, PVC, 12"1347L.F.$33.00$44,451.00 $60.00$80,820.00 $38.00$51,186.00 
9Storm Sewer, Trenched, RCP, 12"199L.F.$90.00$17,910.00 $75.00$14,925.00 $45.00$8,955.00 
10Flared End Section, RCP, 12"1Each$600.00$600.00 $3,300.00$3,300.00 $2,500.00$2,500.00 
11Water Main Adjustment1Each$250.00$250.00 $1,000.00$1,000.00 $16,500.00$16,500.00 
12Manhole, SW-401, 48"6Each$8,500.00$51,000.00 $4,000.00$24,000.00 $8,500.00$51,000.00 
13Intake, SW-512, 18"5Each$5,250.00$26,250.00 $2,000.00$10,000.00 $3,800.00$19,000.00 
14Intake, Cleanout6Each$750.00$4,500.00 $1,200.00$7,200.00 $1,500.00$9,000.00 
15Building Roof Drainage, Gutters, Downspouts, and Facia6Each$4,800.00$28,800.00 $2,350.00$14,100.00 $1,300.00$7,800.00 
16Removal of Sidewalk335S.Y.$9.00$3,015.00 $15.00$5,025.00 $25.00$8,375.00 
17Removal of Asphalt Trail620S.Y.$9.00$5,580.00 $8.00$4,960.00 $16.00$9,920.00 
18Sidewalk, PCC, 5"335S.Y.$85.00$28,475.00 $65.00$21,775.00 $100.00$33,500.00 
19PCC Trail, 6"620S.Y.$90.00$55,800.00 $70.00$43,400.00 $120.00$74,400.00 
20Seeding, Fertilizing, and Mulching1Acres$2,500.00$2,500.00 $4,500.00$4,500.00 $8,000.00$8,000.00 
21SWPPP Administration1L.S.$1,000.00$1,000.00 $1,000.00$1,000.00 $4,500.00$4,500.00 
22Wattle810L.F.$1.75$1,417.50 $3.00$2,430.00 $3.00$2,430.00 
23Intake Protection6Each$150.00$900.00 $100.00$600.00 $200.00$1,200.00 
24Riprap, Class E50Tons$70.00$3,500.00 $80.00$4,000.00 $84.00$4,200.00 
25Mobilization1L.S.$15,000.00$15,000.00 $17,500.00$17,500.00 $30,000.00$30,000.00 
26Clearing and Grubbing1L.S.$1,500.00$1,500.00 $4,500.00$4,500.00 $5,000.00$5,000.00 
27Topsoil, On-Site1075C.Y.$7.50$8,062.50 $16.50$17,737.50 $8.00$8,600.00 
28Excavation, Class 10, Rough Grading5412C.Y.$6.00$32,472.00 $14.00$75,768.00 $8.00$43,296.00 
29Removal of 15" RCP FES1Each$450.00$450.00 $350.00$350.00 $400.00$400.00 
30Removal of 15" RCP 60L.F.$10.00$600.00 $20.00$1,200.00 $20.00$1,200.00 
31Storm Sewer, Trenched, RCP, 15"81L.F.$110.00$8,910.00 $65.00$5,265.00 $55.00$4,455.00 
32Storm Sewer, Trenched, RCP, 24"24L.F.$140.00$3,360.00 $97.50$2,340.00 $100.00$2,400.00 
33Flared End Section, RCP, 15" With Orifice Plate1Each$1,200.00$1,200.00 $2,200.00$2,200.00 $3,200.00$3,200.00 
34Flared End Section, RCP, 24"1Each$1,500.00$1,500.00 $1,800.00$1,800.00 $3,500.00$3,500.00 
35Manhole, SW-401, 48"1Each$4,500.00$4,500.00 $5,000.00$5,000.00 $6,000.00$6,000.00 
36Manhole, SW-513, 36" x 36"1Each$4,800.00$4,800.00 $5,700.00$5,700.00 $9,500.00$9,500.00 
37Intake Adjustment, Minor SW-5111Each$200.00$200.00 $3,500.00$3,500.00 $1,500.00$1,500.00 
38PCC Pavement, 6"128S.Y.$90.00$11,520.00 $90.00$11,520.00 $120.00$15,360.00 
39Pavement Removal128S.Y.$9.00$1,152.00 $15.00$1,920.00 $25.00$3,200.00 
40Seeding, Fertilizing, and Mulching1.4Acres$3,000.00$4,200.00 $5,000.00$7,000.00 $8,000.00$11,200.00 
41Erosion Control Items1L.S.$750.00$750.00 $750.00$750.00 $3,000.00$3,000.00 
42SWPPP Administration1L.S.$1,500.00$1,500.00 $1,000.00$1,000.00 $4,500.00$4,500.00 
43Riprap, Class E280Tons$70.00$19,600.00 $80.00$22,400.00 $84.00$23,520.00 
44Mobilization1L.S.$40,000.00$40,000.00 $17,500.00$17,500.00 $30,000.00$30,000.00 
      $480,239.00  $516,690.50  $562,507.00 
 
4
5
6
Estimated Cost: $672,000.00
Contractor: 
Iowa Earth WorksCon-Struct IncSteele Excavating Inc
Funding Source: 100% Lake Restoration, 300 Snyder Dr
305 S Dayton Ave
503 N 5th St
Huxley IA  50124Ames IA  50010Montezuma IA  50171
Plan Sets Requested: 3
Quantities
515-290-3438515-232-6443641-891-3471
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clearing and Grubbing1L.S.$6,500.00$6,500.00 $14,000.00$14,000.00 $15,000.00$15,000.00 
2Topsoil, On-Site810C.Y.$10.00$8,100.00 $14.00$11,340.00 $10.00$8,100.00 
3Excavation, Class 10, Rough Grading820C.Y.$15.00$12,300.00 $16.00$13,120.00 $20.00$16,400.00 
4Subgrade Preparation1203S.Y.$3.50$4,210.50 $3.00$3,609.00 $3.50$4,210.50 
5Subbase, Modified, 6"868S.Y.$12.00$10,416.00 $17.00$14,756.00 $12.00$10,416.00 
6Removal of Known Trench Drain1L.S.$900.00$900.00 $4,300.00$4,300.00 $500.00$500.00 
7Storm Sewer, Trenched, PVC, 6"113L.F.$108.00$12,204.00 $47.00$5,311.00 $55.00$6,215.00 
8Storm Sewer, Trenched, PVC, 12"1347L.F.$76.00$102,372.00 $68.00$91,596.00 $60.00$80,820.00 
9Storm Sewer, Trenched, RCP, 12"199L.F.$75.00$14,925.00 $77.00$15,323.00 $75.00$14,925.00 
10Flared End Section, RCP, 12"1Each$4,000.00$4,000.00 $2,575.00$2,575.00 $2,450.00$2,450.00 
11Water Main Adjustment1Each$11,000.00$11,000.00 $9,064.00$9,064.00 $10,000.00$10,000.00 
12Manhole, SW-401, 48"6Each$3,850.00$23,100.00 $5,459.00$32,754.00 $7,500.00$45,000.00 
13Intake, SW-512, 18"5Each$3,700.00$18,500.00 $1,957.00$9,785.00 $2,000.00$10,000.00 
14Intake, Cleanout6Each$1,150.00$6,900.00 $2,369.00$14,214.00 $2,250.00$13,500.00 
15Building Roof Drainage, Gutters, Downspouts, and Facia6Each$4,200.00$25,200.00 $1,959.00$11,754.00 $6,000.00$36,000.00 
16Removal of Sidewalk335S.Y.$15.00$5,025.00 $23.00$7,705.00 $10.00$3,350.00 
17Removal of Asphalt Trail620S.Y.$15.00$9,300.00 $20.00$12,400.00 $10.00$6,200.00 
18Sidewalk, PCC, 5"335S.Y.$58.00$19,430.00 $45.00$15,075.00 $70.00$23,450.00 
19PCC Trail, 6"620S.Y.$60.00$37,200.00 $49.00$30,380.00 $72.00$44,640.00 
20Seeding, Fertilizing, and Mulching1Acres$6,000.00$6,000.00 $4,120.00$4,120.00 $6,600.00$6,600.00 
21SWPPP Administration1L.S.$2,900.00$2,900.00 $4,635.00$4,635.00 $3,300.00$3,300.00 
22Wattle810L.F.$2.75$2,227.50 $2.25$1,822.50 $2.25$1,822.50 
23Intake Protection6Each$150.00$900.00 $129.00$774.00 $220.00$1,320.00 
24Riprap, Class E50Tons$80.00$4,000.00 $76.00$3,800.00 $85.00$4,250.00 
25Mobilization1L.S.$35,000.00$35,000.00 $23,500.00$23,500.00 $13,000.00$13,000.00 
26Clearing and Grubbing1L.S.$4,000.00$4,000.00 $6,500.00$6,500.00 $15,000.00$15,000.00 
27Topsoil, On-Site1075C.Y.$10.00$10,750.00 $16.00$17,200.00 $10.00$10,750.00 
28Excavation, Class 10, Rough Grading5412C.Y.$15.00$81,180.00 $29.00$156,948.00 $20.00$108,240.00 
29Removal of 15" RCP FES1Each$900.00$900.00 $600.00$600.00 $3,000.00$3,000.00 
30Removal of 15" RCP 60L.F.$50.00$3,000.00 $58.00$3,480.00 $20.00$1,200.00 
31Storm Sewer, Trenched, RCP, 15"81L.F.$140.00$11,340.00 $82.00$6,642.00 $100.00$8,100.00 
32Storm Sewer, Trenched, RCP, 24"24L.F.$150.00$3,600.00 $136.00$3,264.00 $100.00$2,400.00 
33Flared End Section, RCP, 15" With Orifice Plate1Each$3,750.00$3,750.00 $3,708.00$3,708.00 $4,500.00$4,500.00 
34Flared End Section, RCP, 24"1Each$3,095.00$3,095.00 $2,987.00$2,987.00 $3,500.00$3,500.00 
35Manhole, SW-401, 48"1Each$8,000.00$8,000.00 $6,386.00$6,386.00 $7,500.00$7,500.00 
36Manhole, SW-513, 36" x 36"1Each$6,500.00$6,500.00 $5,665.00$5,665.00 $8,500.00$8,500.00 
37Intake Adjustment, Minor SW-5111Each$1,600.00$1,600.00 $979.00$979.00 $3,500.00$3,500.00 
38PCC Pavement, 6"128S.Y.$74.00$9,472.00 $61.00$7,808.00 $93.00$11,904.00 
39Pavement Removal128S.Y.$15.00$1,920.00 $32.00$4,096.00 $15.00$1,920.00 
40Seeding, Fertilizing, and Mulching1.4Acres$5,400.00$7,560.00 $4,120.00$5,768.00 $6,600.00$9,240.00 
41Erosion Control Items1L.S.$2,600.00$2,600.00 $1,081.50$1,081.50 $1,750.00$1,750.00 
42SWPPP Administration1L.S.$2,000.00$2,000.00 $618.00$618.00 $3,300.00$3,300.00 
43Riprap, Class E280Tons$80.00$22,400.00 $76.00$21,280.00 $85.00$23,800.00 
44Mobilization1L.S.$55,000.00$55,000.00 $11,500.00$11,500.00 $15,000.00$15,000.00 
      $621,277.00  $624,223.00  $624,573.00 
 
7
8
9
Estimated Cost: $672,000.00
Contractor: 
On Track Construction, LLCTK Concrete, IncReilly Construction Co Inc
Funding Source: 100% Lake Restoration, 1435 West F Ave

PO Box 111

PO Box 99
Nevada IA  50201Pella IA  50219Ossian IA  52161
Plan Sets Requested: 3
Quantities
888-850-0208641-628-4590563-532-9211
No.Description:No.UnitUnit Price AmountUnit Price AmountUnit Price Amount
1Clearing and Grubbing1L.S.$6,500.00$6,500.00 $10,000.00$10,000.00 $7,500.00$7,500.00 
2Topsoil, On-Site810C.Y.$8.00$6,480.00 $10.00$8,100.00 $20.00$16,200.00 
3Excavation, Class 10, Rough Grading820C.Y.$31.00$25,420.00 $15.00$12,300.00 $20.00$16,400.00 
4Subgrade Preparation1203S.Y.$3.00$3,609.00 $4.00$4,812.00 $5.00$6,015.00 
5Subbase, Modified, 6"868S.Y.$14.50$12,586.00 $14.50$12,586.00 $18.00$15,624.00 
6Removal of Known Trench Drain1L.S.$900.00$900.00 $2,500.00$2,500.00 $1,500.00$1,500.00 
7Storm Sewer, Trenched, PVC, 6"113L.F.$108.00$12,204.00 $40.00$4,520.00 $50.00$5,650.00 
8Storm Sewer, Trenched, PVC, 12"1347L.F.$76.00$102,372.00 $62.00$83,514.00 $70.00$94,290.00 
9Storm Sewer, Trenched, RCP, 12"199L.F.$75.00$14,925.00 $85.00$16,915.00 $80.00$15,920.00 
10Flared End Section, RCP, 12"1Each$4,000.00$4,000.00 $3,500.00$3,500.00 $2,000.00$2,000.00 
11Water Main Adjustment1Each$11,000.00$11,000.00 $8,500.00$8,500.00 $9,500.00$9,500.00 
12Manhole, SW-401, 48"6Each$3,650.00$21,900.00 $5,000.00$30,000.00 $4,250.00$25,500.00 
13Intake, SW-512, 18"5Each$3,700.00$18,500.00 $3,000.00$15,000.00 $2,150.00$10,750.00 
14Intake, Cleanout6Each$1,150.00$6,900.00 $2,500.00$15,000.00 $1,200.00$7,200.00 
15Building Roof Drainage, Gutters, Downspouts, and Facia6Each$4,200.00$25,200.00 $7,500.00$45,000.00 $5,000.00$30,000.00 
16Removal of Sidewalk335S.Y.$7.00$2,345.00 $12.00$4,020.00 $20.00$6,700.00 
17Removal of Asphalt Trail620S.Y.$7.00$4,340.00 $10.00$6,200.00 $20.00$12,400.00 
18Sidewalk, PCC, 5"335S.Y.$62.00$20,770.00 $65.00$21,775.00 $60.00$20,100.00 
19PCC Trail, 6"620S.Y.$63.75$39,525.00 $65.00$40,300.00 $63.00$39,060.00 
20Seeding, Fertilizing, and Mulching1Acres$4,000.00$4,000.00 $5,500.00$5,500.00 $4,200.00$4,200.00 
21SWPPP Administration1L.S.$4,500.00$4,500.00 $3,000.00$3,000.00 $5,000.00$5,000.00 
22Wattle810L.F.$2.00$1,620.00 $4.00$3,240.00 $2.00$1,620.00 
23Intake Protection6Each$125.00$750.00 $150.00$900.00 $125.00$750.00 
24Riprap, Class E50Tons$90.00$4,500.00 $85.00$4,250.00 $85.00$4,250.00 
25Mobilization1L.S.$21,000.00$21,000.00 $37,500.00$37,500.00 $20,000.00$20,000.00 
26Clearing and Grubbing1L.S.$5,000.00$5,000.00 $7,500.00$7,500.00 $5,000.00$5,000.00 
27Topsoil, On-Site1075C.Y.$8.00$8,600.00 $10.00$10,750.00 $20.00$21,500.00 
28Excavation, Class 10, Rough Grading5412C.Y.$25.00$135,300.00 $17.50$94,710.00 $25.00$135,300.00 
29Removal of 15" RCP FES1Each$900.00$900.00 $1,500.00$1,500.00 $750.00$750.00 
30Removal of 15" RCP 60L.F.$50.00$3,000.00 $25.00$1,500.00 $25.00$1,500.00 
31Storm Sewer, Trenched, RCP, 15"81L.F.$140.00$11,340.00 $85.00$6,885.00 $95.00$7,695.00 
32Storm Sewer, Trenched, RCP, 24"24L.F.$150.00$3,600.00 $125.00$3,000.00 $135.00$3,240.00 
33Flared End Section, RCP, 15" With Orifice Plate1Each$3,250.00$3,250.00 $5,000.00$5,000.00 $2,850.00$2,850.00 
34Flared End Section, RCP, 24"1Each$3,095.00$3,095.00 $5,000.00$5,000.00 $2,350.00$2,350.00 
35Manhole, SW-401, 48"1Each$8,000.00$8,000.00 $4,000.00$4,000.00 $4,250.00$4,250.00 
36Manhole, SW-513, 36" x 36"1Each$6,500.00$6,500.00 $5,000.00$5,000.00 $6,000.00$6,000.00 
37Intake Adjustment, Minor SW-5111Each$1,600.00$1,600.00 $2,750.00$2,750.00 $1,700.00$1,700.00 
38PCC Pavement, 6"128S.Y.$75.00$9,600.00 $70.00$8,960.00 $78.00$9,984.00 
39Pavement Removal128S.Y.$14.00$1,792.00 $15.00$1,920.00 $20.00$2,560.00 
40Seeding, Fertilizing, and Mulching1.4Acres$4,200.00$5,880.00 $5,500.00$7,700.00 $4,200.00$5,880.00 
41Erosion Control Items1L.S.$1,050.00$1,050.00 $1,575.00$1,575.00 $1,250.00$1,250.00 
42SWPPP Administration1L.S.$605.00$605.00 $3,000.00$3,000.00 $1,000.00$1,000.00 
43Riprap, Class E280Tons$90.00$25,200.00 $85.00$23,800.00 $85.00$23,800.00 
44Mobilization1L.S.$16,500.00$16,500.00 $37,500.00$37,500.00 $20,000.00$20,000.00 
      $626,658.00  $630,982.00  $634,738.00 
 



 

9/18/2026